A0 Bucharest Ring Motorway
Outer motorway ring around Bucharest, about 101 km when complete, running beyond the existing Bucharest Ring Road and linking the A1, A2 and A3 motorways. The southern half-ring (51.2 km) opened in stages between December 2023 and June 2025. On the northern half-ring, the DN1–A3–DN2 section opened in November 2023 and December 2024; the western (A1–DN1) and eastern (DN2–A2) lots are still under construction.
- Total length
- 102 km
- Open today
- 70 km
- Under construction
- 32 km
- Sections
- 8
- Cost on record
- €662.364M
- 3 of 8 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| South lot 1: A2 – Popești-Leordeni (DN4) Eastern part of south lot 1 (A2 – CF902 Jilava, 16.93 km), whose contract also covers a 700 m sector of the north ring at the A2 junction (km 52+070 – 52+770). Opened in July 2024, three months after the lot's western 6.0 km (130km.ro). The 10.93 km is the lot's 16.93 km less those 6.0 km, so it includes the 700 m north-ring sector. Contract signed with Alsim Alarko on 26 August 2019. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews). | Opened | 11 km |
| – |
|
| 12 mo design · 30 mo execution · 42 mo total · Contract value lei 830.68M |
| South lot 1: Popești-Leordeni (DN4) – Jilava (CF902) Western part of south lot 1, opened in April 2024 together with Jilava – DN5 of lot 2 (130km.ro). The rest of lot 1, to the A2, opened in July 2024. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews). | Opened | 6 km |
| – |
|
| 12 mo design · 30 mo execution · 42 mo total · Contract value lei 830.68M |
| South lot 2: Jilava (CF902) – DN5 Eastern part of south lot 2 (CF902 Jilava – DN6, 16.30 km), opened in April 2024, four months after DN5 – DN6 (130km.ro). Contract signed with Alsim Alarko on 9 March 2019. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews). | Opened | 6 km |
| – |
|
| 12 mo design · 30 mo execution · 42 mo total · Contract value lei 750.85M |
| South lot 2: DN5 – DN6 (Bragadiru) First section of the south ring to open, in December 2023 (130km.ro). The rest of lot 2, Jilava – DN5, followed in April 2024. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews). | Opened | 10 km |
| – |
|
| 12 mo design · 30 mo execution · 42 mo total · Contract value lei 750.85M |
| South lot 3: DN6 (Bragadiru) – A1 – DJ601 Signed on 14 April 2019 with Aktor – Euroconstruct Trading; Aktor later took over the whole contract. Opened in June 2025, completing the south ring (130km.ro, ro.wikipedia). 130km.ro gives the length as 17.97 km. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews). | Opened | 18 km |
| – |
|
| 12 mo design · 30 mo execution · 42 mo total · Contract value lei 853.422M |
| North half-ring: A2 – DN2 Bucharest ring motorway, found eligible for EU financing after the 2016 traffic studies. Lot 4 (Pantelimon – Glina, 4.47 km) reached 99% physical progress in June 2026 but cannot open before Lot 3, because without it Lot 4 has no outlet (Mediafax, 27 June 2026). For Lot 3 (Afumați – Pantelimon), CNAIR reported the contractor's commitment to open traffic on 10 October 2026, at about 94% progress (Cine Construiește, 29 August 2026). 130km.ro records 2.3 km of lot 3 open since December 2024, next to north lot 2. It is not drawn separately: its extent is not published, and OpenStreetMap maps only about 0.4 km of lot 3 as open motorway. | Under construction 45 of 18 contracted months 27 months past the contract date | 14 km |
|
|
|
| 12 mo design · 18 mo execution |
| North half-ring: DN2 – DN1 (via A3) North ring lot 2 (Corbeanca–Afumați, 19 km): Spedition UMB entered site November 2021, building permit issued July 2022 | Opened | 19 km |
|
|
|
| 12 mo design · 22 mo execution · Contract value lei 831.92M |
| North half-ring: DN1 – A1 (via Buftea) Bucharest ring motorway, found eligible for EU financing after the 2016 traffic studies. OpenStreetMap tags construction:opening_date=2026 on the A0 Nord Lot 1 (Bâcu–Corbeanca) construction ways | Under construction 19 of 22 contracted months | 18 km |
|
|
|
| 12 mo design · 22 mo execution · 34 mo total · Contract value lei 815.08M |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union102 km8 sections
- Found eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
- EU funds
- National budget102 km8 sections
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysA7 Motorway (Moldavia Motorway)Same contractor: Impresa Pizzarotti, Retter, SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysA1 Bucharest–Nădlac MotorwaySame contractor: SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysA3 Transylvania Motorway (Brașov–Cluj–Borș)Same contractor: SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysA8 Târgu Mureș–Iași–Ungheni Motorway (Unirii)Same contractor: SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysFocșani – Brăila ExpresswaySame contractor: SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysCraiova–Pitești Expressway (DEx12)Same contractor: SA&PE Construct, Spedition UMB, Tehnostrade
Sources
- Wikipedia: Bucharest Ring Motorway
- Wikipedia (ro): Autostrada A0 (România)
- OpenStreetMap contributors (geometry, ODbL)
- digi24.ro
- profit.ro
- Economedia.ro: Autostrada Bucureștiului A0 Nord. Lotul 4 Pantelimon – Glina se apropie de finalizare, va face legătura cu Autostrada Soarelui (8 February 2026)read Sep 25, 2026
- Economedia.ro: Autostrada A0 București Nord: Pizzarotti-Retter a primit autorizație de construire completă pe Lotul 1 (29 January 2025)read Sep 25, 2026
- HotNews.ro: Autostrada de Centură Sud (A0) a Capitalei are acum constructori pe toată lungimea: ultimul tronson a fost semnat cu turcii de la Alsim Alarko pentru 177 mil. euro (26 August 2019)read Sep 25, 2026
- Economica.net: Autostrada Bucureștiului A0: Ce lucrări mai trebuie executate la pasajul DN3, pentru ca lotul chinezilor să fie în trafic la finalul lunii viitoare (15 September 2026)read Sep 25, 2026
- Economedia.ro: Autostrada Bucureștiului A0 Nord. Grupul Retter: Lotul 1 al A0 Nord, între DN1A și DN1, va fi finalizat înainte de termenul contractual (25 June 2026)read Sep 28, 2026
- Mediafax: Un lot din A0 Nord este aproape de recepția finală, dar nu va fi dat încă în circulațieread Sep 28, 2026
- Cine Construiește: Două noi loturi de pe A0 Nord ar urma să fie deschise până în octombrieread Sep 28, 2026
- Ziua Cargo: Loturile 1, 2 și 3 ale Autostrăzii de Centura București Nord, la licitație (5 June 2019)read Oct 1, 2026
- HotNews.ro: Autostrada de Centură (A0) a Capitalei – Nord: Ultimul tronson, scos la licitație (4 March 2020)read Oct 1, 2026
- 130km.ro: Autostrada A0 Centura București (lots, contract prices and opening dates)read Oct 2, 2026
- 130km.ro: Review autostrăzi și drumuri expres, trimestrul III 2026 (30 September 2026)read Oct 2, 2026