S 10 Mühlviertler Schnellstraße

The S 10 runs north from Unterweitersdorf toward the Czech border at Wullowitz. The 22 km section to Freistadt Nord opened in 2015. The Freistadt Nord–Rainbach Nord section is under construction, and the Rainbach Nord–Wullowitz border section is planned.

Total length
38 km
Open today
22 km
Under construction
7 km
Sections
3
Loading map data…

Sections

Sections of S 10 Mühlviertler Schnellstraße: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Unterweitersdorf–Freistadt Nord

The sourced length is 22 km. The OSM-derived line measures about 19.2 km; the published length is retained because the mapped centerline cut is shorter.

Opened22 km
  1. Aug 1, 2009Construction start
  2. Dec 21, 2015Opened
––––
Freistadt Nord–Rainbach Nord

The 7.2 km project is built in two construction lots. ASFINAG lists the total project cost as €361.5 million and planned completion in 2027. The mapped construction alignment measures about 7.8 km.

Under construction7 km
  1. 2023Construction start
  2. 2027Expected opening
––––
Rainbach Nord–Wullowitz border

ASFINAG submitted the project for environmental assessment on 22 October 2025. The length, cost, 2029 target construction start and 2032 planned completion are ASFINAG estimates. The line follows the mapped proposed OSM alignment.

Planned9 km
  1. 2029Construction start
  2. 2032Expected opening
––––

Related projects

Sources

  1. ASFINAG: S 10 Freistadt Nord–Rainbach Nordread Oct 10, 2026
  2. ASFINAG: S 10 Rainbach Nord–Staatsgrenze bei Wullowitzread Oct 10, 2026
  3. BMIMI: S 10 Mühlviertler Schnellstraßeread Oct 13, 2026
  4. Wikipedia: Mühlviertler Schnellstraßeread Oct 10, 2026
  5. OpenStreetMap: S 10 route geometry, proposed way 48633414read Oct 10, 2026