Impresa S.p.A.
Bulgaria
- Sections
- 3
- Length
- 54 km
- Median slip
- +4 mo
- Median overrun
- –
Slip measured on 2 of 3 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Struma – 1 Consortium
- Struma-Lot 2 Consortium
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A3 Struma Motorway / Dolna Dikanya – Dupnitsa North | Bulgaria | Opened | 14 km | Jul 2013 | −2 mo |
| A3 Struma Motorway / Dupnitsa North – km 322 (end of Lot 1) | Bulgaria | Opened | 3 km | Oct 2015 | – |
| A3 Struma Motorway / Dupnitsa – Blagoevgrad | Bulgaria | Opened | 37 km | Oct 2015 | +10 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.