Sofia Metro Line M1 (Slivnitsa – Business Park Sofia)

The red line and the first to be built on the Sofia Metro, the only metro system in Bulgaria. Its first 6.5 km with five stations, from Slivnitsa through the Lyulin housing estates to Konstantin Velichkov, opened on 28 January 1998; Opalchenska followed in 1999 and Serdika, under St Nedelya Square, in 2000, taking the system to 8.1 km. Sections begun in 2005 and 2006 carried the line east under the city centre to Mladost 1 in 2009, and a 2.7 km extension reached Business Park Sofia in May 2015, bringing the line to 17.6 km and 16 stations. Between Slivnitsa and Mladost 1 it shares its tunnels with line M4, which branches away to Sofia Airport; a westward extension beyond Lyulin is in planning but has not been contracted.

Total length
19 km
Open today
19 km
Sections
5
Loading map data…

Sections

Sections of Sofia Metro Line M1 (Slivnitsa – Business Park Sofia): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Stage I: Slivnitsa – Konstantin Velichkov

First section of the Sofia Metro: 6.5 km and five stations from Slivnitsa Blvd through the Lyulin housing estates to Konstantin Velichkov Blvd, inaugurated 28 January 1998. Station works began in 1979 at Vardar and the last, Konstantin Velichkov, in 1985; depot works began in 1978

Opened7 km
  1. 1979Construction start
  2. Jan 28, 1998Opened
–
  • National budgetBuilt by the City of Sofia with its own funds, as part of the first seven stations (JBIC: "self-secured funds"). No amount published
––
Konstantin Velichkov – Serdika (Opalchenska, Serdika)

Opalchenska entered service on 17 September 1999 and Serdika, on St Nedelya Square, on 31 October 2000, extending the operating system to 8.1 km. The two station openings were not costed separately in the published sources

Opened2 km
  1. Oct 31, 2000Opened
–
  • National budgetBuilt by the City of Sofia with its own funds, as part of the first seven stations (JBIC: "self-secured funds"). No amount published
––
Serdika – Frédéric Joliot-Curie

4.8 km of tunnel and three stations from St Nedelya Square to the Interped World Trade Centre in Izgrev, started in 2005. Vasil Levski Stadium and Frédéric Joliot-Curie opened on 8 May 2009; the remaining Serdika – Vasil Levski Stadium link followed on 7 September 2009, when the section was in service over its full length

Opened5 km
  1. 2005Construction start
  2. Sep 7, 2009Opened
–
  • LoanJBIC ODA loan BG-P5 to Sofia Municipality, guaranteed by the Government of Bulgaria, signed February 2002: ¥12,894 million approved, ¥12,833 million disbursed. It financed the central 2.3 km with two stations
  • National budgetThe remaining 2.5 km with one station was financed locally
  • Taisei Corporation (shield tunnel, Serdika – Vasil Levski Stadium)Builder
–
Frédéric Joliot-Curie – Mladost 1

3.2 km of tunnel and three stations (G. M. Dimitrov, Musagenitsa, Mladost 1) linking Izgrev with the Mladost 1 housing estate, started in 2006 and opened on 8 May 2009, at first as an isolated segment

Opened3 km
  1. 2006Construction start
  2. May 8, 2009Opened
–
  • National budgetDomestic funds, not the Japanese loan (JBIC: "self-procured funds" for the tenth to thirteenth stations). No amount published
––
Mladost 1 – Business Park Sofia

Lot 2 of the third construction stage: 2.7 km and three underground stations (Aleksandar Malinov, Akad. Aleksandar Teodorov-Balan, Business Park) from Mladost 1 to Business Park Sofia in Mladost 4. Works began 25 April 2013 and the section opened 8 May 2015; the two contracts totalled 85,388,562.98 leva excluding VAT. Built under two design-and-build contracts from an open procedure: 119/2013 (Mladost 1 – km 17+000) signed 29 March 2013 and 114/2013 (km 17+000 – Business Park) signed 28 March 2013, each for 24 months from the start of works

Opened3 km
  1. Mar 28, 2013Tender awarded
  2. Apr 25, 2013Construction start
  3. May 8, 2015Opened
  • Actual лв102.466MIncluding VAT. Amounts paid under contracts 119/2013 (64,678,925.98 leva) and 114/2013 (37,787,349.60 leva), closed August and September 2015.
  • European UnionOP Transport 2007–2013, Priority Axis 3: ERDF grant of €93 million towards the €110 million third construction stage, which also covered the M4 airport extension
  • National budget
  • Обединение "МЕТРО БИЛД МЛАДОСТ" (Mladost 1 – km 17+000)Builder
  • Обединение "ГЕОМЕТРО Б.П." (km 17+000 – Business Park)Builder
24 mo execution · Contract value лв85.389M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • National budget19 km
    5 sections
    • Built by the City of Sofia with its own funds, as part of the first seven stations (JBIC: "self-secured funds"). No amount published
    • The remaining 2.5 km with one station was financed locally
    • Domestic funds, not the Japanese loan (JBIC: "self-procured funds" for the tenth to thirteenth stations). No amount published
  • Loan5 km
    1 section
    • JBIC ODA loan BG-P5 to Sofia Municipality, guaranteed by the Government of Bulgaria, signed February 2002: ¥12,894 million approved, ¥12,833 million disbursed. It financed the central 2.3 km with two stations
  • European Union3 km
    1 section
    • OP Transport 2007–2013, Priority Axis 3: ERDF grant of €93 million towards the €110 million third construction stage, which also covered the M4 airport extension

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia: Sofia Metro
  2. Metropoliten Sofia: Third stage of the metro extension (OP Transport)
  3. Novinite: Subway Extension to Business Park Sofia Opens
  4. Metropoliten: 20 години метро в София (2018-01)read Sep 25, 2026
  5. JBIC: ODA Loan Project Mid-Term Review 2006, Sofia Metro Extension Project (BG-P5) (2007)read Sep 25, 2026
  6. JICA: Ex-Post Evaluation of Japanese ODA Loan Project, Sofia Metro Extension Project (2014)read Sep 25, 2026
  7. Metropoliten Sofia: History of metro extensionsread Sep 25, 2026
  8. Metropoliten buyer profile: Договор №119/2013, участък от МС13 до км 17+000read Sep 25, 2026
  9. Metropoliten buyer profile: Договор №114/2013, участък от км 17 до МС16 (Бизнес парк)read Sep 25, 2026
  10. Metropoliten: Информация за приключване на договор № 119/29.03.2013read Sep 25, 2026
  11. Metropoliten: Информация за приключване на договор № 114/28.03.2013read Sep 25, 2026
  12. OpenStreetMap contributors (geometry, ODbL)