A7 Motorway (Moldavia Motorway)
Partially built motorway that will link Ploiești (A3) to the Ukrainian border at Siret via Buzău, Focșani, Bacău, Roman, Pașcani and Suceava, partly along Pan-European Corridor IX. As of December 2025, 211.9 km are open (Dumbrava–Adjud and the Bacău bypass), 185.3 km are under construction (Adjud–Suceava) and the 56.1 km Suceava–Siret section is tendered, out of 453.3 km planned. The Pașcani–Siret section is to be co-financed from EU funds, while Ploiești–Pașcani is to be financed through the Romanian PNRR (Next Generation EU).
- Total length
- 454 km
- Open today
- 259 km
- Under construction
- 77 km
- Sections
- 16
- Cost on record
- €3.7B
- 12 of 16 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Dumbrava (A3) – Mizil (Ploiești–Buzău lot 1) Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026 | Opened | 21 km |
|
|
|
| 20 mo execution · Contract value lei 1.5B |
| Mizil – Stâlpu (Ploiești–Buzău lot 2) Ploiești–Buzău tendered July 2021 in three lots: lot 1 Dumbrava–Mizil (km 0–21), lot 2 Mizil–Stâlpu (km 21+000–49+350), lot 3 Stâlpu–Buzău (km 49+350–63+250). Opening months corroborated by the exit list: Mizil (km 21) July 2025, Sărata (km 39) October 2025, Spătaru (km 53) November 2025, Buzău Est (km 62) July 2025 | Opened | 28 km |
|
|
|
| 20 mo execution · Contract value lei 1.2B |
| Stâlpu – Buzău (Ploiești–Buzău lot 3) Ploiești–Buzău tendered July 2021 in three lots: lot 1 Dumbrava–Mizil (km 0–21), lot 2 Mizil–Stâlpu (km 21+000–49+350), lot 3 Stâlpu–Buzău (km 49+350–63+250). Opening months corroborated by the exit list: Mizil (km 21) July 2025, Sărata (km 39) October 2025, Spătaru (km 53) November 2025, Buzău Est (km 62) July 2025 | Opened | 14 km |
|
|
|
| 20 mo execution · Contract value lei 1.1B |
| Buzău bypass Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026 | Opened | 5 km |
|
|
|
| 20 mo execution · Contract value lei 689.28M |
| Buzău – Râmnicu Sărat Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026 | Opened | 31 km |
|
|
|
| 26 mo execution · Contract value lei 1.3B |
| Râmnicu Sărat – Mândrești-Munteni Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026 | Opened | 36 km |
|
|
|
| 26 mo execution · 120 mo guarantee · Contract value lei 1.5B |
| Focșani bypass (Buzău–Focșani lot 4) Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026 | Opened | 11 km |
|
|
|
| 20 mo execution · Contract value lei 763.72M |
| Focșani – Domnești-Târg (Focșani–Bacău lot 1) Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026 | Opened | 36 km |
|
|
|
| 30 mo execution · Contract value lei 2.4B |
| Domnești-Târg – Adjud Financed through the Romanian PNRR (Next Generation EU), an instrument running to 2026 | Opened | 16 km |
| – |
|
| – |
| Bacău bypass CNAIR contract signed 22 December 2018 with Spedition UMB–Tehnostrade: €142M, 36 months for construction, 7-year guarantee (opened 2 years ahead of term) | Opened | 16 km |
|
|
|
| 6 mo design · 30 mo execution · 36 mo total · 84 mo guarantee · Contract value €142M |
| Adjud – Bacău Sud Focșani–Bacău lots 2–3 (Domnești-Târg–Răcăciuni, Răcăciuni–Bacău Sud) awarded November 2022 and signed December 2022 with Spedition UMB; PNRR-funded. CNAIR opened 47.1 km from Adjud Nord to Bacău at 16:00 on 31 August 2026, the last day of the PNRR instrument, first as far as the DN2F junction towards Vaslui while the Bacău Nord junction was finished | Opened | 46 km |
| – |
|
| – |
| Bacău – Roman (Bacău–Pașcani lot 1) Bacău–Pașcani lot 1 (Săucești–Trifești, 30.3 km) awarded December 2022 to the Spedition UMB – SA&PE Construct – Tehnostrade association; PNRR-funded. It missed the PNRR deadline of 31 August 2026 and moves to the Transport Programme from 2027; the ministry's stated aim is to open the A7 as far as Săbăoani by the end of 2026 | Under construction 41 of 30 contracted months 11 months past the contract date | 30 km |
|
|
|
| 30 mo execution · 150 mo total · 120 mo guarantee · Contract value lei 1.6B |
| Roman – Săbăoani (Bacău–Pașcani lot 2) Bacău–Pașcani lot 2 (Trifești–Gherăești, 18.99 km) awarded December 2022 to the Spedition UMB – SA&PE Construct – Tehnostrade association; PNRR-funded. It missed the PNRR deadline of 31 August 2026 and moves to the Transport Programme from 2027; the ministry's stated aim is to open the A7 as far as Săbăoani by the end of 2026 | Under construction 41 of 30 contracted months 11 months past the contract date | 19 km |
|
|
|
| 30 mo execution · 150 mo total · 120 mo guarantee · Contract value lei 1.3B |
| Săbăoani – Pașcani (Bacău–Pașcani lot 3) Bacău–Pașcani lot 3 (Mircești–Pașcani, 28.09 km) awarded December 2022 to the Spedition UMB – SA&PE Construct – Tehnostrade association; PNRR-funded. It missed the PNRR deadline of 31 August 2026; state secretary Horațiu Cosma said on that day that the lot would realistically run two to three months into 2027 | Under construction 41 of 30 contracted months 11 months past the contract date | 28 km |
|
|
|
| 30 mo execution · 150 mo total · 120 mo guarantee · Contract value lei 1.8B |
| Pașcani – Suceava Design-and-build, signed 1 May 2026 as two contracts: lot 1 Pașcani–Roșcani and lot 2 Roșcani–Suceava (to km 61+970). Each runs 30 months (6 design, 24 works), both in parallel, with a 10-year works guarantee. No start of works had been reported by September 2026, so the lot is shown as tendered. | Tendered | 62 km |
|
|
|
| 6 mo design · 24 mo execution · 30 mo total · 120 mo guarantee · Contract value lei 5.9B |
| Suceava – Siret (Ukrainian border) Tendered in three lots totalling 55.7 km: Suceava – Dărmănești (18.6 km), Dărmănești – Bălcăuți (24.5 km) and Bălcăuți – Vama Siret (12.7 km). Lots 1 and 2 were signed in May 2026, but the court annulled their award on 18 September 2026 and the offers go back to evaluation; lot 3 is still in tender. The listed builders are the association that won all three lots before the ruling. Libertatea's July 2026 motorway map, relaying 130km.ro, puts the Suceava–Siret opening in 2029. This is a press forecast, not an official date. North of Milișăuți (Rădăuți) the road is planned as an expressway to the border. | Tendered | 56 km | – |
|
|
| – |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union398 km15 sections
- PNRR (Next Generation EU)
- Cohesion Fund via the Large Infrastructure Operational Programme (POIM) 2014–2020, financing contract no. 50/26.11.2019, project code 120235
- Transport Programme 2021–2027 (EU non-reimbursable funds) for now
- Loan118 km2 sections
- Later to be financed through SAFE (Security Action for Europe), an EU long-term loan instrument
- SAFE (Security Action for Europe), an EU long-term loan instrument
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysA0 Bucharest Ring MotorwaySame contractor: Impresa Pizzarotti, Retter, SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysA3 Transylvania Motorway (Brașov–Cluj–Borș)Same contractor: Nurol, SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysA8 Târgu Mureș–Iași–Ungheni Motorway (Unirii)Same contractor: Nurol, SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysA1 Bucharest–Nădlac MotorwaySame contractor: SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysFocșani – Brăila ExpresswaySame contractor: SA&PE Construct, Spedition UMB, Tehnostrade
- HighwaysCraiova–Pitești Expressway (DEx12)Same contractor: SA&PE Construct, Spedition UMB, Tehnostrade
Corridors
The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.
- Pan-European Corridor IXPan-European
Sources
- Wikipedia: A7 motorway (Romania)
- Wikipedia (ro): Autostrada A7 (România)
- HotNews: A fost deschis traficul pe o nouă secțiune din Autostrada Moldovei / Alte trei loturi din A7 ratează termenul PNRR (31 August 2026)read Sep 24, 2026
- G4Media: Încă 47 de kilometri din Autostrada Moldovei, între Adjud și Bacău, au fost deschiși circulației (31 August 2026)read Sep 24, 2026
- OpenStreetMap contributors (geometry, ODbL)
- rettergroup.com
- traficmedia.ro
- economica.net
- constructiv.ro
- economica.net
- constructiv.ro
- agerpres.ro
- ziuacargo.ro
- hotnews.ro
- stiridevrancea.ro
- hotnews.ro
- web.archive.org (dates.constructionStart)
- hotnews.ro (contract.totalMonths)
- Wikipedia (ro): Autostrada A7 (România)#Construcția finanțată prin PNRR
- CNAIR: CNAIR a semnat contractele pentru proiectarea și construcția Autostrăzii Pașcani – Suceava (1 May 2026)read Sep 25, 2026
- Agenda Construcțiilor: UMB semnează pentru A7 Pașcani-Suceava (lot 1 și 2): 62 de km pentru 5,9 miliarde lei (6 May 2026)read Sep 25, 2026
- Economedia: Drumul Expres Suceava - Siret. Contestații respinse și pentru lotul 3 / Drumul va fi construit cu banii din programul european SAFE (4 June 2026)read Sep 25, 2026
- CNAIR: CNAIR a semnat contractele necesare construcției celor 3 loturi ale Autostrăzii Bacău – Pașcani, parte din A7 (15 February 2023)read Sep 25, 2026
- Economica.net: Autostrada Bacău - Pașcani: E oficial! Umbrărescu a fost desemnat câștigător pe lotul 1 (22 December 2022)read Sep 25, 2026
- CNAIR: S-au semnat contractele pentru construcția ultimelor două loturi ale autostrăzii Buzău – Focșani (12 January 2023)read Sep 25, 2026
- Agerpres: Execuţia autostrăzii Ploieşti - Buzău, scoasă la licitaţie; valoarea maximă estimată depăşeşte 5 miliarde de lei (1 June 2021)read Sep 25, 2026
- Economica.net: Autostrada A7 Buzău - Focșani: A fost publicată prima licitație pentru loturile 1 și 4 (5 February 2022)read Sep 25, 2026
- CNAIR: Începe licitația și pentru construcția sectorului de autostrada Focșani – Bacău! (3 August 2022)read Sep 25, 2026
- CNAIR: Varianta de ocolire Bacău (Act Adițional nr.1 la Contractul de Finanțare nr. 50/26.11.2019)read Sep 25, 2026
- Capital: CNAIR a semnat contractele necesare construcţiei celor 3 loturi ale Autostrăzii Bacău – Paşcani (15 February 2023)read Sep 25, 2026
- HotNews: Autostrada „Moldovei” A7: A fost scos la licitație un tronson de 77 km estimat la 1,2 mld euro (26 July 2022)read Sep 25, 2026
- Campus TV Buzău: Autostrada Buzău – Focșani, acoperită de contracte. Tronsonul va fi construit de compania lui Umbrărescu (13 January 2023)read Sep 25, 2026
- Agerpres: Șerban: A fost aprobată Hotărârea de Guvern privind indicatorii tehnico-economici pentru DEx Suceava-Siret (26 March 2026)read Sep 25, 2026
- Libertatea: Harta autostrăzilor și drumurilor expres din România în iulie 2026 (7 July 2026)read Sep 25, 2026
- APIX: Stadiul lucrărilor la fiecare segment din autostrada A7 Ploiești – Pașcani (24 October 2024)read Sep 28, 2026
- Economedia: Autostrada Pașcani – Suceava, lot 1: CNAIR scoate la licitație primii 33 km (18 July 2024)read Sep 28, 2026
- Economica.net: Autostrada Buzău - Focșani: A fost publicat anunțul de licitație pentru tronsoanele 2 și 3 (11 February 2022)read Oct 1, 2026
- 130km.ro: Review autostrazi si drumuri expres - Trimestrul I 2026read Oct 2, 2026
- 130km.ro: Review autostrazi si drumuri expres - Trimestrul II 2026read Oct 2, 2026
- 130km.ro: Review autostrazi si drumuri expres - Trimestrul III 2026 (30 September 2026)read Oct 2, 2026
- Economedia: Atribuire anulată pentru contracte deja semnate prin programul SAFE / Curtea de Apel obligă CNAIR să reevalueze ofertele pentru primele două loturi din Drumul Expres Suceava – Siret (18 September 2026)read Oct 2, 2026
- CNAIR: Infrastructure project status, September 2025 (copy hosted by Forum Metrou Usor)read Oct 12, 2026