A2 Bucharest–Constanța Motorway

The "Motorway of the Sun" (Autostrada Soarelui) linking Bucharest to the Black Sea port of Constanța, 206 km. The Cernavodă bridges section dates from 1987; the motorway was completed end-to-end in November 2012.

Total length
210 km
Open today
210 km
Sections
8
Cost on record
€170.544M
1 of 8 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A2 Bucharest–Constanța Motorway: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Bucharest – Fundulea

Bucharest–Fetești sector built 2001–2007 in four sections; this one by the Romanian company Romis, surfaced with concrete slabs

Opened27 km
  1. 2001Tender awarded
  2. 2001Construction start
  3. Jun 4, 2004Opened
  • Actual €57.3MFinal value of works per Jurnalul Național (2009). No price year or VAT status stated.
  • Loan
  • RomisBuilder
Contract value €73.8M
Fundulea – Lehliu

Bucharest–Fetești sector, section 2, built by the Turkish joint venture Yuksel–Makimsan–Ener

Opened29 km
  1. 2001Tender awarded
  2. 2001Construction start
  3. Jun 4, 2004Opened
  • Actual €87MAmount paid per Jurnalul Național (2009). No price year or VAT status stated.
  • Loan
  • Yuksel / Makimsan / Ener (JV)Builder
  • IPTANA SADesigner
Contract value €87.068M
Lehliu – Drajna

Bucharest–Fetești sector, section 3, built by the French company Colas

Opened42 km
  1. 2001Tender awarded
  2. 2001Construction start
  3. Nov 16, 2004Opened
  • Actual €93.7MFinal value per Jurnalul Național (2009). No price year or VAT status stated.
  • Loan
  • ColasBuilder
Contract value €116.826M
Drajna – Fetești

Bucharest–Fetești sector, section 4, built by the Astaldi–Max Bögl–CCCF joint venture with ISPA pre-accession support

Opened37 km
  1. Dec 9, 2003Tender awarded
  2. 2004Construction start
  3. May 1, 2007Opened
  • Actual €110Mwhole programmeApproximate total value of works for the whole Drajna – Cernavodă sector (Drajna – Fetești and Fetești – Cernavodă), per Jurnalul Național (2009). No price year stated.
  • European UnionISPA pre-accession funds
  • National budget
  • Astaldi / Max Bögl / CCCF (JV)Builder
6 mo design · 18 mo execution · 24 mo total · 48 mo guarantee · Contract value €64.549M
Fetești – Cernavodă (Danube bridges)

Oldest section: the Cernavodă bridge complex over the Danube, opened 21 November 1987; closed September 2006 for complete rebuilding and reopened 2007

Opened17 km
  1. 1984Construction start
  2. Nov 21, 1987Opened
–
  • National budget
  • IPTANA SADesigner
  • Astaldi / Max Bögl / CCCF (JV) (rehabilitation)Builder
–
Cernavodă – Medgidia

Part of the Cernavodă–Constanța section, total cost €413.95M: €250M European Investment Bank loan, €70.81M European Commission, ~€90M Romanian state. Works began in 2009 under an earlier contract; the contract signed on 21 September 2011 re-awarded the remaining works.

Opened21 km
  1. 2009Construction start
  2. Mar 2009Tender awarded
  3. Jul 19, 2012Opened
  • Estimated lei 726.2MExcluding VAT. Initial estimated value of the re-tendered contract.
  • European UnionCohesion Fund / European Commission: €70.81M of the €413.95M Cernavodă–Constanța cost
  • LoanEuropean Investment Bank: €250M of the €413.95M Cernavodă–Constanța cost
  • National budget
  • Astaldi – Max Bögl (JV)Builder
  • Colas (initial contract, terminated 2011)Builder
3 mo design · 12 mo execution · 15 mo total · 48 mo guarantee · Contract value lei 498.8M
Medgidia – Murfatlar

Part of the Cernavodă–Constanța section, total cost €413.95M: €250M European Investment Bank loan, €70.81M European Commission, ~€90M Romanian state

Opened16 km
  1. Mar 9, 2009Tender awarded
  2. Jun 4, 2009Construction start
  3. Jul 19, 2012Opened
–
  • European UnionCohesion Fund / European Commission: €70.81M of the €413.95M Cernavodă–Constanța cost
  • LoanEuropean Investment Bank: €250M of the €413.95M Cernavodă–Constanța cost
  • National budget
  • Astaldi – Max Bögl (JV)Builder
6 mo design · 18 mo execution · 24 mo total · 48 mo guarantee · Contract value lei 596.054M
Murfatlar – Constanța

Part of the Cernavodă–Constanța section, total cost €413.95M: €250M European Investment Bank loan, €70.81M European Commission, ~€90M Romanian state

Opened21 km
  1. Mar 9, 2009Tender awarded
  2. Jun 4, 2009Construction start
  3. Sep 30, 2011Opened
–
  • European UnionCohesion Fund / European Commission: €70.81M of the €413.95M Cernavodă–Constanța cost
  • LoanEuropean Investment Bank: €250M of the €413.95M Cernavodă–Constanța cost
  • National budget
  • Astaldi – Max Bögl (JV)Builder
6 mo design · 18 mo execution · 24 mo total · 48 mo guarantee · Contract value lei 596.054M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • Loan156 km
    6 sections
    • European Investment Bank: €250M of the €413.95M Cernavodă–Constanța cost
  • National budget112 km
    5 sections
  • European Union95 km
    4 sections
    • ISPA pre-accession funds
    • Cohesion Fund / European Commission: €70.81M of the €413.95M Cernavodă–Constanța cost

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia: A2 motorway (Romania)
  2. OpenStreetMap contributors (geometry, ODbL)read Aug 14, 2026
  3. businesscover.ro
  4. ro.wikipedia.org
  5. mediafax.ro
  6. Wikipedia (ro): Autostrada A2 (România)#Costuri
  7. Jurnalul Național: Autostrada Soarelui – zero kilometri în doi ani (2009-07-09)read Sep 25, 2026
  8. CNADNR: Construcția autostrăzii Cernavodă – Constanța (archived 2013)read Sep 25, 2026
  9. HotNews: CNADNR a semnat cu Astaldi contractul pentru tronsonul Cernavodă – Medgidia (2011-09-21)read Sep 25, 2026
  10. Newsweek România: Astaldi despăgubită cu 265 milioane de leiread Sep 25, 2026
  11. HotNews: CNADNR a lăsat tronsonul de autostradă Cernavodă-Medgidia fără constructor (2011-04-11)read Sep 28, 2026 · archived copy
  12. HotNews: Tronsonul Drajna-Fetesti al Autostrazii Soarelui, finalizat de 1 Mai (2007-04-30)read Sep 28, 2026
  13. CNADNR: Proiecte ISPA, secțiunile 4 și 5 ale autostrăzii București – Constanța (archived 2013)read Sep 28, 2026