IHI Infrastructure Systems

Romania

Name variants are not merged

Unregistered spelling

Sections
1
Length
2 km
Median slip
+19 mo
Median overrun

Slip measured on 1 of 1 sections built.

No section this firm built records both an estimate and a final cost.

Too few sections to rank. The figures below describe the work; they are not a track record.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Sections built

SectionCountryStatusLengthOpenedSlip
Brăila Bridge / Main bridge and access roadsRomaniaOpened2 kmJul 2023+19 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.