Dugo Selo – Križevci – Koprivnica – Hungarian border railway (M201, second track)

Reconstruction of the single-track M201 line (state border – Botovo – Dugo Selo) and construction of a second track for 160 km/h, on the Rijeka – Zagreb – Budapest section of the Mediterranean corridor. HŽ Infrastruktura runs it as two projects. Dugo Selo – Križevci (38.2 km) has a works contract signed on 29 April 2016. Križevci – Koprivnica – state border (42.6 km) has one signed on 12 March 2020 with Cengiz İnşaat, co-financed by the Connecting Europe Facility. The works contract, the grant agreement and the project cost are different figures and are kept apart in the lot notes.

Total length
81 km
Open today
0 km
Sections
2
Cost on record
€604.696M
2 of 2 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Dugo Selo – Križevci – Koprivnica – Hungarian border railway (M201, second track): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Dugo Selo – Križevci

Works contract signed 29 April 2016 with the DIV GRUPA d.o.o., DALEKOVOD d.d. and ZAGREB-MONTAŽA d.o.o. consortium for EUR 164.6 million (VAT basis not stated); supervision contract EUR 2.5 million, ended November 2021. The page states 38.2 km for the section and 36.4 km of second track (38.23 km with the Dugo Selo station rebuilt). The EU grant eligibility period for phase I runs from January 2012 to December 2016, which is not the construction start, so no start date is recorded. In February 2026 HŽ Infrastruktura said the new track was fully laid and connected at the end of 2025 and trains already ran on both tracks between Vrbovec and Križevci. Dual-track operation Dugo Selo – Vrbovec was expected in April 2026 and the remaining works, concentrated in Dugo Selo station, were planned for completion in the second half of 2026. The press put the section at about EUR 200 million.

Under construction38 km
  1. Apr 29, 2016Tender awarded
  • Estimated €200MestimatedPress figure for the whole section ("otprilike 200 milijuna eura"); VAT basis and price year not stated.
  • European UnionPhase I only: grant agreement TR.1.1.03-0001 of 8 June 2015 under the Operational Programme Transport 2007–2013 (ERDF), EUR 23.5 million in total, of which EUR 20.0 million (85%) from the programme
  • National budgetPhase I only: EUR 3.5 million (15%) from the state budget
  • European UnionPhase II: Operational Programme Competitiveness and Cohesion 2014–2020; amount not stated
  • DIV GRUPA – DALEKOVOD – ZAGREB-MONTAŽABuilder
Contract value €164.6M
Križevci – Koprivnica – state border

Works contract signed 12 March 2020 with Cengiz İnşaat for EUR 320.9 million (VAT basis not stated); supervision contract EUR 5.3 million signed 23 March 2020. The CEF grant agreement (EUR 283.9 million) covers project management, land, works and supervision, so it is not the works price. The contract term was three and a half years (about 42 months), which put completion at the end of 2023. HŽ Infrastruktura now gives the end of 2026 for all works, with about 90 percent done in December 2025; local press expects the first half of 2027. The new double-track section follows the existing alignment except Carevdar – Lepavina, and shortens the section from 43.2 km to 42.6 km.

Under construction
79 of 42 contracted months
37 months past the contract date
43 km
  1. Mar 12, 2020Tender awarded
  2. Dec 2026Expected opening
  • Estimated €350MestimatedIncluding VAT. Press figure for the whole section ("oko 350 milijuna eura s pdv-om"); price year not stated.
  • European UnionConnecting Europe Facility: grant agreement INEA/CEF/TRAN/M2015/1126931 of 6 October 2016, EUR 283.9 million in total, of which EUR 241.3 million (85%) from CEF
  • National budgetState budget: EUR 42.6 million (15%) of the grant agreement value
  • Cengiz İnşaat Sanayi ve Ticaret A.Ş.Builder
42 mo execution · Contract value €320.9M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union119 km
    3 sections
    • Phase I only: grant agreement TR.1.1.03-0001 of 8 June 2015 under the Operational Programme Transport 2007–2013 (ERDF), EUR 23.5 million in total, of which EUR 20.0 million (85%) from the programme
    • Phase II: Operational Programme Competitiveness and Cohesion 2014–2020; amount not stated
    • Connecting Europe Facility: grant agreement INEA/CEF/TRAN/M2015/1126931 of 6 October 2016, EUR 283.9 million in total, of which EUR 241.3 million (85%) from CEF
  • National budget81 km
    2 sections
    • Phase I only: EUR 3.5 million (15%) from the state budget
    • State budget: EUR 42.6 million (15%) of the grant agreement value

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. HŽ Infrastruktura: Rekonstrukcija postojećeg i izgradnja drugog kolosijeka željezničke pruge na dionici Dugo Selo – Križevciread Oct 5, 2026
  2. HŽ Infrastruktura: Rekonstrukcija postojećeg i izgradnja drugog kolosijeka na dionici Križevci – Koprivnica – državna granicaread Oct 5, 2026
  3. Podravski.hr: Nova pruga bit će gotova tek krajem 2026. godine, doznajemo zašto (24 December 2025)read Oct 5, 2026
  4. Danica.hr: Koprivnica, Bjelovar i Križevci postat će zagrebačka predgrađa (3 February 2026)read Oct 5, 2026
  5. OpenStreetMap: relation 1646296, railway M201 (geometry, ODbL)read Oct 5, 2026
  6. OpenStreetMap contributors: route geometry (ODbL)read Oct 5, 2026