Bucharest Metro Line M4 (Gara de Nord 2 – Străulești)
The shortest line of the Bucharest Metro, running north-west from Gara de Nord 2 along Calea Griviței and Bucureștii Noi to Străulești. Construction started in December 1989 and stopped after the revolution, so the first section opened only on 1 March 2000, followed by Parc Bazilescu in 2011, both financed with European Investment Bank loans, and Străulești in 2017, funded from the state budget. Metrorex records 7.44 km and 8 stations in operation. The section from Gara de Nord 2 to 1 Mai will also carry line M6 to the airport, and an 11 km southern extension to Gara Progresul went to tender in April 2024.
- Total length
- 19 km
- Open today
- 8 km
- Sections
- 4
- Cost on record
- €236.378M
- 1 of 4 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Section I: Gara de Nord 2 – 1 Mai 3.6 km and 4 stations, the first line begun under the communist government and finished after it. Tunnelling reached as far as today's Parc Bazilescu before works were abandoned and restarted in the 1990s. Basarab 2 is a four-track station with the M1 tracks between the M4 tracks. Ziarul Financiar reported the investment at €220 million; no price year is published for a spend running from 1989 to 2000, so no cost is recorded. Line M6 will share this section | Opened | 4 km |
| – |
| – | – |
| 1 Mai – Jiului – Parc Bazilescu 2.62 km and 2 stations, Jiului and Parc Bazilescu. Parc Bazilescu was not in the original plan and was built to bring the section into service sooner. România liberă put the cost of the two stations at 300 million lei (about US$100 million), 200 million of it spent between 1990 and 2010 and the rest in the two years before opening. The sums are nominal across the 2005 redenomination, so no cost is recorded. Works on Racordul 2 (Gara de Nord – Laromet, 6.1 km, including Pajura, today's Jiului, and Bazilescu) began under Decree 303 of 7 December 1989, per Metrorex; România liberă gives 1988. The association of SOMET, Schindler and TIAB carried out the 2010–2011 completion works on Jiului, Parc Bazilescu and the interstation, with Metroul as general designer; the contractor for the structural works begun in 1989 is not named. On 20 August 2010 Metrorex signed a 21.9 million lei contract with TIAB, funded from the state budget, for general installations and finishes of the technical spaces on 1 Mai – Parc Bazilescu, with a six-month execution period. | Opened | 3 km |
| – |
|
| – |
| Parc Bazilescu – Străulești 2.1 km and 2 stations, Laminorului and Străulești, together with the Străulești depot and an interchange with the surface network. Works started in 2013, tunnelling was finished on 3 September 2015 and the stations opened on 31 March 2017. The English article gives this section as 1.89 km and the M4 article as 1.6 km. Works contract signed on 12 July 2012 with a consortium led by Astaldi (with SOMET, TIAB and UTI), covering the tunnel, both stations, the Străulești depot, the multimodal terminal and park and ride. Economica.net gave the total project value as 1,115 million lei (€252.4 million), covering stations, tunnel, depot, intermodal terminal and park and ride, with no price year or VAT basis. At the opening the transport minister gave the project value as €241 million. | Opened | 2 km |
| – |
|
| 30 mo execution · Contract value lei 714.731M |
| Southern extension: Gara de Nord – Gara Progresul About 11 km and 14 new stations south from Gara de Nord along Berzei, Vasile Pârvan, Hașdeu, Izvor, 13 Septembrie, Tudor Vladimirescu, Șoseaua Viilor and Șoseaua Giurgiului to Gara Progresul, where a depot is planned. Route from the revised feasibility study presented in November 2020; the tender was launched on 26 April 2024. The English article gives the planned length as 10.6 km. The alignment drawn here follows those streets and is indicative. Contracting authority: Sector 4 City Hall. Both design-and-build contracts were awarded in August 2025: Section I (Gara de Nord – Eroii Revoluției) to a consortium led by Dogus, Section II (Eroii Revoluției – Gara Progresul) to one led by Construcții Erbașu. The Section I contract was signed at the end of 2025 and its start order for design and execution was issued on 4 December 2025; physical works follow the design phase. Each contract runs 60 months, starting with a design phase given as 8 or 10 months depending on the release. By December 2025 Sector 4 gave the investment value as €3.5 billion (over 17 billion lei) of non-reimbursable EU funds. The EU award notice gives 4,691.4 million lei for Section I (signed 2 December 2025) and 4,383.0 million lei for Section II (signed 26 January 2026), 9,074.5 million lei in all, against a tender estimate of 11,395.1 million lei, all excluding VAT. The two contracts are recorded separately, so no single contract value is given. | Tendered | 11 km |
|
|
|
| 60 mo total |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union11 km1 section
- Programul Transport 2021-2027, non-reimbursable EU funds; financing contract signed by Sector 4 on 4 June 2024
- Loan6 km2 sections
- European Investment Bank loan
- National budget2 km1 section
- State budget allocations, as planned at contract signing (Metrorex, 2012)
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- RailwaysSofia Metro Line M3 (Gorna Banya – Levski)Same contractor: Doğuş İnşaat, GP Group, Trace Group Hold
- RailwaysBucharest Metro Line M2 (Pipera – Tudor Arghezi)Same contractor: Construcții Erbașu, Somet, TIAB
- HighwaysA1 Trakia MotorwaySame contractor: Doğuş İnşaat, Trace Group Hold
- RailwaysSofia Metro Line M2 (Obelya – Vitosha)Same contractor: Doğuş İnşaat, GP Group
- HighwaysA3 Transylvania Motorway (Brașov–Cluj–Borș)Same contractor: Astaldi, Construcții Erbașu
- HighwaysA2 Hemus MotorwaySame contractor: Trace Group Hold
Sources
- Wikipedia: Metroul din București
- Wikipedia: Bucharest Metro Line M4
- UrbanRail.Net: Bucharest Metro
- OpenStreetMap contributors (geometry of the opened sections, ODbL)
- Metrorex: Semnarea contractului de executie a lucrarilor pentru extinderea retelei de metrou pe Tronsonul Parc Bazilescu – Laminorului – Lac Straulesti (12 July 2012)read Sep 25, 2026 · archived copy
- Economica.net: E oficial: Metrorex poate în sfârşit să inaugureze staţiile Străuleşti şi Laminorului (30 March 2017)read Sep 25, 2026
- Știrile Pro TV: Statiile de metrou Laminorul si Straulesti se deschid oficial vineri (31 March 2017)read Sep 25, 2026
- România liberă: EXCLUSIV. Cum arată două staţii de metrou din Bucureşti care au costat 100 de milioane de dolari (30 June 2011)read Sep 25, 2026 · archived copy
- Metrorex: Extinderea retelei de metrou – Magistrala 4 Racorduri (archived 29 June 2007)read Sep 25, 2026 · archived copy
- Primăria Sectorului 4: E oficial! Vin banii pentru prelungirea Magistralei M4, contractul de finanțare în valoare de 2,5 miliarde de euro (4 June 2024)read Sep 25, 2026
- Primăria Sectorului 4: Primarul Daniel Băluță a semnat ordinul de începere a lucrărilor de extindere a magistralei de metrou M4 (4 December 2025)read Sep 25, 2026
- Economedia: Magistrala M4 Gara de Nord – Filaret – Gara Progresu, ofertele la contractul de 2 miliarde de euro se depun până marți, 8 octombrie (October 2024)read Sep 25, 2026
- Economedia: Metrou de la Gara de Nord la Gara Progresu, Primăria Sectorului 4 a ales constructorul pentru prima secțiune până la Eroii Revoluției (30 August 2025)read Sep 25, 2026
- Economedia: Magistrala de metrou M4, o asociere turco-bulgară rămâne câștigătoare pentru prima secțiune din linia Gara de Nord – Gara Progresu (27 November 2025)read Sep 25, 2026
- Primăria Sectorului 4: Extinderea Magistralei M4 de metrou, cel mai mare proiect de infrastructură din România derulat de o autoritate publică locală, intră în linie dreaptă (1 February 2026)read Sep 25, 2026
- Revista Construcțiilor: Statiile de metrou JIULUI si PARC BAZILESCU (5 August 2012)read Sep 28, 2026
- Mediafax: Staţiile de metrou Pajura şi Parc Bazilescu vor fi puse în funcţiune în prima parte a anului 2011 (31 August 2010)read Sep 28, 2026
- TED 250034-2024: Romania – Underground railway works – Extinderea rețelei de metrou Magistrala 4 de metrou, secțiunea Gara de Nord – Gara Progresul (contract notice, OJ S 83/2024, 26 April 2024)read Sep 28, 2026
- TED 86723-2026: Romania – Underground railway works – Extinderea rețelei de metrou Magistrala 4 de metrou, secțiunea Gara de Nord – Gara Progresul (contract award notice, OJ S 26/2026, 6 February 2026)read Sep 28, 2026