A2 Hemus Motorway

Motorway running 418 km from Sofia to the Black Sea port of Varna via Shumen, crossing the Balkan Mountains and carrying European routes E70, E83 and E772. Work began on 4 October 1974 and the first section, Varna – Devnya, opened in 1979. As of December 2025, 206 km are open in two disconnected stretches, Sofia to Ugarchin (approximately 103 km) and Buhovtsi to Varna (approximately 108 km); the roughly 208 km between Ugarchin and Buhovtsi are under construction or still in planning. The motorway is managed by the Bulgarian Roads Agency, successor to NCSIP.

Total length
412 km
Open today
204 km
Sections
22
Cost on record
€172.966M
3 of 22 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A2 Hemus Motorway: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Sofia – YanaOpened8 km
  1. Sep 21, 2011Tender awarded
  2. Sep 26, 2011Construction start
  3. Aug 2013Opened
–
  • European UnionCohesion Fund, OP Transport 2007–2013 (grant contract ДОПТ 15 of 14 October 2011)
  • National budgetNational co-financing
  • ДЗЗД „Хемус А2“Builder
  • Трейс Груп Холд АДBuilder
  • Конструктор инженеринг АДBuilder
  • СК-13 Пътстрой АДBuilder
22 mo execution · Contract value лв38.34M
Yana – Potop

Yana – Pravets (44.4 km in total) opened in 1986 according to Bulgarian Wikipedia. The 5 December 1999 opening was the Pravets bypass, in Pravets – Yablanitsa.

Opened13 km
  1. 1986Opened
––––
Potop – Botevgrad

Partial contractor list. Мостстрой built the Bebresh viaduct (km 38, completed 1985). Yana – Pravets (44.4 km in total) opened in 1986 according to Bulgarian Wikipedia. The 5 December 1999 opening was the Pravets bypass, in Pravets – Yablanitsa.

Opened25 km
  1. 1986Opened
––
  • МостстройBuilder
–
Botevgrad – Pravets

Yana – Pravets (44.4 km in total) opened in 1986 according to Bulgarian Wikipedia. The 5 December 1999 opening was the Pravets bypass, in Pravets – Yablanitsa.

Opened6 km
  1. 1986Opened
––––
Pravets – Yablanitsa

Partial contractor list. Мостстрой built the viaduct at km 56 (1986–1999).

Opened22 km
  1. 1984Construction start
  2. Dec 5, 1999Opened
––
  • МостстройBuilder
  • Хидрострой ТунелиBuilder
  • Пътстрой 92Builder
–
Yablanitsa – Boaza

Design-and-build contract. Contract durations converted from days: 910 days total, 150 days design, 730 days works.

Opened9 km
  1. Jul 19, 2017Tender awarded
  2. Mar 27, 2018Construction start
  3. Oct 2019Opened
–
  • National budgetState budget
  • Консорциум „ХВП Ябланица“Builder
  • Хидрострой АДBuilder
  • Водстрой 98 АДBuilder
  • Пътстрой Бургас ЕООДBuilder
5 mo design · 24 mo execution · 30 mo total · Contract value лв54.99M
Boaza – Dermantsi

Direct award to Avtomagistrali EAD under agreement Д-122 of 20 December 2018, covering km 87+800–222+000. Construction start is the official start of works on 23 April 2019, marked symbolically.

Opened10 km
  1. Dec 20, 2018Tender awarded
  2. Apr 23, 2019Construction start
  3. Oct 2025Opened
–
  • National budgetState budget, for the whole Boaza – I-5 stretch
  • Автомагистрали ЕАДBuilder
–
Dermantsi – Ugarchin

Direct award to Avtomagistrali EAD under agreement Д-122 of 20 December 2018, covering km 87+800–222+000.

Opened5 km
  1. Dec 20, 2018Tender awarded
  2. Dec 13, 2025Opened
–
  • National budgetState budget, for the whole Boaza – I-5 stretch
  • Автомагистрали ЕАДBuilder
–
Dermantsi – Kalenik

Lot 2, km 103+150–122+260. Direct award to Avtomagistrali EAD under agreement Д-122 of 20 December 2018, covering km 87+800–222+000. Building permit РС-69 of 27 August 2020. Marked under construction on magistralahemus.bg, which gives 2028 as the expected opening.

Under construction19 km
  1. Dec 20, 2018Tender awarded
––
  • Автомагистрали ЕАДBuilder
–
Kalenik – Pleven

Lot 3, km 122+260–139+340. Direct award to Avtomagistrali EAD under agreement Д-122 of 20 December 2018, covering km 87+800–222+000. Building permits РС-31 of 17 April 2019 and РС-30 of 1 June 2020. Marked under construction on magistralahemus.bg, which gives 2028 as the expected opening.

Under construction17 km
  1. Dec 20, 2018Tender awarded
––
  • Автомагистрали ЕАДBuilder
–
Pleven – Letnitsa

Lot 4, km 139+340–167+572. Direct award to Avtomagistrali EAD under agreement Д-122 of 20 December 2018, covering km 87+800–222+000. Building permits РС-111 of 23 December 2025 (km 139+340–152+500) and РС-6 of 4 February 2025 (km 152+500–167+572). Marked under construction on magistralahemus.bg, which gives 2028 as the expected opening. On 1 September 2026 the Ministry reported construction was underway on Hemus Section 4, matching this lot.

Under construction28 km
  1. Dec 20, 2018Tender awarded
––
  • Автомагистрали ЕАДBuilder
–
Letnitsa – Pavlikeni

Lot 5, km 167+572–190+771. Direct award to Avtomagistrali EAD under agreement Д-122 of 20 December 2018, covering km 87+800–222+000. Building permit РС-110 issued on 23 December 2025. magistralahemus.bg still shows the building-permit stage and gives 2028 as the expected opening.

Planned23 km
  1. Dec 20, 2018Tender awarded
––
  • Автомагистрали ЕАДBuilder
–
Pavlikeni – Polikraishte

Lot 6, km 190+771–223+426. Covered by the December 2018 direct award to Avtomagistrali EAD (km 87+800–222+000) and the 18 December 2019 direct contract for km 222+000–310+940. MRRB says a construction permit was signed on 7 May 2026 for the approximately 32 km section from the III-303 Pavlikeni–Levski junction to the I-5 Ruse–Veliko Tarnovo road, including a junction near Kutsina, matching this lot. The permit allows preliminary execution; it does not establish a construction start. The ministry gives 44 months from the site-opening protocol as the works deadline.

Planned33 km–––
  • Автомагистрали ЕАДBuilder
–
Polikraishte – Loznitsa

Lots 7 and 8 combined, km 223+426–299+000: Kutsina/Veliko Tarnovo – Popovo (km 223+426–265+600, 42.2 km) and Popovo – Loznitsa (km 265+600–299+000, 33.4 km). Both are at the technical design stage on magistralahemus.bg, which gives 2030 as the expected opening. Covered by the 18 December 2019 direct contract with Avtomagistrali EAD for km 222+000–310+940, which includes the design work for the km 222+000–265+600 section.

Planned76 km–––
  • Автомагистрали ЕАДBuilder
–
Loznitsa – Buhovtsi

Lot 9, km 299+000–310+940. Direct contract with Avtomagistrali EAD of 18 December 2019 for km 222+000–310+940, value not disclosed. Building permit issued on 17 February 2026. magistralahemus.bg shows the building-permit stage and gives 2028 as the expected opening.

Planned12 km
  1. Dec 18, 2019Tender awarded
––
  • Автомагистрали ЕАДBuilder
–
Belokopitovo – Buhovtsi

Contract duration converted from days: 910 calendar days.

Opened16 km
  1. Sep 29, 2017Tender awarded
  2. Aug 2018Construction start
  3. Oct 2022Opened
–
  • National budgetState budget
  • ДЗЗД „Хемус 16320“Builder
  • Инфра Експерт ЕООДBuilder
  • Пътинженерингстрой-Т ЕАДBuilder
  • Автомагистрали - Черно Море АДBuilder
  • Трансконсулт-22 ООДBuilder
30 mo total · Contract value лв143.742M
Belokopitovo – Panayot Volovo

Km 337+302–342+200, connecting road I-2 Ruse–Varna and road I-4 Koritna–Belokopitovo.

Opened5 km
  1. Aug 29, 2013Construction start
  2. Aug 3, 2015Opened
––––
Panayot Volovo – Shumen

Section from the Makak quarter of Shumen to Panayot Volovo. Works began in July 2011 on 7.8 km valued at about 38 million leva, with a 14-month deadline.

Opened8 km
  1. Jul 2011Construction start
  2. Jul 25, 2013Opened
––––
Shumen – Kaspichan

The section cost 77.6 million leva according to English Wikipedia; Bulgarian Wikipedia cites the government information service for 77.6 million leva invested.

Opened13 km
  1. Dec 30, 2005Opened
––––
Kaspichan – Mlada Gvardiya

No opening date found. The year 2006 is a latest bound, not an opening date: the earliest revision of Bulgarian Wikipedia (27 March 2006) already lists the Varna – Shumen stretch as in service. The exit table of the current page puts Kaspichan at km 351.6 and Mlada Gvardiya at km 370.6, so the length is the 19.0 km difference. The 2005 opening of the adjoining Shumen – Kaspichan section does not date this lot.

Opened19 km
  1. 2006Opened
––––
Devnya – Mlada Gvardiya

Begun in the 1970s. Opening year only; the source gives no month.

Opened20 km
  1. 1983Opened
––––
Varna – Devnya

Opening year only; the source gives no month.

Opened24 km
  1. 1979Opened
––––

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • National budget49 km
    5 sections
    • National co-financing
    • State budget
    • State budget, for the whole Boaza – I-5 stretch
  • European Union8 km
    1 section
    • Cohesion Fund, OP Transport 2007–2013 (grant contract ДОПТ 15 of 14 October 2011)

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia: Hemus motorway
  2. Агенция „Пътна инфраструктура“: АМ „Хемус“ СОП – гара „Яна“read Sep 25, 2026 · archived copy
  3. Trace Group Hold: Доизграждане на АМ „Хемус“read Sep 25, 2026
  4. Агенция „Пътна инфраструктура“: АМ „Хемус“, участък от км 78+500 до км 87+800read Sep 25, 2026 · archived copy
  5. News.bg: Първа копка на АМ „Хемус“ – отсечката Ябланица – Боаза (27 March 2018)read Sep 25, 2026
  6. Investor.bg: Откриха новия участък от АМ „Хемус“ между Ябланица и Боаза (11 October 2019)read Sep 25, 2026
  7. Mediapool: Пускат магистрала „Хемус“ от Буховци до Белокопитово с 2.5 г. закъснениеread Sep 25, 2026
  8. gradat.bg: Завършват предсрочно отсечката Белокопитово – Буховци на АМ „Хемус“read Sep 25, 2026
  9. Investor.bg: Участъкът от магистрала „Хемус“ Белокопитово – Буховци е пуснат за движениеread Sep 25, 2026
  10. Утро Русе (пресцентър на АПИ): На 23 април започва поетапното строителство на АМ „Хемус“ между Боаза и пътя Русе – Велико Търновоread Sep 25, 2026
  11. Агенция „Пътна инфраструктура“: Изграждане на АМ „Хемус“ от км 87+800 до км 222+000read Sep 28, 2026 · archived copy
  12. gradat.bg: Усилено се строи 16 км участък от Боаза до Дерманци на АМ „Хемус“ (17 April 2020)read Sep 28, 2026
  13. МРРБ: Започна поетапното строителство на АМ „Хемус“ между Боаза и пътя Русе – Велико Търново (23 April 2019)read Sep 28, 2026
  14. Ботевградски вести плюс, бр. 49 (6–11 декември 1999): Иван Костов откри участъка Правец – Ябланица на магистрала „Хемус“read Sep 28, 2026
  15. Уикипедия: Виадукт на километър 56 по АМ „Хемус“read Sep 28, 2026
  16. БНТ: 50 години магистрала „Хемус“ е в строеж – ще я видим ли завършена? (4 October 2024)read Oct 1, 2026
  17. Уикипедия: Хемус (магистрала)read Oct 1, 2026
  18. Уикипедия: Хемус (магистрала), първа версия от 27 март 2006read Oct 9, 2026
  19. Магистрала Хемус: Напредък по лотовеread Oct 5, 2026
  20. OpenStreetMap contributors (geometry, ODbL)read Aug 14, 2026
  21. MRRB: Current construction in Hemus Section 4 (1 Sep 2026)read Oct 12, 2026
  22. MRRB: Construction permit signed for Hemus Section 6 (7 May 2026)read Oct 12, 2026

Figures last checked against their sources in Oct 12, 2026.