Euro Construct Trading '98

Romania
Sections
7
Length
280 km
Median slip
+50 mo
Median overrun
–

Slip measured on 5 of 7 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Alstom Transport – Swietelsky – Astaldi – Euro Construct Trading '98 – Dafora
  • RailWorks
  • RailWorks (Alstom – Arcada – Euro Construct Trading '98)

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.