Highways

Ruma – Šabac – Loznica Motorway and Expressway

A 78 km road from the A3 at Ruma to Loznica on the Drina: a motorway to Šabac, a bridge over the Sava, then a two-carriageway expressway. JP Putevi Srbije is the investor; AzVirt built it under a design-build contract signed on 19 November 2019 and concluded without a tender under an intergovernmental agreement with Azerbaijan. The motorway and the Sava bridge opened on 14 October 2023 and the expressway on 29 December 2024. Further sections to Badovinci and Mali Zvornik are not part of this file. The Ministry gives one investment value for the project, not a figure per section, so no lot cost is recorded.

Total length
78 km
Open today
78 km
Sections
3
Cost for the project as a whole
€600Mwhole programmeMGSI investment value for the Ruma – Šabac – Loznica project; the page does not say whether it includes the later Slepčević – Badovinci section, and gives no per-section figures. Price year and VAT treatment not stated.
Loading map data…

Sections

Sections of Ruma – Šabac – Loznica Motorway and Expressway: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Ruma – Šabac motorway

MGSI lists Section 1 as 22.08 km plus a 0.44 km deviation to state road IB 21, which is not counted here. Runs from the Ruma interchange on the A3 to the Šabac interchange. The Ministry gives 19 June 2020 as the project start.

Opened22 km
  1. Nov 19, 2019Tender awarded
  2. Oct 14, 2023Opened
–
  • National budget
  • LoanDomestic commercial bank loans, per the Ministry (MGSI project page).
  • AzVirtBuilder
  • Institut za puteveDesigner
–
Sava bridge with approaches

MGSI lists the bridge over the Sava with its approach structures as a separate Section 2, outside the 22.08 km of Section 1, so it is its own lot and not part of another. The drawn line follows the main bridge way in OpenStreetMap (1.36 km), meeting the end of the Ruma – Šabac line and the start of the Šabac – Loznica line; the eastern approach viaduct is drawn in the Ruma – Šabac lot.

Opened1 km
  1. Nov 19, 2019Tender awarded
  2. Oct 14, 2023Opened
–
  • National budget
  • LoanDomestic commercial bank loans, per the Ministry (MGSI project page).
  • AzVirtBuilder
  • Institut za puteveDesigner
–
Šabac – Loznica expressway

MGSI gives the opening as December 2024 in the section list and as 29 December 2024 in the completion entry. Defect-liability works continued after opening.

Opened55 km
  1. Nov 19, 2019Tender awarded
  2. Dec 29, 2024Opened
–
  • National budget
  • LoanDomestic commercial bank loans, per the Ministry (MGSI project page).
  • AzVirtBuilder
  • Institut za puteveDesigner
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • National budget78 km
    3 sections
  • Loan78 km
    3 sections
    • Domestic commercial bank loans, per the Ministry (MGSI project page).

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Ministry of Construction, Transport and Infrastructure: Izgradnja brze saobraćajnice Ruma – Šabac – Loznicaread Oct 5, 2026
  2. OpenStreetMap contributors: route geometry (ODbL)read Oct 5, 2026