Vt 4 Kirri–Vehniä motorway
A new 16 km motorway between Kirri and Vehniä, opened to traffic on 21 December 2021. The wider Vt 4 Kirri–Tikkakoski project also built parallel and cross roads, which are excluded from this lot.
- Total length
- 16 km
- Open today
- 16 km
- Sections
- 1
Cost for the project as a whole
€141.9Mwhole programmeestimatedVäylävirasto reports this as the budget for the wider Vt 4 Kirri–Tikkakoski project, including a EUR 2.9 million contribution from Jyväskylä. It covers more than this 16 km motorway lot, including parallel and cross roads; the source gives no price year.
Category
Highways
Status
Opened
Under construction
Tendered
Planned
Loading map data…
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Kirri–Vehniä Väylävirasto reports 16 km of new motorway. The OSM line runs between the Kirri J55 and Vehniä J60 junction nodes and measures 15.08 km, about 6% shorter than the reported length; the sourced figure is retained. It represents one motorway carriageway. | Opened | 16 km |
| – | – |
| – |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Related projects
Sources
- Väylävirasto: New motorway between Kirri and Vehniä opens 21 December 2021 (16 Dec 2021)read Oct 11, 2026
- Väylävirasto: Construction of Vt 4 Kirri–Tikkakoski is halfway complete (18 Feb 2021)read Oct 13, 2026
- Väylävirasto: Vt 4 motorway between Kirri and Vehniä completed (20 Dec 2022)read Oct 12, 2026
- OpenStreetMap: Valtatie 4 route relation 14265641read Oct 11, 2026
Figures last checked against their sources in Oct 13, 2026.