← All contractors
Novi Autoput Beograd
Serbia
Name variants are not merged
Unregistered spelling
- Sections
- 1
- Length
- 3 km
- Median slip
- –
- Median overrun
- –
No section this firm built records both a contracted duration and a delivery date, so there is no slip to report.
No section this firm built records both an estimate and a final cost.
Too few sections to rank. The figures below describe the work; they are not a track record.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A4 Niš – Dimitrovgrad (E80) / Trupale – Komren | Serbia | Opened | 3 km | Jan 1992 | – |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.