A5 Slavonika (Hungarian border – Beli Manastir – Osijek – Đakovo – Sredanci – Svilaj)

Croatia's north–south motorway through Slavonia, on Pan-European Corridor Vc and the E73. HAC lists it as 88.6 km, from the Hungarian border at Branjin Vrh to the Bosnia and Herzegovina border at Svilaj, and lists the 660 m Sava bridge at Svilaj among its sections. It joins the A3 at the Sredanci interchange. The sections opened one by one: Sredanci – Đakovo in 2007, Đakovo – Osijek in 2009, Sredanci – Svilaj in 2015, Osijek – Beli Manastir in December 2022 and Beli Manastir – Hungarian border in October 2025, which HAC calls the completion of the motorway in full profile. The Svilaj bridge itself is not a lot here: the last lot ends at its northern abutment. Lengths are the section lengths published by HAC where it gives one; Sredanci – Svilaj is from the Croatian Wikipedia and the Svilaj approach is measured from the mapped alignment. Kuna amounts are given in the lot notes only.

Total length
90 km
Open today
90 km
Sections
7
Cost on record
€47.99M
1 of 7 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of A5 Slavonika (Hungarian border – Beli Manastir – Osijek – Đakovo – Sredanci – Svilaj): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Sredanci – Đakovo

HAC gives 23.0 km for this section; the Croatian Wikipedia gives 21 km and the mapped alignment measures about 21.0 km between the A3 crossing and the Đakovo interchange. The English Wikipedia records the cost as 1.4 billion kuna (HRK), built in eighteen months by a consortium of Croatian construction companies, which are not named.

Opened23 km
  1. Nov 9, 2007Opened
––––
Đakovo – Osijek

The English Wikipedia records a cost of 2.13 billion kuna (HRK), with completion originally scheduled for December 2008 and the opening delayed by four months; toll collection on the A5 began with this opening.

Opened33 km
  1. Apr 17, 2009Opened
––––
Sredanci – Svilaj interchange

From the A3 crossing at Sredanci to the Svilaj interchange. Length is from the Croatian Wikipedia (3.2 km); the mapped alignment measures about 2.9 km. HAC lists Sredanci to the Bosnia and Herzegovina border as 3.5 km, a figure that does not match the sum of this lot and the Svilaj approach lot as drawn.

Opened3 km
  1. Mar 2, 2015Opened
––––
Svilaj interchange – Sava bridge approach

Length measured from OpenStreetMap geometry. The lot ends at the northern abutment of the 660 m Svilaj bridge over the Sava, which is not part of this lot. The Croatian Wikipedia gives 1.9 km for Svilaj – border and says the road was built to the border in 2015 but stayed closed until the bridge and the Bosnian border crossing were finished; HAC says the bridge opened on 30 September 2021.

Opened2 km
  1. Sep 30, 2021Opened
––––
Osijek – Halasica bridge

Sub-section of Osijek – Beli Manastir (24.6 km in all). Includes the 2,507 m bridge over the Drava (the 3rd Guards Brigade Kune bridge). HAC says the works were finished in 2019 and the sub-section stayed closed until the northern sub-section was ready, so it opened with it on 2 December 2022. The mapped alignment measures about 7.9 km between the Osijek interchange and the Halasica bridge, against HAC's 7.1 km.

Opened7 km
  1. 2012Construction start
  2. Dec 2, 2022Opened
  • Actual €126MTotal investment on this sub-section including the Drava bridge, as stated by HAC at the opening. Price year and VAT basis not stated.
–––
Halasica bridge – Beli Manastir

Sub-section of Osijek – Beli Manastir. The works contract for the alignment, signed on 28 April 2020 with a joint venture of Osijek-Koteks and GP Krk, was worth 443 million kuna (HRK) excluding VAT (the English Wikipedia gives the signing date; HAC gives the value and says the alignment works began in 2020, after the first phase of structures worth about 83 million kuna). Ten structures, the Beli Manastir interchange and the Sudaraš toll plaza are on the sub-section. The lot is cut 17.5 km from the Halasica bridge, the length HAC gives for the sub-section, which falls just north of the Beli Manastir interchange.

Opened18 km
  1. Aug 2018Construction start
  2. Dec 2, 2022Opened
  • Actual €80.4MTotal investment on this sub-section as stated by HAC at the opening. Price year and VAT basis not stated.
  • LoanPart of the project Croatia, completion of the motorway on Corridor Vc, worth EUR 107 million in total and financed by the EBRD (51%) and HBOR (49%). The EBRD loan was EUR 55 million at 1% over 15 years.
  • Osijek-Koteks d.d.Builder
  • GP Krk d.d.Builder
–
Beli Manastir – Hungarian border

Contract signed in August 2023 (45,902,212.90 EUR excluding VAT). The section has 8 structures, the longest the 318 m viaduct of the 135th Baranja Brigade HV over the railway and the Karašica. HAC calls it the construction-wise hardest part of the route. The lot is cut 5.0 km from the Hungarian border, just north of the Beli Manastir interchange.

Opened5 km
  1. Aug 2023Tender awarded
  2. Oct 7, 2025Opened
–
  • LoanFinanced in full by the EBRD from the loan for the project Croatia, completion of the motorway on Corridor Vc.
  • Osijek-Koteks d.d.Builder
Contract value €45.902M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • Loan23 km
    2 sections
    • Part of the project Croatia, completion of the motorway on Corridor Vc, worth EUR 107 million in total and financed by the EBRD (51%) and HBOR (49%). The EBRD loan was EUR 55 million at 1% over 15 years.
    • Financed in full by the EBRD from the loan for the project Croatia, completion of the motorway on Corridor Vc.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • Pan-European Corridor VcPan-European

Sources

  1. HAC: Otvorena dionica Beli Manastir – Osijek na A5 (2 December 2022; sub-section lengths, EUR 126M and EUR 80.4M investment, HRK 443M works contract, EBRD/HBOR financing, A5 section lengths)read Oct 5, 2026
  2. HAC: Dionica Beli Manastir – granica Mađarske puštena u promet (7 October 2025; contract with Osijek Koteks, 45,902,212.90 EUR excluding VAT, EBRD financing)read Oct 5, 2026
  3. HAC: Izgradnja mosta Svilaj (660 m bridge, works September 2016 – July 2020, opened 30 September 2021)read Oct 5, 2026
  4. Wikipedia (hr): Autocesta A5 (opening dates and section lengths)read Oct 5, 2026
  5. Wikipedia (en): A5 (Croatia) (history, kuna costs of the 2007 and 2009 sections, April 2020 contract date)read Oct 5, 2026
  6. OpenStreetMap: relation 144787, Autocesta A5 (ref A5)read Oct 5, 2026
  7. OpenStreetMap contributors: route geometry (ODbL)read Oct 5, 2026