Highways

A 5 Nord/Weinviertel Autobahn

The A 5 links the Vienna area with the northern Weinviertel. The Eibesbrunn–Schrick and Schrick–Poysdorf-Nord sections opened in 2010 and 2017. The Drasenhofen bypass opened in 2019, while a later full-profile extension remains planned.

Total length
53 km
Open today
53 km
Sections
3
Loading map data…

Sections

Sections of A 5 Nord/Weinviertel Autobahn: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Eibesbrunn–Schrick

The cited length and EUR 255 million figure cover the 23.5 km PPP section. The source names Bonaventura as main contractor and says the company group also financed and operated the road under a 30-year concession. The price year and VAT basis are not stated. The OSM line measures about 21.7 km, 8% below the published length.

Opened24 km
  1. Feb 26, 2007Construction start
  2. Jan 31, 2010Opened
  • Estimated €255M
–
  • Bonaventura Straßenerrichtungs-GmbHConcessionaire
–
Schrick–Poysdorf-Nord

The section runs from the Schrick junction to Poysdorf-Nord. A separate two-lane Drasenhofen bypass opened in 2019 and is not included here. The OSM line measures about 24.7 km against the published 24.4 km.

Opened24 km
  1. Apr 2015Construction start
  2. Dec 8, 2017Opened
––––
Drasenhofen bypass

The two-lane bypass opened to traffic on 8 September 2019. The City of Poysdorf reports a 5 km section. This lot records the bypass as built; ASFINAG's planned 9 km full-profile Poysbrunn–border project is a later phase and is not added here as a second overlapping route lot. The OSM line measures about 5.1 km.

Opened5 km
  1. Sep 8, 2019Opened
––––

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Related projects

Sources

  1. Nord/Weinviertel Autobahnread Oct 10, 2026
  2. ASFINAG: A 5 gap closure, Poysbrunn to the Drasenhofen state borderread Oct 10, 2026
  3. OpenStreetMap: A 5 Nord/Weinviertel Autobahnread Oct 10, 2026
  4. City of Poysdorf: 2019 chronicle, Drasenhofen bypassread Oct 13, 2026
  5. OpenStreetMap: Drasenhofen bypass, A5read Oct 13, 2026