Sofia Metro Line M2 (Obelya – Vitosha)

The blue line, Sofia's second metro diameter, running 11.7 km with 13 stations from the Obelya estate in the north-west through Nadezhda, the Central Railway Station and the National Palace of Culture to Lozenets and Hladilnika in the south. It was built as the first two EU-funded stages of the metro: a 6.4 km central section with seven stations, partly bored by TBM, and a 4.16 km northern section with four stations, both opened together on 31 August 2012. A 1.3 km extension to Vitosha followed on 20 July 2016. Trains run through at Obelya onto line M4 towards Sofia Airport; the two lines will be separated once the infill station Pancho Vladigerov opens.

Total length
12 km
Open today
12 km
Sections
3
Cost on record
€374.92M
1 of 3 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Sofia Metro Line M2 (Obelya – Vitosha): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Stage II, Lot 1: Obelya – Nadezhda – Nadezhda Overpass

Lot 1 of the second construction stage: 4.16 km (1.3 km on viaduct, 2.86 km underground) and four stations (Lomsko shose, Beli Dunav, Nadezhda and Han Kubrat) linking the Obelya depot with the Nadezhda overpass. Built 2009–2012 and accepted by the State Acceptance Commission in August 2012

Opened4 km
  1. Feb 2010Construction start
  2. Aug 31, 2012Opened
  • Estimated €130MestimatedApproximate indicative value of the whole 4150 m section at tender, February 2010. VAT not stated.
  • European UnionCohesion Fund grant of €200 million for the second construction stage, shared with the M4 section from Mladost 1 to Tsarigradsko shose
  • Loan20% local co-financing by Sofia Municipality from a European Investment Bank loan
  • Балканстрой (Obelya – Lomsko shose, with Lomsko shose station)Builder
  • БКС - Център (Obelya – Lomsko shose, with Lomsko shose station)Builder
  • Обединение „Метро Билд” (Lomsko shose – Nadezhda, with Beli Dunav and Nadezhda stations and tunnels)Builder
  • Станилов (Han Kubrat station, tunnels and depot extension)Builder
  • Обединение "ОБЕЛЯ У-БАН" (track, contact rail and canopy)Builder
  • ИТА ИНЖЕНЕРИНГ (low-current and signalling systems)Builder
–
Stage I: Nadezhda Overpass – Central Railway Station – NDK – James Bourchier

First construction stage: 6.4 km and seven stations from the Nadezhda overpass via the Central Railway Station and St Nedelya Square to Cherni vrah Blvd, including a 3.8 km double-track TBM drive of 8.43 m internal diameter serving four stations. Works ran from December 2008 to the opening on 31 August 2012, with final acceptance in October 2012

Opened6 km
  1. Aug 27, 2008Tender awarded
  2. Dec 2008Construction start
  3. Aug 31, 2012Opened
–
  • European UnionERDF grant of €157 million under Priority Axis 3 of OP Transport 2007–2013
  • National budgetSofia Municipality co-financed 25% of the stage value
  • Доуш Иншаат ве Тиджарет (position 1: Nadezhda overpass – Patriarh Evtimiy, TBM section)Builder
  • Обединение "Метро Трейс" (position 2: Patriarh Evtimiy – Cherni vrah)Builder
  • Геотехмин (James Bourchier station structures)Designer
Contract value лв471.093M
James Bourchier – Vitosha

1.3 km southward extension with the single station Vitosha at Hladilnika, valued at €21.9 million and built between August 2014 and July 2016. Built under contract 52/2014 by the consortium Metro Cherni Vrah 2013, whose members were Stanilov, GP Group and Metroprojekt Praha according to the contract completion notice.

Opened1 km
  1. Mar 6, 2014Tender awarded
  2. Aug 2014Construction start
  3. Jul 20, 2016Opened
  • Estimated лв60Mworks onlyForecast value of the 2013 design-and-build tender (AOP case 00423-2013-0007), reported at the ranking in October 2013 against the winning bid of about 42.3 million leva excluding VAT. VAT not stated for the forecast; no price year stated.
  • Actual лв42.339Mworks onlyExcluding VAT. Amount paid under contract 52/2014 at completion.
  • European UnionOperational Programme Transport, in two phases: phase 1 in the 2007–2013 programming period, phase 2 in 2014–2020
  • National budgetSofia Municipality provided advance financing within its co-financing of the section
  • Обединение "МЕТРО ЧЕРНИ ВРЪХ 2013"Builder
22 mo execution · Contract value лв42.35M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union12 km
    3 sections
    • Cohesion Fund grant of €200 million for the second construction stage, shared with the M4 section from Mladost 1 to Tsarigradsko shose
    • ERDF grant of €157 million under Priority Axis 3 of OP Transport 2007–2013
    • Operational Programme Transport, in two phases: phase 1 in the 2007–2013 programming period, phase 2 in 2014–2020
  • National budget8 km
    2 sections
    • Sofia Municipality co-financed 25% of the stage value
    • Sofia Municipality provided advance financing within its co-financing of the section
  • Loan4 km
    1 section
    • 20% local co-financing by Sofia Municipality from a European Investment Bank loan

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia: Sofia Metro
  2. Metropoliten Sofia: First stage of the metro extension (OP Transport)
  3. Metropoliten Sofia: Second stage of the metro extension (OP Transport)
  4. Metropoliten Sofia: Third stage of the metro extension (OP Transport)
  5. Metropoliten buyer profile: contract 52/2014, MS James Bourchier – MS II-12read Sep 25, 2026
  6. Metropoliten: contract completion notice, contract 52/2014 (16 September 2016)read Sep 25, 2026
  7. Stroitelstvo Gradat: Contracts signed for the extension of the second metro diameter (issue 33, 1 September 2008)read Sep 25, 2026
  8. Vestnik Stroitel: Nadezhda complex, a metro diameter away (30 August 2012)read Sep 25, 2026
  9. AOP: contract award notice 00423-2011-0003 (Metropoliten EAD)read Sep 25, 2026
  10. gradat.bg: Strong interest in the tender for the northern branch of the metro (21 February 2010)read Sep 25, 2026
  11. Mediapool: Метрото стига до кв. „Хладилника“ през 2015 г. (21 October 2013)read Oct 1, 2026
  12. OpenStreetMap contributors (geometry, ODbL)