Tunnels

Romanian railway tunnels

Romania's notable railway tunnels. The Teliu tunnel, bored between 1924 and 1929 on the Brașov–Întorsura Buzăului line and opened in 1931, has been the country's longest railway tunnel for almost a century at 4,369.5 m. The Corridor IV upgrade between Brașov and Sighișoara will overtake it: four tunnel boring machines are driving the twin-bore Ormeniș (about 6.7 km) and Homorod (about 5.2 km) tunnels through the hills around Racoș, replacing the winding Olt valley alignment, and shorter new tunnels are being built at Mureni and Achita on the Cața–Sighișoara subsection. Lengths here are measured from OpenStreetMap geometry of a single bore.

Total length
20 km
Open today
5 km
Under construction
13 km
Sections
10

Includes 16 km whose works another project already measures, either as shared track or as a structure inside one of its sections. Counted in full here, and once in any total that spans projects.

Loading map data…

Sections

Sections of Romanian railway tunnels: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Teliu tunnel (Brașov – Întorsura Buzăului line)

Driven from the north from 15 July 1924 and from the south from 5 July 1925; the two headings met on 1 October 1926, the tunnel was completed on 30 September 1928 and opened to traffic on 25 June 1931. Built for double track and electrification, it is still single-track and unelectrified; it remains Romania's longest railway tunnel

Opened4 km
  1. Jul 15, 1924Construction start
  2. Jun 25, 1931Opened
–
  • National budget
  • Julius Berger TiefbauBuilder
–
Ormeniș tunnel (Apața – Racoș, Brașov–Sighișoara line)

Twin bores on the new Apața–Cața alignment (OpenStreetMap: "CFR line 300 – Variant 5 – Apața-Racoș"), driven by tunnel boring machines from 2024; will be the longest railway tunnel in Romania

Under construction7 km
  1. 2024Construction start
  2. Oct 2026Expected opening
–
  • European UnionConnecting Europe Facility
  • National budget
  • Aktor (RailWorks consortium)Builder
–
Homorod tunnel (Racoș – Homorod, Brașov–Sighișoara line)

Twin bores on the new Apața–Cața alignment (OpenStreetMap: "CFR line 300 – Variant 7 – Racoș-Homorod"); drilling started in October 2024

Under construction5 km
  1. Oct 2024Construction start
  2. Oct 2026Expected opening
–
  • European UnionConnecting Europe Facility
  • National budget
  • Aktor (RailWorks consortium)Builder
–
Mureni tunnel (Cața – Sighișoara)

New tunnel on the realigned Cața–Sighișoara subsection of the Brașov–Sighișoara rehabilitation; contractual completion of the end subsections is April 2027. NATM excavation of the tunnel began in summer 2023 (Asociația Pro Infrastructura, not CFR).

Under construction0.7 km
  1. 2023Construction start
  2. Apr 2027Expected opening
–
  • European UnionConnecting Europe Facility
  • National budget
  • RailWorks (Alstom – Aktor – Arcada – Euro Construct Trading '98)Builder
–
Achita 1 tunnel (Cața – Sighișoara)

New tunnel on the realigned Cața–Sighișoara subsection; contractual completion April 2027

Under construction0.5 km
  1. Apr 2027Expected opening
–
  • European UnionConnecting Europe Facility
  • National budget
  • RailWorks (Alstom – Aktor – Arcada – Euro Construct Trading '98)Builder
–
Achita 2 tunnel (Cața – Sighișoara)

New tunnel on the realigned Cața–Sighișoara subsection; contractual completion April 2027

Under construction0.2 km
  1. Apr 2027Expected opening
–
  • European UnionConnecting Europe Facility
  • National budget
  • RailWorks (Alstom – Aktor – Arcada – Euro Construct Trading '98)Builder
–
Bata tunnel (Bârzava – Vărădia, Curtici – Simeria line)

New 603 m tunnel near the left bank of the Mureș on the Bârzava Nouă – Vărădia alignment of subsection 2b, built by mechanised excavation for 160 km/h passenger and 120 km/h freight traffic. Track II through it opened on 17 July 2025. Length from CFR. Dates are those of the 2a and 2b contracts (signed 19 May 2017, works from 27 July 2017).

Opened0.6 km
  1. May 19, 2017Tender awarded
  2. Jul 27, 2017Construction start
  3. Jul 17, 2025Opened
––
  • Webuild – FCC Construccion – Salcef – Hitachi Rail (subsection 2b Bârzava – Ilteu)Builder
–
Poarta I tunnel (Băile Herculane – Poarta, Craiova – Caransebeș line)

New double-track tunnel, 1,279 m, on Lot 5 (Cap X Băile Herculane – Cap X PO Nou Poarta, km 404+250 – 436+887) of the Craiova – Drobeta-Turnu Severin – Caransebeș rehabilitation. The design-and-build contract for the whole lot was signed with PORR Construct on 27 August 2025 (RON 2,143.13 million excluding VAT, 12 months design and 48 months works); per the CFR August 2026 status report it is in design, due in October 2030. CFR plans to close the Drobeta-Turnu Severin – Caransebeș line from February 2027 to February 2032 for the works. Length from CFR.

Tendered1 km
  1. Aug 27, 2025Tender awarded
  2. Oct 2030Expected opening
––
  • PORR ConstructBuilder
–
Poarta 2 tunnel (Nou Poarta – Caransebeș, Craiova – Caransebeș line)

New double-track tunnel, 550 m, on Lot 6 (Cap X Nou Poarta halt – Caransebeș, km 436+887 – 474+046.53) of the Craiova – Drobeta-Turnu Severin – Caransebeș rehabilitation. The design-and-build contract for the whole lot was announced on 11 December 2025 with İçtaş İnşaat and Rotary Construcții Mentenanță (RON 2,114.35 million, VAT basis not stated by CFR, 12 months of design and 60 months of works). CFR plans to close the Drobeta Turnu Severin – Caransebeș line from February 2027 to February 2032 for the works. Length from CFR.

Tendered0.6 km
  1. Dec 11, 2025Tender awarded
––
  • İçtaş – Rotary Construcții MentenanțăBuilder
–
Poarta 3 tunnel (Nou Poarta – Caransebeș, Craiova – Caransebeș line)

New double-track tunnel, 305 m, on Lot 6 (Cap X Nou Poarta halt – Caransebeș, km 436+887 – 474+046.53) of the Craiova – Drobeta-Turnu Severin – Caransebeș rehabilitation. The design-and-build contract for the whole lot was announced on 11 December 2025 with İçtaş İnşaat and Rotary Construcții Mentenanță (RON 2,114.35 million, VAT basis not stated by CFR, 12 months of design and 60 months of works). CFR plans to close the Drobeta Turnu Severin – Caransebeș line from February 2027 to February 2032 for the works. Length from CFR.

Tendered0.3 km
  1. Dec 11, 2025Tender awarded
––
  • İçtaş – Rotary Construcții MentenanțăBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • National budget18 km
    6 sections
  • European Union13 km
    5 sections
    • Connecting Europe Facility

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia (ro): Tunelul Teliu
  2. Tunnels & Tunnelling: AKTOR enters Racoș mountains using four TBMs on new railway
  3. The Diplomat: AKTOR started drilling on the Homorod tunnels of the Brașov–Sighișoara railwayread Aug 14, 2026
  4. OpenStreetMap contributors (geometry and tunnel lengths, ODbL)
  5. cfr.ro
  6. Asociația Pro Infrastructura: Străpungere la tunelul Mureniread Sep 28, 2026
  7. CFR SA: Varianta nouă de traseu Bârzava – Vărădia și tunelul Bata deschise circulației (2025-07-17)read Oct 2, 2026
  8. CFR SA: Precizări CFR S.A. privind închiderea planificată a liniei Drobeta Turnu Severin – Caransebeș, pentru lucrări de modernizare (2026-06-19)read Oct 2, 2026
  9. CFR SA: Semnare contract pentru proiectare și execuție, Reabilitarea liniei feroviare Craiova – Drobeta Turnu Severin – Caransebeș, Lot 5 Cap X Băile Herculane – Cap X PO Nou Poarta (2025-08-27)read Oct 2, 2026
  10. CFR SA: Start pentru Lotul 6 al proiectului Craiova – Caransebeș (2025-12-11)read Oct 5, 2026
  11. CFR SA: Stadiul proiectelor de reabilitare/modernizare infrastructură feroviară, August 2026 (2026-09)read Oct 2, 2026
  12. Capital.ro: Ministerul Transporturilor dă startul celor mai mari proiecte de pe calea ferată (2017-06-19)read Oct 2, 2026