Skip to content
InfraWorldWide
← All projects
Highways

A7 Motorway (Moldavia Motorway)

Partially built motorway that will link Ploiești (A3) to the Ukrainian border at Siret via Buzău, Focșani, Bacău, Roman, Pașcani and Suceava, partly along Pan-European Corridor IX. As of December 2025, 211.9 km are open (Dumbrava–Adjud and the Bacău bypass), 185.3 km are under construction (Adjud–Suceava) and the 56.1 km Suceava–Siret section is tendered, out of 453.3 km planned. The Pașcani–Siret section is to be co-financed from EU funds, while Ploiești–Pașcani is to be financed through the Romanian PNRR (Next Generation EU).

Total length
454 km
Open today
259 km
Under construction
77 km
Sections
16
Cost on record
€3.7B
12 of 16 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A7 Motorway (Moldavia Motorway): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Dumbrava (A3) – Mizil (Ploiești–Buzău lot 1)

Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026

Opened21 km
  1. 2022Construction start
  2. Jun 16, 2022Tender awarded
  3. Dec 23, 2024Opened
  • Estimated lei 1.7Bworks onlyTender estimate range 1,655–1,952 million lei excluding VAT; lower bound recorded.
  • European UnionPNRR (Next Generation EU)
  • Impresa PizzarottiBuilder
  • RetterBuilder
20 mo execution · Contract value lei 1.5B
Mizil – Stâlpu (Ploiești–Buzău lot 2)

Ploiești–Buzău tendered July 2021 in three lots: lot 1 Dumbrava–Mizil (km 0–21), lot 2 Mizil–Stâlpu (km 21+000–49+350), lot 3 Stâlpu–Buzău (km 49+350–63+250). Opening months corroborated by the exit list: Mizil (km 21) July 2025, Sărata (km 39) October 2025, Spătaru (km 53) November 2025, Buzău Est (km 62) July 2025

Opened28 km
  1. Jun 7, 2022Tender awarded
  2. Aug 12, 2022Construction start
  3. Oct 17, 2025Opened
  • Estimated lei 1.5Bworks onlyTender estimate range 1,475–1,741 million lei excluding VAT; lower bound recorded.
  • European UnionPNRR (Next Generation EU)
  • ConiBuilder
  • TraceBuilder
20 mo execution · Contract value lei 1.2B
Stâlpu – Buzău (Ploiești–Buzău lot 3)

Ploiești–Buzău tendered July 2021 in three lots: lot 1 Dumbrava–Mizil (km 0–21), lot 2 Mizil–Stâlpu (km 21+000–49+350), lot 3 Stâlpu–Buzău (km 49+350–63+250). Opening months corroborated by the exit list: Mizil (km 21) July 2025, Sărata (km 39) October 2025, Spătaru (km 53) November 2025, Buzău Est (km 62) July 2025

Opened14 km
  1. 2022Tender awarded
  2. Mar 1, 2024Construction start
  3. Nov 27, 2025Opened
  • Estimated lei 1.2Bworks onlyTender estimate range 1,160–1,369 million lei excluding VAT; lower bound recorded.
  • European UnionPNRR (Next Generation EU)
  • NurolBuilder
20 mo execution · Contract value lei 1.1B
Buzău bypass

Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026

Opened5 km
  1. 2022Construction start
  2. Sep 6, 2022Tender awarded
  3. Jul 2025Opened
  • Estimated lei 858.85Mworks onlyTender estimate range 858.85–1,010 million lei excluding VAT; lower bound recorded.
  • European UnionPNRR (Next Generation EU)
  • SA&PEBuilder
  • Spedition UMBBuilder
  • TehnostradeBuilder
20 mo execution · Contract value lei 689.28M
Buzău – Râmnicu Sărat

Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026

Opened31 km
  1. Jan 12, 2023Tender awarded
  2. Feb 2023Construction start
  3. Nov 21, 2024Opened
  • Estimated lei 1.6Bworks onlyTender estimate range 1,640–1,940 million lei excluding VAT; lower bound recorded.
  • European UnionPNRR (Next Generation EU)
  • Spedition UMBBuilder
  • SA&PE ConstructBuilder
  • TehnostradeBuilder
26 mo execution · Contract value lei 1.3B
Râmnicu Sărat – Mândrești-Munteni

Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026

Opened36 km
  1. Jan 12, 2023Tender awarded
  2. Feb 2023Construction start
  3. Dec 20, 2024Opened
  • Estimated lei 1.8Bworks onlyTender estimate range 1,830–2,160 million lei excluding VAT; lower bound recorded.
  • European UnionPNRR (Next Generation EU)
  • Spedition UMBBuilder
  • SA&PE ConstructBuilder
  • TehnostradeBuilder
26 mo execution · 120 mo guarantee · Contract value lei 1.5B
Focșani bypass (Buzău–Focșani lot 4)

Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026

Opened11 km
  1. 2022Construction start
  2. Sep 6, 2022Tender awarded
  3. Nov 7, 2024Opened
  • Estimated lei 954.65Mworks onlyTender estimate range 954.65–1,130 million lei excluding VAT; lower bound recorded.
  • European UnionPNRR (Next Generation EU)
  • SA&PEBuilder
  • Spedition UMBBuilder
  • TehnostradeBuilder
20 mo execution · Contract value lei 763.72M
Focșani – Domnești-Târg (Focșani–Bacău lot 1)

Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026

Opened36 km
  1. Dec 2022Tender awarded
  2. Mar 29, 2023Construction start
  3. Dec 2025Opened
  • Estimated lei 3Bworks onlyTender estimate, excluding VAT.
  • European UnionPNRR (Next Generation EU)
  • Spedition UMB - SA&PE Construct - TehnostradeBuilder
30 mo execution · Contract value lei 2.4B
Domnești-Târg – Adjud

Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026

Opened16 km
  1. Dec 2022Tender awarded
  2. May 3, 2023Construction start
  3. Dec 13, 2025Opened
–
  • European UnionPNRR (Next Generation EU)
  • Spedition UMBBuilder
–
Bacău bypass

CNAIR contract signed 22 December 2018 with Spedition UMB–Tehnostrade: €142M, 36 months for construction, 7-year guarantee (opened 2 years ahead of term)

Opened16 km
  1. Dec 22, 2018Tender awarded
  2. Mar 8, 2019Construction start
  3. Dec 2, 2020Opened
  • Estimated €142M(2018)
  • European UnionCohesion Fund via the Large Infrastructure Operational Programme (POIM) 2014–2020, financing contract no. 50/26.11.2019, project code 120235
  • Spedition UMBBuilder
  • TehnostradeBuilder
6 mo design · 30 mo execution · 36 mo total · 84 mo guarantee · Contract value €142M
Adjud – Bacău Sud

Focșani–Bacău lots 2–3 (Domnești-Târg–Răcăciuni, Răcăciuni–Bacău Sud) awarded November 2022 and signed December 2022 with Spedition UMB; PNRR-funded. CNAIR opened 47.1 km from Adjud Nord to Bacău at 16:00 on 31 August 2026, the last day of the PNRR instrument, first as far as the DN2F junction towards Vaslui while the Bacău Nord junction was finished

Opened46 km
  1. Dec 2022Tender awarded
  2. May 3, 2023Construction start
  3. Aug 31, 2026Opened
–
  • European UnionPNRR (Next Generation EU)
  • Spedition UMBBuilder
–
Bacău – Roman (Bacău–Pașcani lot 1)

Bacău–Pașcani lot 1 (Săucești–Trifești, 30.3 km) awarded December 2022 to the Spedition UMB – SA&PE Construct – Tehnostrade association; PNRR-funded. It missed the PNRR deadline of 31 August 2026 and moves to the Transport Programme from 2027; the ministry's stated aim is to open the A7 as far as Săbăoani by the end of 2026

Under construction
41 of 30 contracted months
11 months past the contract date
30 km
  1. Dec 2022Tender awarded
  2. May 2, 2023Construction start
  3. 2026Expected opening
  • Estimated lei 2Bworks onlyTender estimate, excluding VAT.
  • European UnionPNRR (Next Generation EU)
  • Spedition UMBBuilder
  • SA&PE ConstructBuilder
  • TehnostradeBuilder
30 mo execution · 150 mo total · 120 mo guarantee · Contract value lei 1.6B
Roman – Săbăoani (Bacău–Pașcani lot 2)

Bacău–Pașcani lot 2 (Trifești–Gherăești, 18.99 km) awarded December 2022 to the Spedition UMB – SA&PE Construct – Tehnostrade association; PNRR-funded. It missed the PNRR deadline of 31 August 2026 and moves to the Transport Programme from 2027; the ministry's stated aim is to open the A7 as far as Săbăoani by the end of 2026

Under construction
41 of 30 contracted months
11 months past the contract date
19 km
  1. Dec 2022Tender awarded
  2. May 2, 2023Construction start
  3. 2026Expected opening
  • Estimated lei 1.6Bworks onlyTender estimate, excluding VAT.
  • European UnionPNRR (Next Generation EU)
  • Spedition UMBBuilder
  • SA&PE ConstructBuilder
  • TehnostradeBuilder
30 mo execution · 150 mo total · 120 mo guarantee · Contract value lei 1.3B
Săbăoani – Pașcani (Bacău–Pașcani lot 3)

Bacău–Pașcani lot 3 (Mircești–Pașcani, 28.09 km) awarded December 2022 to the Spedition UMB – SA&PE Construct – Tehnostrade association; PNRR-funded. It missed the PNRR deadline of 31 August 2026; state secretary Horațiu Cosma said on that day that the lot would realistically run two to three months into 2027

Under construction
41 of 30 contracted months
11 months past the contract date
28 km
  1. Dec 2022Tender awarded
  2. May 2, 2023Construction start
  3. 2027Expected opening
  • Estimated lei 2.2Bworks onlyTender estimate, excluding VAT.
  • European UnionPNRR (Next Generation EU)
  • Spedition UMBBuilder
  • SA&PE ConstructBuilder
  • TehnostradeBuilder
30 mo execution · 150 mo total · 120 mo guarantee · Contract value lei 1.8B
Pașcani – Suceava

Design-and-build, signed 1 May 2026 as two contracts: lot 1 Pașcani–Roșcani and lot 2 Roșcani–Suceava (to km 61+970). Each runs 30 months (6 design, 24 works), both in parallel, with a 10-year works guarantee. No start of works had been reported by September 2026, so the lot is shown as tendered.

Tendered62 km
  1. May 1, 2026Tender awarded
  2. 2029Expected opening
  • Estimated lei 7.8Bworks onlyPre-award estimated construction value for the whole 62 km Pașcani–Suceava sector (lots 1 and 2), excluding VAT, as reported when lot 1 was tendered in July 2024.
  • European UnionTransport Programme 2021–2027 (EU non-reimbursable funds) for now
  • LoanLater to be financed through SAFE (Security Action for Europe), an EU long-term loan instrument
  • SA&PE ConstructBuilder
  • Spedition UMBBuilder
  • TehnostradeBuilder
6 mo design · 24 mo execution · 30 mo total · 120 mo guarantee · Contract value lei 5.9B
Suceava – Siret (Ukrainian border)

Tendered in three lots totalling 55.7 km: Suceava – Dărmănești (18.6 km), Dărmănești – Bălcăuți (24.5 km) and Bălcăuți – Vama Siret (12.7 km). Lots 1 and 2 were signed in May 2026, but the court annulled their award on 18 September 2026 and the offers go back to evaluation; lot 3 is still in tender. The listed builders are the association that won all three lots before the ruling. Libertatea's July 2026 motorway map, relaying 130km.ro, puts the Suceava–Siret opening in 2029. This is a press forecast, not an official date. North of Milișăuți (Rădăuți) the road is planned as an expressway to the border.

Tendered56 km–
  • Estimated lei 7.4BTotal investment in the technical-economic indicators approved by government decision on 26 March 2026: 'peste 7,4 miliarde lei'. VAT treatment not stated.
  • LoanSAFE (Security Action for Europe), an EU long-term loan instrument
  • Far FoundationBuilder
  • Automagistral PivdenBuilder
  • Lincor TransBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union398 km
    15 sections
    • PNRR (Next Generation EU)
    • Cohesion Fund via the Large Infrastructure Operational Programme (POIM) 2014–2020, financing contract no. 50/26.11.2019, project code 120235
    • Transport Programme 2021–2027 (EU non-reimbursable funds) for now
  • Loan118 km
    2 sections
    • Later to be financed through SAFE (Security Action for Europe), an EU long-term loan instrument
    • SAFE (Security Action for Europe), an EU long-term loan instrument

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • Pan-European Corridor IXPan-European

Sources

  1. Wikipedia: A7 motorway (Romania)
  2. Wikipedia (ro): Autostrada A7 (România)
  3. HotNews: A fost deschis traficul pe o nouă secțiune din Autostrada Moldovei / Alte trei loturi din A7 ratează termenul PNRR (31 August 2026)read Sep 24, 2026
  4. G4Media: Încă 47 de kilometri din Autostrada Moldovei, între Adjud și Bacău, au fost deschiși circulației (31 August 2026)read Sep 24, 2026
  5. OpenStreetMap contributors (geometry, ODbL)
  6. rettergroup.com
  7. traficmedia.ro
  8. economica.net
  9. constructiv.ro
  10. economica.net
  11. constructiv.ro
  12. agerpres.ro
  13. ziuacargo.ro
  14. hotnews.ro
  15. stiridevrancea.ro
  16. hotnews.ro
  17. web.archive.org (dates.constructionStart)
  18. hotnews.ro (contract.totalMonths)
  19. Wikipedia (ro): Autostrada A7 (România)#Construcția finanțată prin PNRR
  20. CNAIR: CNAIR a semnat contractele pentru proiectarea și construcția Autostrăzii Pașcani – Suceava (1 May 2026)read Sep 25, 2026
  21. Agenda Construcțiilor: UMB semnează pentru A7 Pașcani-Suceava (lot 1 și 2): 62 de km pentru 5,9 miliarde lei (6 May 2026)read Sep 25, 2026
  22. Economedia: Drumul Expres Suceava - Siret. Contestații respinse și pentru lotul 3 / Drumul va fi construit cu banii din programul european SAFE (4 June 2026)read Sep 25, 2026
  23. CNAIR: CNAIR a semnat contractele necesare construcției celor 3 loturi ale Autostrăzii Bacău – Pașcani, parte din A7 (15 February 2023)read Sep 25, 2026
  24. Economica.net: Autostrada Bacău - Pașcani: E oficial! Umbrărescu a fost desemnat câștigător pe lotul 1 (22 December 2022)read Sep 25, 2026
  25. CNAIR: S-au semnat contractele pentru construcția ultimelor două loturi ale autostrăzii Buzău – Focșani (12 January 2023)read Sep 25, 2026
  26. Agerpres: Execuţia autostrăzii Ploieşti - Buzău, scoasă la licitaţie; valoarea maximă estimată depăşeşte 5 miliarde de lei (1 June 2021)read Sep 25, 2026
  27. Economica.net: Autostrada A7 Buzău - Focșani: A fost publicată prima licitație pentru loturile 1 și 4 (5 February 2022)read Sep 25, 2026
  28. CNAIR: Începe licitația și pentru construcția sectorului de autostrada Focșani – Bacău! (3 August 2022)read Sep 25, 2026
  29. CNAIR: Varianta de ocolire Bacău (Act Adițional nr.1 la Contractul de Finanțare nr. 50/26.11.2019)read Sep 25, 2026
  30. Capital: CNAIR a semnat contractele necesare construcţiei celor 3 loturi ale Autostrăzii Bacău – Paşcani (15 February 2023)read Sep 25, 2026
  31. HotNews: Autostrada „Moldovei” A7: A fost scos la licitație un tronson de 77 km estimat la 1,2 mld euro (26 July 2022)read Sep 25, 2026
  32. Campus TV Buzău: Autostrada Buzău – Focșani, acoperită de contracte. Tronsonul va fi construit de compania lui Umbrărescu (13 January 2023)read Sep 25, 2026
  33. Agerpres: Șerban: A fost aprobată Hotărârea de Guvern privind indicatorii tehnico-economici pentru DEx Suceava-Siret (26 March 2026)read Sep 25, 2026
  34. Libertatea: Harta autostrăzilor și drumurilor expres din România în iulie 2026 (7 July 2026)read Sep 25, 2026
  35. APIX: Stadiul lucrărilor la fiecare segment din autostrada A7 Ploiești – Pașcani (24 October 2024)read Sep 28, 2026
  36. Economedia: Autostrada Pașcani – Suceava, lot 1: CNAIR scoate la licitație primii 33 km (18 July 2024)read Sep 28, 2026
  37. Economica.net: Autostrada Buzău - Focșani: A fost publicat anunțul de licitație pentru tronsoanele 2 și 3 (11 February 2022)read Oct 1, 2026
  38. 130km.ro: Review autostrazi si drumuri expres - Trimestrul I 2026read Oct 2, 2026
  39. 130km.ro: Review autostrazi si drumuri expres - Trimestrul II 2026read Oct 2, 2026
  40. 130km.ro: Review autostrazi si drumuri expres - Trimestrul III 2026 (30 September 2026)read Oct 2, 2026
  41. Economedia: Atribuire anulată pentru contracte deja semnate prin programul SAFE / Curtea de Apel obligă CNAIR să reevalueze ofertele pentru primele două loturi din Drumul Expres Suceava – Siret (18 September 2026)read Oct 2, 2026
  42. CNAIR: Infrastructure project status, September 2025 (copy hosted by Forum Metrou Usor)read Oct 12, 2026