A4 Niš – Dimitrovgrad (E80)

Serbia's 105 km motorway from the A1 at Trupale near Niš to the Gradina border crossing with Bulgaria, the eastern branch (Xc) of Pan-European Corridor X and part of E80. The first 3 km opened in 1992 and the Niš bypass in 2006; the remaining 86 km was built from 2010 by Koridori Srbije and opened in stages between 2017 and 9 November 2019, when Bancarevo – Crvena Reka completed the route. Lots follow the section names and lengths of the construction table on Serbian Wikipedia; the drawn centreline totals 103.67 km. No section cost is recorded: the Ekonomske Vesti report of the 2019 opening gives about EUR 476 million, but it is unclear whether that covers the Prosek – Crvena Reka section or the whole 86.9 km east branch. The railway between Niš and Dimitrovgrad is a separate project.

Total length
104 km
Open today
104 km
Sections
9
Loading map data…

Sections

Sections of A4 Niš – Dimitrovgrad (E80): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Trupale – Komren

First 3 km of the motorway, from the Trupale interchange with the A1 towards Niš. Built 1990–1992 and then paused by sanctions and the wars. The OpenStreetMap interchange Niš sever lies about 1.6 km from Trupale, so the cut at 3 km follows the published length.

Opened3 km
  1. 1990Construction start
  2. 1992Opened
––
  • Novi Autoput BeogradBuilder
–
Komren – Prosek (Niš bypass)

Niš bypass. Serbian Wikipedia gives construction from 1997; English Wikipedia gives 1998. Published length 15 km; the drawn centreline measures 13.73 km because the cuts follow the published lengths of the neighbouring sections and the Malča interchange.

Opened15 km
  1. 1997Construction start
  2. 2006Opened
––
  • PzP NišBuilder
–
Prosek – Bancarevo

Works were completed on 30 June 2017 but the section opened only with Bancarevo – Crvena Reka on 9 November 2019. The Prosek end is placed at the Malča interchange area, about 16.7 km from Trupale.

Opened9 km
  1. Mar 15, 2012Construction start
  2. Nov 9, 2019Opened
––
  • TernaBuilder
–
Bancarevo – Crvena Reka

Includes the 0.8 km Bancarevo tunnel (Subterra, Czech Republic; construction works finished 9 June 2017, fully opened 2019). Last section to open, on 9 November 2019, completing the motorway from Niš to the Bulgarian border.

Opened13 km
  1. Mar 15, 2012Construction start
  2. Nov 9, 2019Opened
––
  • AktorBuilder
  • SubterraBuilder
–
Crvena Reka – Čiflik

Opened 13 July 2017 together with Čiflik – Staničenje. English Wikipedia also gives 2011 as the start year.

Opened13 km
  1. Oct 10, 2011Construction start
  2. Jul 13, 2017Opened
––
  • AktorBuilder
–
Čiflik – Staničenje

Opened 13 July 2017 together with Crvena Reka – Čiflik.

Opened12 km
  1. Sep 2013Construction start
  2. Jul 13, 2017Opened
––
  • RubauBuilder
–
Staničenje – Pirot istok

Opened in stages. The sub-section table of Serbian Wikipedia still lists a 0.6 km slope and overpass and a 1.2 km tunnel with two bridges as under construction, while its Corridor X article puts the opening of the whole section on 9 November 2019; the date recorded follows the latter.

Opened17 km
  1. Sep 2013Construction start
  2. Nov 9, 2019Opened
––
  • AktorBuilder
–
Pirot istok – Dimitrovgrad

Works were completed in November 2016 but the section could not open until its neighbours were finished. The drawn centreline measures 14.95 km, cut at the mapped Pirot-istok and Dimitrovgrad interchanges.

Opened14 km
  1. Nov 24, 2010Construction start
  2. Sep 16, 2017Opened
––
  • AlpineBuilder
  • TraceBuilder
–
Dimitrovgrad bypass

Tunnels built by Terna, electromechanical equipment by Elef (Italy). Dates follow the construction table of Serbian Wikipedia; its Corridor X article puts the bypass among sections opened on 9 November 2019. The drawn centreline measures 8.89 km and ends at the Gradina border interchange.

Opened9 km
  1. Apr 14, 2010Construction start
  2. Jun 25, 2018Opened
––
  • AlpineBuilder
  • TraceBuilder
  • AktorBuilder
  • TernaBuilder
  • ElefBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • Pan-European Corridor XPan-European

Sources

  1. Wikipedia (sr): Autoput A4 (Srbija), construction chronology tableread Oct 5, 2026
  2. Wikipedia: A4 motorway (Serbia)read Oct 5, 2026
  3. Wikipedia (sr): Panevropski koridor X (branch Xc, sections opened 9.11.2019)read Oct 5, 2026
  4. Ekonomske Vesti: Otvara se autoput Niš – Dimitrovgrad – bugarska granica (9 November 2019)read Oct 5, 2026
  5. OpenStreetMap contributors: motorway ref A4 geometry (ODbL)read Oct 5, 2026