Hidrostroy

Bulgaria
Sections
2
Length
22 km
Median slip
+26 mo
Median overrun
–

Slip measured on 2 of 2 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • AM Struma 3.1 Consortium
  • HVP Yablanitsa Consortium

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A2 Hemus Motorway / Yablanitsa – BoazaBulgariaOpened9 kmOct 2019−5 mo
A3 Struma Motorway / Blagoevgrad – KrupnikBulgariaOpened13 kmFeb 2024+56 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.