Skip to content
InfraWorldWide
← All contractors

PST Group

Bulgaria
Sections
1
Length
30 km
Median slip
+54 mo
Median overrun
–

Slip measured on 1 of 1 sections built.

No section this firm built records both an estimate and a final cost.

Too few sections to rank. The figures below describe the work; they are not a track record.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • DZZD Severozapad Lot 1

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
Vidin – Montana Motorway / Vidin – Makresh (Lot 1)BulgariaUnder construction30 km–+54 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.