Skip to content
InfraWorldWide
← All contractors

VINCI Construction Grands Projets

Greece
Sections
6
Length
198 km
Median slip
–
Median overrun
–

No section this firm built records both a contracted duration and a delivery date, so there is no slip to report.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Apion Kleos Construction JV
  • Kinopraxia Gefyra

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A8 Olympia Odos Motorway / Ancient Corinth – KiatoGreeceOpened20 kmSep 2016–
A8 Olympia Odos Motorway / Kiato – XylokastroGreeceOpened14 kmFeb 2017–
A8 Olympia Odos Motorway / Xylokastro – RioGreeceOpened86 kmApr 2017–
A8 Olympia Odos Motorway / Mintilogli – KaminiaGreeceOpened10 kmDec 2025–
A8 Olympia Odos Motorway / Kaminia – PyrgosGreeceOpened65 kmAug 2025–
Rio – Antirrio Bridge (Charilaos Trikoupis Bridge) / Main bridge and access viaducts (Rio – Antirrio)GreeceOpened3 kmAug 2004–

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.