Skip to content
InfraWorldWide
All contractors

Trakia IV consortium

Bulgaria

Name variants are not merged

Unregistered spelling

Sections
1
Length
49 km
Median slip
Median overrun

No section this firm built records both a contracted duration and a delivery date, so there is no slip to report.

No section this firm built records both an estimate and a final cost.

Too few sections to rank. The figures below describe the work; they are not a track record.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Sections built

SectionCountryStatusLengthOpenedSlip
A1 Trakia Motorway / Yambol – KarnobatBulgariaOpened49 kmJul 2013

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.