A8 Târgu Mureș–Iași–Ungheni Motorway (Unirii)

Motorway of about 304 km, partly under construction, crossing the Eastern Carpathians to link Transylvania with Moldavia: from Târgu Mureș (A3) to Iași, then on to the Moldovan border at Ungheni (Prut crossing towards Chișinău). Also known as the Union Motorway (Autostrada Unirii) or East–West Motorway, it is part of the TEN-T Core Network. As of May 2026, eleven sections (~260 km) are under design and construction, the first contract (Leghin–Târgu Neamț) signed in September 2023; the last two sections (Târgu Frumos–Lețcani and Iași–Ungheni, ~44 km) are tendered.

Total length
300 km
Open today
0 km
Under construction
229 km
Sections
6
Cost on record
€4.6B
2 of 6 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A8 Târgu Mureș–Iași–Ungheni Motorway (Unirii): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Târgu Mureș – Ditrău (sections 1A–1D)

Section 1A Târgu Mureș–Miercurea Nirajului, contract signed 16 February 2024 (Nurol)

Under construction
16 of 24 contracted months
92 km
  1. Feb 16, 2024Tender awarded
  2. May 2025Construction start
  3. 2030Expected opening
  • Estimated €4.1B(2023)
  • European UnionPNRR (Next Generation EU): the Târgu Mureș–Miercurea Nirajului mountain-end lot carries an EU-imposed 2026 deadline
  • National budget
  • NurolBuilder
  • ÖzaltınBuilder
  • Spedition UMBBuilder
6 mo design · 24 mo execution
Ditrău – Moțca (DN2) (sections 2A–2C, 3)

Ditrău–Grințieș (section 2A) contract, SA&PE Construct–Tehnostrade–Euro Asfalt–Spedition UMB; Leghin–Târgu Neamț signed September 2023 at RON 1.56bn (≈€313M), 6 months design + 24 months execution

Under construction
36 of 40 contracted months
119 km
  1. Sep 2023Tender awarded
  2. Sep 2023Construction start
  3. ≈2027Expected openingProjected from contract
  • Estimated lei 1.6B(2023)
  • European UnionPNRR (Next Generation EU)
  • National budget
  • SA&PE Construct – Spedition UMB – TehnostradeBuilder
14 mo design · 40 mo execution · Contract value lei 1.6B
Moțca – Târgu Frumos (incl. A7 junction)

Tronson 1 Moțca–Târgu Frumos (27 km): CNIR designated the SA&PE Construct (leader) – Tehnostrade – Spedition UMB – Euro-Asfalt association on 24 April 2026 and signed the design-and-execution contract on 28 May 2026, RON 4.87bn excluding VAT, 46 months of which 10 for design and 36 for execution. Design runs from the CNIR start order of 24 August 2026, with works due from June 2027. A priority 5.5 km segment linking the A8 to DN2 and the A7 is contracted for 12 months. Danlin XXL had won the original October 2025 award at RON 4.76bn; it was overturned on appeal and the offers re-evaluated.

Under construction
5 of 46 contracted months
27 km
  1. Apr 24, 2026Tender awarded
  2. ≈2030Expected openingProjected from contract
  • Estimated lei 4.9B(2026)
  • European UnionSAFE (Security Action for Europe): the first Romanian motorway contract financed under the programme
  • National budget
  • SA&PE Construct – Tehnostrade – Spedition UMB – Euro AsfaltBuilder
10 mo design · 36 mo execution · 46 mo total · Contract value lei 4.9B
Târgu Frumos – Lețcani (sector 2)

Tendered section of the A8; the Ungheni road bridge over the Prut is to be financed from EU grants and the state budget

Tendered29 km
  • European UnionEU funds
  • National budget
Lețcani – Iași (sector 3)

Lețcani–Iași (sector 3, 17.7 km) execution contract with FCC Construcción

Under construction18 km
  1. 2024Construction start
  • European UnionEU funds
  • National budget
  • FCC ConstrucciónBuilder
Iași – Ungheni (Moldova border, sector 4)

Tendered section of the A8; the Ungheni road bridge over the Prut is to be financed from EU grants and the state budget

Tendered15 km
  • European UnionThe Ungheni road bridge over the Prut is to be financed from EU grants and the state budget
  • National budget

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union300 km
    6 sections
    • PNRR (Next Generation EU): the Târgu Mureș–Miercurea Nirajului mountain-end lot carries an EU-imposed 2026 deadline
    • PNRR (Next Generation EU)
    • SAFE (Security Action for Europe): the first Romanian motorway contract financed under the programme
    • EU funds
    • The Ungheni road bridge over the Prut is to be financed from EU grants and the state budget
  • National budget300 km
    6 sections

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • TEN-T core networkTEN-T

Sources

  1. Wikipedia: A8 motorway (Romania)
  2. Wikipedia (ro): Autostrada A8 (România)
  3. OpenStreetMap contributors (geometry, ODbL)
  4. jurnalul.ro (dates.constructionStart)
  5. punctul.ro (dates.expectedOpening)
  6. bursa.ro (dates.tenderAwarded, CNIR designation of 24 April 2026)
  7. economedia.ro (contract signature of 28 May 2026, value, contractors)
  8. hotnews.ro (contract.designMonths, length, overturned October 2025 award)
  9. apix.ro (contract.executionMonths)
  10. ziare.com (contract.totalMonths)
  11. stireadeiasi.ro (CNIR start order, design from 24 August 2026, works from June 2027)