TERNA JV
Greece
Name variants are not merged
Unregistered spelling
- Sections
- 2
- Length
- 52 km
- Median slip
- –
- Median overrun
- –
No section this firm built records both a contracted duration and a delivery date, so there is no slip to report.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Aktor – AVAX – TERNA JV
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| Athens – Thessaloniki railway modernisation (PATHE) / Lianokladi – Aggeies (Othrys tunnel) | Greece | Opened | 31 km | Jan 2019 | – |
| Athens – Thessaloniki railway modernisation (PATHE) / Aggeies – Domokos | Greece | Opened | 21 km | Jan 2019 | – |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.