GBS Infrastructure Construction

Bulgaria
Sections
6
Length
105 km
Median slip
−2 mo
Median overrun
–

Slip measured on 5 of 6 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • AM Struma 3.2.2 Consortium
  • Struma Lot 3.3 Consortium
  • Struma – 1 Consortium
  • Struma-Lot 2 Consortium

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A3 Struma Motorway / Dolna Dikanya – Dupnitsa NorthBulgariaOpened14 kmJul 2013−2 mo
A3 Struma Motorway / Dupnitsa North – km 322 (end of Lot 1)BulgariaOpened3 kmOct 2015–
A3 Struma Motorway / Dupnitsa – BlagoevgradBulgariaOpened37 kmOct 2015+10 mo
A3 Struma Motorway / Krupnik – Kresna (Kresna Gorge Bypass)BulgariaUnder construction10 km–+32 mo
A3 Struma Motorway / Kresna – SandanskiBulgariaOpened24 kmDec 2018−3 mo
A6 Europe Motorway / Dragoman – SlivnitsaBulgariaOpened17 kmNov 2020−6 mo