Railways

Caransebeș – Timișoara – Arad railway modernisation

Modernisation of 162 km of line from Caransebeș through Lugoj and Timișoara to Arad as an electrified double track for 120–160 km/h, with ERTMS (ETCS Level 2 and GSM-R). Four design-and-build lots financed from the PNRR: the financing contract is worth RON 8,774.73 million, of which RON 5,681.33 million from PNRR, with implementation until 31 December 2026. Traffic reopened on Lugoj – Timișoara Est on 31 August 2026.

Total length
162 km
Open today
0 km
Under construction
162 km
Sections
4
Cost on record
€1.7B
4 of 4 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Caransebeș – Timișoara – Arad railway modernisation: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Lot 1: Caransebeș – Lugoj

Design and works contract signed on 18 December 2023, with the start order for design and works dated 15 January 2024 (recorded as construction start). Contract deadline 15 July 2027. Six stations (Caransebeș, Zăgujeni, Căvăran, Jena, Găvojdia, Tapia), 12 bridges, ERTMS (ETCS Level 2 and GSM-R). Status in CFR's December 2025 presentation: contract in progress.

Under construction40 km
  1. Dec 18, 2023Tender awarded
  2. Jan 15, 2024Construction start
  3. Jul 2027Expected opening
–
  • European UnionPNRR (Next Generation EU). Financing contract for the whole Caransebeș – Arad project: RON 8,774.73 million total value, RON 5,681.33 million from PNRR, implementation until 31 December 2026.
  • RailWorks (Alstom Transport – Arcada Company – Euro Construct Trading '98)Builder
Contract value lei 1.3B
Lot 2: Lugoj – Timișoara Est

Design and works contract signed on 28 November 2022, with the start order for design and works dated 28 December 2022 (recorded as construction start). The December 2025 presentation gave June 2026 as the works deadline. Traffic was suspended from 2 June to 31 August 2026 and reopened on 31 August 2026 at 16:50 on about 51 km of newly modernised and electrified track, plus about 3 km on the old alignment near km 524+013 and about 3 km of lot 3 at Timișoara Est. CFR states that the works needed to complete the lot continue, so the lot stays under construction. Neither the release nor the presentation gives where the old-alignment stretch lies beyond the chainage, so the lot is not split. 160 km/h for passenger and 120 km/h for freight trains are the design speeds at completion. Seven stations, 14 bridges and 1 overpass, ERTMS (ETCS Level 2 and GSM-R). Drawn geometry measures about 52.7 km.

Under construction54 km
  1. Nov 28, 2022Tender awarded
  2. Dec 28, 2022Construction start
–
  • European UnionPNRR (Next Generation EU). Financing contract for the whole Caransebeș – Arad project: RON 8,774.73 million total value, RON 5,681.33 million from PNRR, implementation until 31 December 2026.
  • FCC ConstrucciónBuilder
Contract value lei 1.9B
Lot 3: Timișoara Est – Ronaț Triaj Gr. D

Design and works contract signed on 4 November 2022, with the start order for design and works dated 5 December 2022 (recorded as construction start). The December 2025 presentation gave June 2026 as the works deadline and the contract as in progress. Five stations (Timișoara Est, Nord, Centru, P.M. Ronaț Triaj, Ronaț Triaj Gr. D), a new passenger building with annexes, 3 bridges, 4 overpasses, 5 underpasses and 15 level crossings. Drawn geometry measures about 12.6 km.

Under construction14 km
  1. Nov 4, 2022Tender awarded
  2. Dec 5, 2022Construction start
–
  • European UnionPNRR (Next Generation EU). Financing contract for the whole Caransebeș – Arad project: RON 8,774.73 million total value, RON 5,681.33 million from PNRR, implementation until 31 December 2026.
  • Webuild – Participazioni Italia – SalcefBuilder
Contract value lei 1.4B
Lot 4: Ronaț Triaj Gr. D – Arad and Aradu Nou – Glogovăț

Design and works contract signed on 17 November 2022, with the start order for design and works dated 16 December 2022 (recorded as construction start). The December 2025 presentation gave June 2026 as the works deadline and the contract as in progress. The 54.86 km covers Ronaț Triaj Gr. D – Arad and the Aradu Nou – Glogovăț link, with stations at Sânandrei, Băile Călacea, Orțișoara, Vinga, Șag, P.M. Valea Viilor, Aradu Nou and Glogovăț, 6 bridges, 5 overpasses, 11 underpasses and 7 level crossings. The drawn geometry (about 55.7 km, both parts) is trimmed by about 2.4 km where it meets the line of the Curtici – Simeria project, at Arad station and at Glogovăț, so that nothing is drawn twice; the recorded length is not split between the two projects.

Under construction55 km
  1. Nov 17, 2022Tender awarded
  2. Dec 16, 2022Construction start
–
  • European UnionPNRR (Next Generation EU). Financing contract for the whole Caransebeș – Arad project: RON 8,774.73 million total value, RON 5,681.33 million from PNRR, implementation until 31 December 2026.
  • Webuild – Participazioni Italia – SalcefBuilder
Contract value lei 2.2B

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union162 km
    4 sections
    • PNRR (Next Generation EU). Financing contract for the whole Caransebeș – Arad project: RON 8,774.73 million total value, RON 5,681.33 million from PNRR, implementation until 31 December 2026.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. CFR SA: Modernizarea liniei feroviare Caransebeș – Timișoara – Arad (prezentare, decembrie 2025)read Oct 5, 2026
  2. CFR SA: 31 august 2026 – Lotul 2 Lugoj – Timișoara Est, redeschis circulației feroviare pe infrastructura modernizatăread Oct 5, 2026
  3. OpenStreetMap contributors (geometry of CFR line 900, ODbL)read Oct 5, 2026