Ferrovial
Greece
- Sections
- 6
- Length
- 149 km
- Median slip
- –
- Median overrun
- –
No section this firm built records both a contracted duration and a delivery date, so there is no slip to report.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Euroionia JV
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A5 Ionia Odos (Antirrio – Ioannina) / Antirrio – Klokova Tunnel | Greece | Opened | 6 km | Jun 2017 | – |
| A5 Ionia Odos (Antirrio – Ioannina) / Klokova Tunnel – Chaliki | Greece | Opened | 40 km | Apr 2017 | – |
| A5 Ionia Odos (Antirrio – Ioannina) / Kouvaras – Amfilochia | Greece | Opened | 25 km | Dec 2016 | – |
| A5 Ionia Odos (Antirrio – Ioannina) / Amfilochia – Kompoti | Greece | Opened | 28 km | Jul 2017 | – |
| A5 Ionia Odos (Antirrio – Ioannina) / Filippiada – Perdika | Greece | Opened | 36 km | Feb 2017 | – |
| A5 Ionia Odos (Antirrio – Ioannina) / Perdika – Pedini (A2 Egnatia Odos) | Greece | Opened | 14 km | Aug 2017 | – |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.