Sofia – Dragoman railway modernisation
Modernisation of the Sofia – Dragoman – Serbian border line, in two lots: a new third track and a new Obelya station between Sofia Central and Voluyak (10 km), and partial doubling with ERTMS between Voluyak and Dragoman (33.34 km). The Dragoman – Serbian border section is not part of this project.
- Total length
- 43 km
- Open today
- 0 km
- Under construction
- 43 km
- Sections
- 2
- Cost on record
- €381.664M
- 2 of 2 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Sofia Central – Voluyak Design and construction contract: BGN 199,850,060.56 excluding VAT, 10 km of double line (NRIC). Scope: new third electrified track from Sofia Central to Voluyak, new six-track Obelya station with a link to the metro, new station buildings at Voluyak and Obelya, renewed Nadezhda and Vrabnitsa stops. Contract signed on 30 October 2020; construction was officially launched on 13 July 2021; NRIC still lists Obelya station as to be built. A separate signalling and ERTMS contract (IRTMS KA Voluyak DZZD, BGN 45,499,420.29 excluding VAT) is not included in the figure above. The stated length includes the station track layouts; the line drawn between the two station centres measures 8.0 km on OpenStreetMap. | Under construction | 10 km |
| – |
|
| Contract value лв199.85M |
| Voluyak – Dragoman Partial doubling of the single-track electrified line for 160 km/h passenger and 120 km/h freight trains. A new second track is built from Voluyak to Aldomirovtsi West (km 9+200 – 36+420); stations Kostinbrod, Petarch, Aldomirovtsi and Dragoman are rebuilt and a new Slivnitsa station is added. Two contracts of 22 March 2021: no. 11366, Voluyak – Petarch (about 12 km of doubling, BGN 91,999,000 excluding VAT), DZZD VISTRA; no. 11365, Petarch – Dragoman (about 17 km of doubling and 6.5 km of single-track modernisation, plus signalling, BGN 275,000,000 excluding VAT), TERNA AD. Works started on Petarch – Dragoman on 20 January 2023 and on Voluyak – Petarch on 18 September 2024. NRIC put overall physical progress at nearly 43% on 27 March 2025, with completion expected by the end of 2027, and reports significant delay. The ERTMS contractor was still being selected. The new border station beyond Dragoman, due by 2030, belongs to the Dragoman – Serbian border section. | Under construction | 33 km |
| – |
|
| Contract value лв366.999M |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union43 km2 sections
- Connecting Europe Facility, approved July 2015. Project total EUR 104,211,047: CEF EUR 76,074,064, national co-financing EUR 13,297,326, NRIC EUR 14,839,656. These are project-level figures, not the construction contract.
- Transport Connectivity Programme 2021–2027, phase 2, grant agreement DPTS-11/09.12.2024: project value BGN 331,747,941.77, of which EU contribution BGN 281,985,750.51 and national co-financing BGN 49,762,191.26. This is a grant, not the cost of the works.
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysA1 Motorway Athens – Thessaloniki – Evzonoi (PATHE)Same contractor: TERNA
- HighwaysA29 Siatista – Kastoria – KrystallopigiSame contractor: TERNA
- HighwaysA5 Ionia Odos (Antirrio – Ioannina)Same contractor: TERNA
- HighwaysA7 Moreas Motorway (Corinth – Tripoli – Kalamata) and A71 Lefktro – SpartiSame contractor: TERNA
- HighwaysA8 Olympia Odos MotorwaySame contractor: TERNA
- HighwaysBOAK Northern Crete Motorway (Kissamos – Agios Nikolaos)Same contractor: TERNA
Sources
- ДП НКЖИ: Развитие на жп възел София – железопътен участък София-Волуякread Oct 5, 2026
- 3E news: Започва мащабна модернизация на жп инфраструктурата между София и Волуяк за близо 200 млн. лв. (2021-07-13)read Oct 5, 2026
- ДП НКЖИ: Проект Модернизация на железопътната линия София – Драгоман – сръбска граница, жп участък Волуяк – Драгоман, Фаза 2read Oct 5, 2026
- ДП НКЖИ: Подписаха два ключови договора за развитието на железопътен възел София (2020-10-30)read Oct 5, 2026
- ДП НКЖИ: Подписаха договорите за модернизация на жп участък Волуяк-Драгоман (2021-03-22)read Oct 5, 2026
- ДП НКЖИ: Стартира модернизацията на железопътния участък Петърч-Драгоман (2023-01-20)read Oct 5, 2026
- ДП НКЖИ: Стартира модернизацията на железопътния участък Волуяк – Петърч (2024-09-18)read Oct 5, 2026
- ДП НКЖИ: Ръководството на НКЖИ направи пълен обход и проверка на строителните дейности по проекта за модернизация на участъка Волуяк-Драгоман (2025-03-27)read Oct 5, 2026
- OpenStreetMap contributors (geometry, ODbL)read Oct 5, 2026