Strade Bauunternehmung
Romania
Name variants are not merged
Unregistered spelling
- Sections
- 1
- Length
- 18 km
- Median slip
- +46 mo
- Median overrun
- –
Slip measured on 1 of 1 sections built.
No section this firm built records both an estimate and a final cost.
Too few sections to rank. The figures below describe the work; they are not a track record.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Ozaltin Insaat – Strade Bauunternehmung – Visio Construction Works
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| Craiova–Pitești Expressway (DEx12) / Craiova – Balș | Romania | Opened | 18 km | Nov 2024 | +46 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.