A2 Miloš Veliki Motorway (Belgrade – Požega)

The A2 «Miloš Veliki» motorway on European route E763, running south-west from Belgrade at Surčin through Obrenovac, Ub, Lajkovac and Ljig to Preljina near Čačak, then west through Lučani to Požega, opened section by section between 2016 and 2025. Section lengths here are the figures published by JP Putevi Srbije and the ministry rather than measurements off the mapped alignment: the Lajkovac–Ljig contract boundary sits about 3 km from the Ljig interchange used to cut the geometry, though the Lajkovac–Preljina total agrees to within 600 m. The 7.9 km Novi Beograd – Surčin road that links the city to the motorway (opened 1 April 2023) is a state road designed for 80 km/h with at-grade junctions, so it is not recorded here. Nor is the Požega–Boljare extension to the Montenegrin border (about 107 km): a contract for design and works on Požega–Duga Poljana (75 km) was signed on 26 December 2021, but the ministry says works can be contracted only once design and financing are in place, and the route still awaits its spatial plan.

Total length
152 km
Open today
152 km
Sections
7
Cost on record
€402.99M
2 of 7 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A2 Miloš Veliki Motorway (Belgrade – Požega): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Surčin – ObrenovacOpened18 km
  1. Jun 20, 2016Tender awarded
  2. May 2017Construction start
  3. Dec 2019Opened
  • Estimated $233.67M(2017)
  • LoanExport–Import Bank of China, 85% of the contract value.
  • National budgetRepublic of Serbia, 15%.
  • China Communications Construction Company Ltd.Builder
–
Obrenovac – UbOpened26 km
  1. May 2013Tender awarded
  2. 2014Construction start
  3. 2019Opened
  • Estimated $333.748Mwhole programmeMinistry's estimated value for Obrenovac – Ub and Lajkovac – Ljig together, built under one commercial contract.
  • LoanExport–Import Bank of China loan, USD 301 million, for Obrenovac – Ub and Lajkovac – Ljig together. 20 years including 5 years' grace, 2.5% fixed.
  • National budgetRepublic of Serbia, 10% participation.
  • Shandong Hi-Speed Group Co., Ltd.Builder
–
Ub – Lajkovac

Preparatory works officially started on 29 July 2010. Main works were held up by unfinished expropriation (B92, October 2010). The 11th annex was signed in June 2014, with completion due on 27 November 2014. At completion the minister put additional works at RSD 1 billion and the average cost at EUR 6 million per km (B92, December 2014). Works finished on 30 November 2014; the section opened to traffic on 18 August 2019 with the rest of the motorway.

Opened12 km
  1. Jul 2, 2010Tender awarded
  2. Jul 29, 2010Construction start
  3. Aug 18, 2019Opened
–
  • National budgetRepublic of Serbia budget, EUR 73 million.
  • Putevi Užice a.d.Builder
  • GP Planum a.d.Builder
16 mo total · Contract value дин.7.3B
Lajkovac – Ljig

Commercial contract for the Obrenovac – Ljig sector signed in May 2013: 10 May per AutoZona, 13 May per the ministry, whose page prints the year as 2023. Preparatory works for the sector were officially started on 24 December 2013 at Dići, near Ljig.

Opened24 km
  1. May 2013Tender awarded
  2. Dec 24, 2013Construction start
  3. Aug 18, 2019Opened
  • Estimated $333.748Mwhole programmeMinistry's estimated value for Obrenovac – Ub and Lajkovac – Ljig together, built under one commercial contract. Alo! (December 2013) says the total includes Serbia's 10% share.
  • LoanExport–Import Bank of China loan, USD 301 million, for Obrenovac – Ub and Lajkovac – Ljig together. 20 years including 5 years' grace, 2.5% fixed.
  • National budgetRepublic of Serbia, 10% participation.
  • Shandong Hi-Speed Group Co., Ltd.Builder
–
Ljig – PreljinaOpened40 km
  1. Apr 7, 2012Tender awarded
  2. Apr 20, 2012Construction start
  3. Nov 2016Opened
  • Estimated €308MMinistry's estimated investment value. Koridori Srbije gives the same figure as the value of works. It equals the Azerbaijani loan.
  • LoanGovernment of Azerbaijan loan, EUR 308 million, 4% fixed, 15 years with 3 years' grace.
  • AzVirtBuilder
–
Preljina – Pakovraće

Opened on 30 January 2022 (ministry). Part of the 30.9 km Preljina – Požega commercial contract with CCCC, signed on 27 November 2017. The ministry dates the start of works to July 2020; Tanjug (July 2025) says the road was built from May 2019. Length 11.4 km per the ministry; the geometry, cut at the Preljina and Pakovraće interchanges, measures 12.5 km.

Opened11 km
  1. Nov 27, 2017Tender awarded
  2. Jul 2020Construction start
  3. Jan 30, 2022Opened
  • Estimated $675Mwhole programmeMinistry's investment value for the whole 30.9 km Preljina – Požega section, built under one commercial contract. Price year not stated.
  • LoanLoan from a Chinese bank, for Preljina – Požega as a whole.
  • National budgetRepublic of Serbia budget.
  • China Communications Construction Company Ltd.Builder
–
Pakovraće – Požega

Opened to traffic at 12:00 on 6 July 2025, the day after the official ceremony (JP Putevi Srbije, via Tanjug). Carries the Laz (2,840 m) and Munjino Brdo (2,755 m) tunnels, the longest road tunnels in Serbia, and ends at the Prilipac interchange near Požega. The ministry dates the start of works on Preljina – Požega to July 2020; Tanjug says this section was built from May 2019. Length 19.56 km per Tanjug, of 30.96 km for Preljina – Požega; the geometry, cut at the Pakovraće and Prilipac interchanges, measures 17.7 km.

Opened20 km
  1. Nov 27, 2017Tender awarded
  2. Jul 2020Construction start
  3. Jul 6, 2025Opened
  • Estimated $675Mwhole programmeMinistry's investment value for the whole 30.9 km Preljina – Požega section, built under one commercial contract. Price year not stated.
  • LoanLoan from a Chinese bank, for Preljina – Požega as a whole.
  • National budgetRepublic of Serbia budget.
  • China Communications Construction Company Ltd.Builder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • Loan139 km
    6 sections
    • Export–Import Bank of China, 85% of the contract value.
    • Export–Import Bank of China loan, USD 301 million, for Obrenovac – Ub and Lajkovac – Ljig together. 20 years including 5 years' grace, 2.5% fixed.
    • Government of Azerbaijan loan, EUR 308 million, 4% fixed, 15 years with 3 years' grace.
    • Loan from a Chinese bank, for Preljina – Požega as a whole.
  • National budget111 km
    6 sections
    • Republic of Serbia, 15%.
    • Republic of Serbia, 10% participation.
    • Republic of Serbia budget, EUR 73 million.
    • Republic of Serbia budget.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. JP Putevi Srbije: Auto-put „Miloš Veliki“ pušten u saobraćaj (section lengths)
  2. Ministry of Construction, Transport and Infrastructure: Construction of E-763 highway, Surčin–Obrenovac section
  3. Wikipedia: A2 motorway (Serbia)
  4. OpenStreetMap: relation 6697754, Милош Велики (ref A2)
  5. OpenStreetMap contributors: route geometry (ODbL)
  6. Koridori Srbije: Beograd – Južni Jadranread Sep 25, 2026
  7. MGSI: Izgradnja autoputa E-763, deonica: Obrenovac-Ub i Lajkovac-Ljig (2025-06-27)read Sep 25, 2026
  8. Alo!: Kinezi se uključuju u gradnju Koridora 11 (2013-12-24)read Sep 25, 2026
  9. AutoZona.rs: Ub - Lajkovac (Koridor 11 deonice)read Sep 25, 2026 · archived copy
  10. B92: Ub-Lajkovac čeka eksproprijaciju (2010-10-22)read Sep 25, 2026
  11. AutoZona.rs: Lajkovac - Ljig autoputread Sep 25, 2026 · archived copy
  12. AutoZona.rs: Ljig - Preljinaread Sep 25, 2026 · archived copy
  13. MGSI: Izgradnja autoputa E-763, deonica: Ljig-Preljina (2025-06-27)read Sep 25, 2026
  14. Koridori Srbije: 2015–2016 audit report (AzVirt construction contract signed 07.04.2012)read Oct 11, 2026
  15. B92: Azerbejdžan nam daje 308 mil. evra (2012-04-06)read Sep 25, 2026
  16. B92: Ugovor o izgradnji deonice autoputa (2010-07-02)read Sep 28, 2026
  17. B92: Završena deonica Ub-Lajkovac (2014-12-12)read Oct 1, 2026
  18. MGSI: Izgradnja auto-puta E-763, deonica: Preljina-Požega (2025-06-19)read Oct 2, 2026
  19. Tanjug: Deonica auto-puta Pakovraće - Požega otvorena za saobraćaj (2025-07-06)read Oct 2, 2026
  20. MGSI: Izgradnja auto-puta E-763 „Miloš Veliki“, deonica: Požega-Boljare (2025-06-18)read Oct 2, 2026
  21. MGSI: Novi Beograd - Surčin (2025-06-19)read Oct 2, 2026