Retter
Romania
Name variants are not merged
Unregistered spelling
- Sections
- 2
- Length
- 39 km
- Median slip
- +15 mo
- Median overrun
- –
Slip measured on 1 of 2 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Impresa Pizzarotti – Retter
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A0 Bucharest Ring Motorway / North half-ring: DN1 – A1 (via Buftea) | Romania | Under construction | 18 km | – | – |
| A7 Motorway (Moldavia Motorway) / Dumbrava (A3) – Mizil (Ploiești–Buzău lot 1) | Romania | Opened | 21 km | Dec 2024 | +15 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.