Polimex Mostostal
Poland
- Sections
- 5
- Length
- 155 km
- Median slip
- +6 mo
- Median overrun
- –
Slip measured on 1 of 5 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A1 motorway (Rusocin – Toruń – Łódź – Częstochowa – Gliwice – Gorzyczki) / Łódź Północ – Tuszyn | Poland | Opened | 40 km | Jul 2016 | – |
| A1 motorway (Rusocin – Toruń – Łódź – Częstochowa – Gliwice – Gorzyczki) / Gliwice Wschód – Gliwice Sośnica | Poland | Opened | 6 km | Sep 2011 | – |
| A2 motorway (Świecko – Poznań – Łódź – Warszawa – Siedlce – Biała Podlaska – Kukuryki) / Łódź Północ – Skierniewice | Poland | Opened | 32 km | Jun 2012 | – |
| A4 motorway (Jędrzychowice – Wrocław – Katowice – Kraków – Rzeszów – Korczowa) / Kraków Wieliczka – Targowisko (Szarów) | Poland | Opened | 20 km | Oct 2009 | +6 mo |
| A4 motorway (Jędrzychowice – Wrocław – Katowice – Kraków – Rzeszów – Korczowa) / Targowisko – Bochnia – Brzesko – Tarnów Północ | Poland | Opened | 57 km | May 2013 | – |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.