A0 Bucharest Ring Motorway

Outer motorway ring around Bucharest, about 101 km when complete, running beyond the existing Bucharest Ring Road and linking the A1, A2 and A3 motorways. The southern half-ring (51.3 km) was completed in stages between December 2023 and July 2025. On the northern half-ring, the DN1–A3–DN2 section opened in November 2023 and December 2024; the western (A1–DN1) and eastern (DN2–A2) lots are still under construction.

Total length
101 km
Open today
69 km
Under construction
32 km
Sections
4
Cost on record
€962.902M
2 of 4 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A0 Bucharest Ring Motorway: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
South half-ring: A1 – A2

South ring tendered July 2017: 52 km, €580M, completion estimated after 2022; execution contracts signed with Alsim Alarko (lots 1–2, March 2019) and Aktor (lot 3, April 2019)

Opened51 km
  1. Dec 2012Announced
  2. 2019Construction start
  3. Mar 9, 2019Tender awarded
  4. Jul 2025Opened
  • Estimated €580M(2017)
  • European UnionFound eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
  • National budget
  • Alsim Alarko (south lots 1–2)Builder
  • Aktor (south lot 3)Builder
Contract value €580M
North half-ring: A2 – DN2

Bucharest ring motorway, found eligible for EU financing after the 2016 traffic studies. OpenStreetMap tags construction:opening_date=2026 on the A0 Nord Lot 3 (Afumați–Pantelimon) and Lot 4 (Pantelimon–Manolache) construction ways

Under construction14 km
  1. 2023Construction start
  2. 2026Expected opening
  • European UnionEU funds
  • National budget
  • CCECC (north lot 3, Afumați–Pantelimon)Builder
  • Spedition UMB (north lot 4, Pantelimon–Manolache)Builder
North half-ring: DN2 – DN1 (via A3)

North ring lot 2 (Corbeanca–Afumați, 19 km): Spedition UMB entered site November 2021, building permit issued July 2022

Opened18 km
  1. Nov 2021Construction start
  2. Dec 2024Opened
  • European UnionEU funds
  • National budget
  • Spedition UMB (north lot 2, Corbeanca–Afumați)Builder
22 mo execution · Contract value lei 831.92M
North half-ring: DN1 – A1 (via Buftea)

Bucharest ring motorway, found eligible for EU financing after the 2016 traffic studies. OpenStreetMap tags construction:opening_date=2026 on the A0 Nord Lot 1 (Bâcu–Corbeanca) construction ways

Under construction18 km
  1. 2023Construction start
  2. 2026Expected opening
  • European UnionEU funds
  • National budget
  • Impresa Pizzarotti – Retter (north lot 1, Bâcu–Corbeanca)Builder

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union101 km
    4 sections
    • Found eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
    • EU funds
  • National budget101 km
    4 sections

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.