Highways

A0 Bucharest Ring Motorway

Outer motorway ring around Bucharest, about 101 km when complete, running beyond the existing Bucharest Ring Road and linking the A1, A2 and A3 motorways. The southern half-ring (51.2 km) opened in stages between December 2023 and June 2025. On the northern half-ring, the DN1–A3–DN2 section opened in November 2023 and December 2024; the western (A1–DN1) and eastern (DN2–A2) lots are still under construction.

Total length
102 km
Open today
70 km
Under construction
32 km
Sections
8
Cost on record
€662.364M
3 of 8 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A0 Bucharest Ring Motorway: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
South lot 1: A2 – Popești-Leordeni (DN4)

Eastern part of south lot 1 (A2 – CF902 Jilava, 16.93 km), whose contract also covers a 700 m sector of the north ring at the A2 junction (km 52+070 – 52+770). Opened in July 2024, three months after the lot's western 6.0 km (130km.ro). The 10.93 km is the lot's 16.93 km less those 6.0 km, so it includes the 700 m north-ring sector. Contract signed with Alsim Alarko on 26 August 2019. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews).

Opened11 km
  1. Dec 2012Announced
  2. 2019Construction start
  3. Aug 26, 2019Tender awarded
  4. Jul 2024Opened
–
  • European UnionFound eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
  • National budget
  • Alsim Alarko (south lot 1)Builder
12 mo design · 30 mo execution · 42 mo total · Contract value lei 830.68M
South lot 1: Popești-Leordeni (DN4) – Jilava (CF902)

Western part of south lot 1, opened in April 2024 together with Jilava – DN5 of lot 2 (130km.ro). The rest of lot 1, to the A2, opened in July 2024. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews).

Opened6 km
  1. Dec 2012Announced
  2. 2019Construction start
  3. Aug 26, 2019Tender awarded
  4. Apr 2024Opened
–
  • European UnionFound eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
  • National budget
  • Alsim Alarko (south lot 1)Builder
12 mo design · 30 mo execution · 42 mo total · Contract value lei 830.68M
South lot 2: Jilava (CF902) – DN5

Eastern part of south lot 2 (CF902 Jilava – DN6, 16.30 km), opened in April 2024, four months after DN5 – DN6 (130km.ro). Contract signed with Alsim Alarko on 9 March 2019. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews).

Opened6 km
  1. Dec 2012Announced
  2. 2019Construction start
  3. Mar 9, 2019Tender awarded
  4. Apr 2024Opened
–
  • European UnionFound eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
  • National budget
  • Alsim Alarko (south lot 2)Builder
12 mo design · 30 mo execution · 42 mo total · Contract value lei 750.85M
South lot 2: DN5 – DN6 (Bragadiru)

First section of the south ring to open, in December 2023 (130km.ro). The rest of lot 2, Jilava – DN5, followed in April 2024. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews).

Opened10 km
  1. Dec 2012Announced
  2. 2019Construction start
  3. Mar 9, 2019Tender awarded
  4. Dec 2023Opened
–
  • European UnionFound eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
  • National budget
  • Alsim Alarko (south lot 2)Builder
12 mo design · 30 mo execution · 42 mo total · Contract value lei 750.85M
South lot 3: DN6 (Bragadiru) – A1 – DJ601

Signed on 14 April 2019 with Aktor – Euroconstruct Trading; Aktor later took over the whole contract. Opened in June 2025, completing the south ring (130km.ro, ro.wikipedia). 130km.ro gives the length as 17.97 km. The July 2017 tender for the whole 52 km south ring was estimated at €580M (HotNews).

Opened18 km
  1. Dec 2012Announced
  2. 2019Construction start
  3. Apr 14, 2019Tender awarded
  4. Jun 2025Opened
–
  • European UnionFound eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
  • National budget
  • Aktor (south lot 3)Builder
12 mo design · 30 mo execution · 42 mo total · Contract value lei 853.422M
North half-ring: A2 – DN2

Bucharest ring motorway, found eligible for EU financing after the 2016 traffic studies. Lot 4 (Pantelimon – Glina, 4.47 km) reached 99% physical progress in June 2026 but cannot open before Lot 3, because without it Lot 4 has no outlet (Mediafax, 27 June 2026). For Lot 3 (Afumați – Pantelimon), CNAIR reported the contractor's commitment to open traffic on 10 October 2026, at about 94% progress (Cine Construiește, 29 August 2026). 130km.ro records 2.3 km of lot 3 open since December 2024, next to north lot 2. It is not drawn separately: its extent is not published, and OpenStreetMap maps only about 0.4 km of lot 3 as open motorway.

Under construction
45 of 18 contracted months
27 months past the contract date
14 km
  1. 2023Construction start
  2. Oct 2026Expected opening
  • Estimated lei 314.663Mworks onlyNorth lot 4 (Cernica – A2, km 47+600 – km 52+070, 4.5 km) only: estimated contract value 314,662,587 lei. VAT treatment not stated in the source.
  • European UnionEU funds
  • National budget
  • CCECC (north lot 3, Afumați–Pantelimon)Builder
  • Spedition UMB (north lot 4, Pantelimon–Manolache)Builder
12 mo design · 18 mo execution
North half-ring: DN2 – DN1 (via A3)

North ring lot 2 (Corbeanca–Afumați, 19 km): Spedition UMB entered site November 2021, building permit issued July 2022

Opened19 km
  1. May 12, 2021Tender awarded
  2. Nov 2021Construction start
  3. Dec 2024Opened
  • Estimated lei 880Mworks onlyExcluding VAT. North lot 2 (DN1 Corbeanca – DN2 Afumați, 19 km), design and build tender estimate.
  • European UnionEU funds
  • National budget
  • Spedition UMB (north lot 2, Corbeanca–Afumați)Builder
  • SA & PE Construct (north lot 2, association leader)Builder
  • Tehnostrade (north lot 2)Builder
12 mo design · 22 mo execution · Contract value lei 831.92M
North half-ring: DN1 – A1 (via Buftea)

Bucharest ring motorway, found eligible for EU financing after the 2016 traffic studies. OpenStreetMap tags construction:opening_date=2026 on the A0 Nord Lot 1 (Bâcu–Corbeanca) construction ways

Under construction
19 of 22 contracted months
18 km
  1. Sep 2023Tender awarded
  2. Mar 2025Construction start
  3. 2026Expected opening
  • Estimated lei 842Mworks onlyExcluding VAT. North lot 1 (DJ601A Dragomirești Vale – Bâcu to DN1 Corbeanca, 17.5 km), design and build tender estimate.
  • European UnionEU funds
  • National budget
  • Impresa Pizzarotti – Retter (north lot 1, Bâcu–Corbeanca)Builder
12 mo design · 22 mo execution · 34 mo total · Contract value lei 815.08M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union102 km
    8 sections
    • Found eligible for EU funding after 2016 traffic studies (no EU financing was sought under the 2014 General Transport Master Plan)
    • EU funds
  • National budget102 km
    8 sections

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia: Bucharest Ring Motorway
  2. Wikipedia (ro): Autostrada A0 (România)
  3. OpenStreetMap contributors (geometry, ODbL)
  4. digi24.ro
  5. profit.ro
  6. Economedia.ro: Autostrada Bucureștiului A0 Nord. Lotul 4 Pantelimon – Glina se apropie de finalizare, va face legătura cu Autostrada Soarelui (8 February 2026)read Sep 25, 2026
  7. Economedia.ro: Autostrada A0 București Nord: Pizzarotti-Retter a primit autorizație de construire completă pe Lotul 1 (29 January 2025)read Sep 25, 2026
  8. HotNews.ro: Autostrada de Centură Sud (A0) a Capitalei are acum constructori pe toată lungimea: ultimul tronson a fost semnat cu turcii de la Alsim Alarko pentru 177 mil. euro (26 August 2019)read Sep 25, 2026
  9. Economica.net: Autostrada Bucureștiului A0: Ce lucrări mai trebuie executate la pasajul DN3, pentru ca lotul chinezilor să fie în trafic la finalul lunii viitoare (15 September 2026)read Sep 25, 2026
  10. Economedia.ro: Autostrada Bucureștiului A0 Nord. Grupul Retter: Lotul 1 al A0 Nord, între DN1A și DN1, va fi finalizat înainte de termenul contractual (25 June 2026)read Sep 28, 2026
  11. Mediafax: Un lot din A0 Nord este aproape de recepția finală, dar nu va fi dat încă în circulațieread Sep 28, 2026
  12. Cine Construiește: Două noi loturi de pe A0 Nord ar urma să fie deschise până în octombrieread Sep 28, 2026
  13. Ziua Cargo: Loturile 1, 2 și 3 ale Autostrăzii de Centura București Nord, la licitație (5 June 2019)read Oct 1, 2026
  14. HotNews.ro: Autostrada de Centură (A0) a Capitalei – Nord: Ultimul tronson, scos la licitație (4 March 2020)read Oct 1, 2026
  15. 130km.ro: Autostrada A0 Centura București (lots, contract prices and opening dates)read Oct 2, 2026
  16. 130km.ro: Review autostrăzi și drumuri expres, trimestrul III 2026 (30 September 2026)read Oct 2, 2026