← All contractors
China Communications Construction Company Ltd.
Serbia
- Sections
- 5
- Length
- 191 km
- Median slip
- +8 mo
- Median overrun
- –
Slip measured on 2 of 5 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A2 Miloš Veliki Motorway (Belgrade – Požega) / Surčin – Obrenovac | Serbia | Opened | 18 km | Dec 2019 | – |
| A2 Miloš Veliki Motorway (Belgrade – Požega) / Preljina – Pakovraće | Serbia | Opened | 11 km | Jan 2022 | – |
| A2 Miloš Veliki Motorway (Belgrade – Požega) / Pakovraće – Požega | Serbia | Opened | 20 km | Jul 2025 | – |
| Belgrade – Novi Sad – Subotica High-Speed Railway / Belgrade Centre – Stara Pazova | Serbia | Opened | 35 km | Mar 2022 | +9 mo |
| Belgrade – Novi Sad – Subotica High-Speed Railway / Novi Sad – Subotica – Kelebija border | Serbia | Opened | 108 km | Oct 2025 | +6 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.