← All contractors
Infra Expert
Bulgaria
- Sections
- 2
- Length
- 57 km
- Median slip
- +31 mo
- Median overrun
- –
Slip measured on 1 of 2 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- DZZD Hemus-16320
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A2 Hemus Motorway / Belokopitovo – Buhovtsi | Bulgaria | Opened | 16 km | Oct 2022 | +31 mo |
| Ruse – Veliko Tarnovo Motorway / Ruse – Byala (Section 1) | Bulgaria | Tendered | 40 km | – | – |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.