Impresa S.p.A.

Bulgaria
Sections
3
Length
54 km
Median slip
+4 mo
Median overrun
–

Slip measured on 2 of 3 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Struma – 1 Consortium
  • Struma-Lot 2 Consortium

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A3 Struma Motorway / Dolna Dikanya – Dupnitsa NorthBulgariaOpened14 kmJul 2013−2 mo
A3 Struma Motorway / Dupnitsa North – km 322 (end of Lot 1)BulgariaOpened3 kmOct 2015–
A3 Struma Motorway / Dupnitsa – BlagoevgradBulgariaOpened37 kmOct 2015+10 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.