Euro Construct Trading '98
Romania
- Sections
- 7
- Length
- 280 km
- Median slip
- +50 mo
- Median overrun
- –
Slip measured on 5 of 7 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Alstom Transport – Swietelsky – Astaldi – Euro Construct Trading '98 – Dafora
- RailWorks
- RailWorks (Alstom – Arcada – Euro Construct Trading '98)
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.