Highways

Podgorica Western Bypass

Four-lane urban bypass between Donja Gorica and Komanski most.

Total length
3 km
Open today
0 km
Sections
1
Loading map data…

Sections

Sections of Podgorica Western Bypass: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Donja Gorica–Komanski most

The Transport Administration gives an approximate length of 3 km and a construction period of 550 calendar days from site handover. The length is recorded as stated; the drawn OSM alignment is about 2.85 km. Contract value omitted because the cited source does not state the VAT basis.

Tendered3 km
  1. Aug 28, 2026Tender awarded
––
  • Euromont stil–Toškovići JVBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Related projects

Sources

  1. Government of Montenegro: contract signed for the Podgorica Western Bypassread Oct 12, 2026
  2. OpenStreetMap contributors: proposed Zapadna obilaznica alignment near Podgoricaread Oct 12, 2026

Figures last checked against their sources in Oct 12, 2026.