All contractors

CCCF București

Romania
Sections
3
Length
39 km
Median slip
+58 mo
Median overrun

Slip measured on 1 of 3 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Astaldi / Max Bögl / CCCF

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
Fetești–Cernavodă bridges (A2 / CFR line 800) / Borcea branch bridge (Fetești)RomaniaOpened1 kmMay 1987
Fetești–Cernavodă bridges (A2 / CFR line 800) / Danube bridge at CernavodăRomaniaOpened2 kmNov 1987
A2 Bucharest–Constanța Motorway / Drajna – FeteștiRomaniaOpened37 kmMay 2007+58 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.