← All contractors
TSS Grade
Slovakia
- Sections
- 1
- Length
- 13 km
- Median slip
- +14 mo
- Median overrun
- –
Slip measured on 1 of 1 sections built.
No section this firm built records both an estimate and a final cost.
Too few sections to rank. The figures below describe the work; they are not a track record.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Združenie pod Dubinou
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| Žilina – Košice railway modernisation (160 km/h) / Poprad-Tatry – Vydrník (stage A1) | Slovakia | Under construction | 13 km | – | +14 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.