Консорциум „АМ Струма тунел 2018“
Bulgaria
Name variants are not merged
Unregistered spelling
- Sections
- 1
- Length
- 13 km
- Median slip
- +56 mo
- Median overrun
- –
Slip measured on 1 of 1 sections built.
No section this firm built records both an estimate and a final cost.
Too few sections to rank. The figures below describe the work; they are not a track record.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A3 Struma Motorway / Blagoevgrad – Krupnik | Bulgaria | Opened | 13 km | Feb 2024 | +56 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.