← All contractors
Heilit+Woerner
Poland
- Sections
- 3
- Length
- 111 km
- Median slip
- +33 mo
- Median overrun
- –
Slip measured on 1 of 3 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A4 motorway (Jędrzychowice – Wrocław – Katowice – Kraków – Rzeszów – Korczowa) / Targowisko – Bochnia – Brzesko – Tarnów Północ | Poland | Opened | 57 km | May 2013 | – |
| A4 motorway (Jędrzychowice – Wrocław – Katowice – Kraków – Rzeszów – Korczowa) / Tarnów Północ – Dębica Wschód | Poland | Opened | 35 km | Oct 2014 | +33 mo |
| S8 expressway (Wrocław – Łódź – Warszawa – Białystok) / Złoczew – Sieradz Południe | Poland | Opened | 20 km | Oct 2014 | – |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.