Craiova – Drobeta-Turnu Severin – Caransebeș railway rehabilitation
Rehabilitation of the 225.29 km Craiova – Filiași – Drobeta-Turnu Severin – Băile Herculane – Caransebeș line (km 248+760 – km 474+046.53), part of the Orient/East-Med corridor, in six design-and-build lots. Five lots have contracts (values per lot below, on differing price years and VAT bases); for lot 3, CFR has designated FCC Construccion as winner without a published signing. The line is to be electrified at 25 kV with ERTMS level 2. Lots 5 and 6 include new double-track tunnels at Poarta, and CFR plans to close Drobeta Turnu Severin – Caransebeș from February 2027 to February 2032.
- Total length
- 225 km
- Open today
- 0 km
- Sections
- 6
- Cost on record
- €1.3B
- 3 of 6 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Lot 1: Craiova – Filiași Design-and-build contract signed on 31 March 2026 with the TrackWorks association (Alstom Transport lead, Terna), RON 2,037,420,531.88 excluding VAT: 12 months of design, 42 months of works, 120 months of guarantee. CFR gives the lot as km 248+760 – km 286+735 and no works start date. Electrification at 25 kV, ERTMS level 2, freight at 100–120 km/h and passenger trains at 120–160 km/h. Length from the CFR chainage; the drawn line follows the existing track between the station areas. | Tendered | 38 km |
| – |
|
| 12 mo design · 42 mo execution · 120 mo guarantee · Contract value lei 2B |
| Lot 2: Filiași – Igiroasa Design-and-build contract signed on 20 July 2026 with the TrackWorks association (Alstom Transport lead, Terna), RON 1,800,131,764.37 excluding VAT: 12 months of design, 48 months of works, 120 months of guarantee. CFR gives the lot as km 286+735 – km 331+000 and no works start date. Length from the CFR chainage. | Tendered | 44 km |
| – |
|
| 12 mo design · 48 mo execution · 120 mo guarantee · Contract value lei 1.8B |
| Lot 3: Igiroasa – Drobeta-Turnu Severin On 25 June 2026 CFR announced FCC Construccion S.A. as the designated winner with an offer of RON 5,166,618,843.00 excluding VAT; no contract signing has been published. The estimated contract value was RON 5,167.14 – 6,152.38 million excluding VAT. Planned duration 135 months: 12 months of design, 60 months of works, at least 60 months of guarantee, 3 months after final acceptance. CFR gives the lot as km 331+000 – km 362+632, including the links to the Prunișor and Drobeta Marfă stations and the Dudașu junction. Length from the CFR chainage. | Tendered | 32 km | – | – |
| – | – |
| Lot 4: Drobeta-Turnu Severin – Băile Herculane Design-and-build contract signed on 23 June 2025 with the association of İçtaş İnşaat (lead) and Rotary Construcții Mentenanță, RON 2,309,944,931.12 excluding VAT: 12 months of design, 60 months of works, 120 months of guarantee. CFR gives the lot as km 362+632 – km 404+250, with seven existing tunnels rehabilitated (Moșu, Baba, Vir, Vârciorova, Bahna, Alion, Tufari) and a maximum speed of 100 km/h. CFR plans to close the Drobeta Turnu Severin – Caransebeș section to traffic from February 2027 to February 2032 for lots 4 to 6. | Tendered | 42 km |
| – |
|
| 12 mo design · 60 mo execution · 120 mo guarantee · Contract value lei 2.3B |
| Lot 5: Băile Herculane – Nou Poarta Design-and-build contract signed on 27 August 2025 with PORR Construct, RON 2,143,133,821.65 excluding VAT (CFR calls it the estimated total value): 12 months of design and 48 months of works, 60 months in all. CFR gives the lot as km 404+250 – km 436+887 (Cap X Băile Herculane – Cap X Nou Poarta halt), with the Rachitoberg tunnel (496 m) rehabilitated and the new double-track Poarta I tunnel (1,279 m) built, at a maximum speed of 100 km/h. CFR plans to close the Drobeta Turnu Severin – Caransebeș section to traffic from February 2027 to February 2032 for lots 4 to 6. | Tendered | 33 km |
| – |
|
| 12 mo design · 48 mo execution · Contract value lei 2.1B |
| Lot 6: Nou Poarta – Caransebeș Design-and-build contract announced on 11 December 2025 with the association of İçtaş İnşaat (lead) and Rotary Construcții Mentenanță, RON 2,114,352,202.96 (CFR does not say whether VAT is included): 12 months of design, 60 months of works, 120 months of guarantee. CFR gives the lot as km 436+887 – km 474+046.53, with the Feneș and Tâmpa tunnels rehabilitated (Tâmpa widened), the new double-track Poarta 2 (550 m) and Poarta 3 (305 m) tunnels built, and a maximum speed of 120 km/h. CFR plans to close the Drobeta Turnu Severin – Caransebeș section to traffic from February 2027 to February 2032 for lots 4 to 6. | Tendered | 37 km |
| – |
|
| 12 mo design · 60 mo execution · 120 mo guarantee · Contract value lei 2.1B |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- National budget225 km6 sections
- State budget through the Ministry of Transport and Infrastructure
- Transport Programme 2021–2027 and the state budget through the Ministry of Transport and Infrastructure
- European Union151 km4 sections
- Transport Programme 2021–2027 (external non-reimbursable funds)
- Proposed for funding from the Transport Programme 2021–2027 (external non-reimbursable funds)
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- TunnelsRomanian railway tunnelsSame contractor: Alstom, Porr, Rotary Construcții Mentenanță, İçtaş, İçtaş – Rotary Construcții Mentenanță JV
- RailwaysSofia – Dragoman railway modernisationSame contractor: TERNA
- RailwaysSofia – Plovdiv railway modernisationSame contractor: Porr
- HighwaysA1 Motorway Athens – Thessaloniki – Evzonoi (PATHE)Same contractor: TERNA
- HighwaysA29 Siatista – Kastoria – KrystallopigiSame contractor: TERNA
- HighwaysA5 Ionia Odos (Antirrio – Ioannina)Same contractor: TERNA
Sources
- CFR SA: Semnarea contractului pentru reabilitarea liniei feroviare Craiova – Drobeta Turnu Severin – Caransebeș, Lot 1 Craiova – Filiași (2026-03-31)read Oct 5, 2026
- CFR SA: CFR S.A. a semnat contractul de 1,8 miliarde de lei pentru reabilitarea lotului Filiași – Igiroasa (2026-07-20)read Oct 5, 2026
- CFR SA: CFR S.A. anunță desemnarea ofertei câștigătoare pentru Lotul 3 Igiroasa – Drobeta Turnu Severin (2026-06-25)read Oct 5, 2026
- CFR SA: Semnarea contractului pentru modernizarea liniei feroviare Drobeta Turnu Severin – Băile Herculane, Lot 4 (2025-06-23)read Oct 5, 2026
- CFR SA: Semnare contract pentru proiectare și execuție, Reabilitarea liniei feroviare Craiova – Drobeta Turnu Severin – Caransebeș, Lot 5 Cap X Băile Herculane – Cap X PO Nou Poarta (2025-08-27)read Oct 5, 2026
- CFR SA: Start pentru Lotul 6 al proiectului Craiova – Caransebeș (2025-12-11)read Oct 5, 2026
- CFR SA: Precizări CFR S.A. privind închiderea planificată a liniei Drobeta Turnu Severin – Caransebeș, pentru lucrări de modernizare (2026-06-19)read Oct 5, 2026
- OpenStreetMap contributors (geometry of the existing Craiova – Caransebeș line, ODbL)read Oct 5, 2026