Sofia – Plovdiv railway modernisation

Modernisation of line 1 between Sofia and Plovdiv, about 154 km, in four parts. Septemvri – Plovdiv (53.5 km) was rebuilt for 160 km/h and commissioned in March 2017. Sofia – Elin Pelin (23 km), Elin Pelin – Kostenets (51 km in three lots, with Bulgaria's longest railway tunnel at 6.8 km) and Kostenets – Septemvri (24.5 km) are under construction.

Total length
152 km
Open today
54 km
Sections
6
Cost on record
€34.402M
1 of 6 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Sofia – Plovdiv railway modernisation: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Sofia – Elin Pelin

Double-track electrified line of about 23 km through Poduyane, Iskar and Kazichene stations (Sofia and Elin Pelin stations are outside the 2023 contract), part of the Sofia – Plovdiv modernisation. The 2023 contract (up to 24 months, BGN 63,336,032.24 excluding VAT) covers only the Sofia – Iskar finishing works. Double-track running was suspended in 2018 during the works; NRIC restored it on the 13 km Iskar – Elin Pelin stretch with its own forces on 9 May 2025. The drawn geometry follows the OpenStreetMap line, 22.55 km from Sofia Central Station to the start of the Elin Pelin – Kostenets project at km 22+554. Contractor in Cyrillic: Транспортно строителство и възстановяване ЕАД (ТСВ ЕАД).

Under construction23 km––
  • European UnionConnecting Europe Facility
  • Transportno stroitelstvo i vazstanovyavane EAD (TSV EAD)Builder
24 mo execution · Contract value лв63.34M
Elin Pelin – Kostenets, lot 1: Elin Pelin – Vakarel

Km 22+554 to 42+200 (length from the chainage), the hardest stretch of the Sofia – Plovdiv line. It includes Bulgaria's longest railway tunnel at 6.8 km, the first of its kind since the Koznitsa tunnel of 1949–1951, a new Elin Pelin station, Pobit Kamak halt and Vakarel passing loop, two twin-bore tunnels of about 1.5 km in total, and 8 bridges and trestles. Construction supervision: Zhp Trans DZZD. The 51.044 km project (14.544 km renewed, 36.5 km new double track) is designed for 160 km/h passenger and 120 km/h freight traffic. NRIC gives the total as BGN 1.310 billion and says works started with considerable delay after appeals against detailed plans, slow land expropriation and COVID-19, so the project was split into two funding phases.

Under construction20 km––
  • European UnionPhase 1: Operational Programme Transport and Transport Infrastructure 2014–2020. Phase 2: Transport Connectivity Programme 2021–2027, grant agreement DPTS-7/11.09.2024 for the whole Elin Pelin – Kostenets project: project value BGN 907.80 million, EU contribution BGN 600.21 million and national co-financing BGN 105.92 million (NRIC marks the project value and the national share as excluding VAT).
  • Dzhen-Duy zhp Elin Pelin DZZDBuilder
–
Elin Pelin – Kostenets, lot 2: Vakarel – Ihtiman

Km 42+200 to 62+400 (length from the chainage). Includes Verinsko halt, Ihtiman station and Stambolovo halt, 4 overpasses, 3 bridges and 39 culverts. Construction supervision: Zhp Trans DZZD. The 51.044 km project (14.544 km renewed, 36.5 km new double track) is designed for 160 km/h passenger and 120 km/h freight traffic. NRIC gives the total as BGN 1.310 billion and says works started with considerable delay after appeals against detailed plans, slow land expropriation and COVID-19, so the project was split into two funding phases.

Under construction20 km––
  • European UnionPhase 1: Operational Programme Transport and Transport Infrastructure 2014–2020. Phase 2: Transport Connectivity Programme 2021–2027, grant agreement DPTS-7/11.09.2024 for the whole Elin Pelin – Kostenets project: project value BGN 907.80 million, EU contribution BGN 600.21 million and national co-financing BGN 105.92 million (NRIC marks the project value and the national share as excluding VAT).
  • Evro pat DZZDBuilder
–
Elin Pelin – Kostenets, lot 3: Ihtiman – Kostenets

Km 62+400 to 73+598 (length from the chainage). Includes 8 single-bore tunnels for double track of about 5,478 m in total, 2 viaducts of about 1,005 m and 11 bridges of about 777.70 m, and Nemirovo halt. Construction supervision: Zhp Trans DZZD. The 51.044 km project (14.544 km renewed, 36.5 km new double track) is designed for 160 km/h passenger and 120 km/h freight traffic. NRIC gives the total as BGN 1.310 billion and says works started with considerable delay after appeals against detailed plans, slow land expropriation and COVID-19, so the project was split into two funding phases.

Under construction11 km––
  • European UnionPhase 1: Operational Programme Transport and Transport Infrastructure 2014–2020. Phase 2: Transport Connectivity Programme 2021–2027, grant agreement DPTS-7/11.09.2024 for the whole Elin Pelin – Kostenets project: project value BGN 907.80 million, EU contribution BGN 600.21 million and national co-financing BGN 105.92 million (NRIC marks the project value and the national share as excluding VAT).
  • Shtrabag Dzhi Pi Reyl 2017 DZZDBuilder
–
Kostenets – Septemvri

About 24.5 km of double electrified line: 3 tunnels of 4.6 km in total, 23 bridges and viaducts of 2.49 km, a new Kostenets station and reconstruction of Belovo station. NRIC gives the total project value as BGN 300,251,198 excluding VAT. In August 2025 the deputy prime minister said the 2.5 km tunnel had broken through and that, despite delays, the line would be built for 160 km/h by 2029. Construction supervision: Iver DZZD. The drawn geometry is 25.3 km from OpenStreetMap, cut at the end of the Elin Pelin – Kostenets lot 3 and at Septemvri station.

Under construction25 km
  1. 2029Expected opening
–
  • European UnionConnecting Europe Facility, financing agreement signed 10 November 2016.
  • National budget
  • Kostenets-Septemvri 2018 DZZDBuilder
–
Septemvri – Plovdiv

Track for 160 km/h passenger trains (200 km/h tilting stock) and 120 km/h freight, catenary, signalling with ETCS level 1, in three positions: Septemvri – Pazardzhik (BGN 57.08 million, Svitelski-RVP Kyone), Pazardzhik – Stamboliyski (BGN 49.84 million, Ay Dzhi Ey – Zhp Infrastruktura) and Stamboliyski – Plovdiv (BGN 50.93 million, Porr Bau), plus a BGN 69.25 million signalling and telecommunications contract (TKB Sofia-Plovdiv), all excluding VAT. NRIC records all four as commissioned in March 2017. Total project value BGN 630,626,259.28. BTA reported on 24 September 2026 that a demonstration run covered the 53.5 km at 160 km/h in 25 minutes, against 40 minutes at 80 km/h with older stock. NRIC chainage runs from km 102+014 to km 154+606 (52.6 km). The drawn geometry is 52.3 km from OpenStreetMap.

Opened54 km
  1. Mar 2017Opened
–
  • European UnionCohesion Fund, Operational Programme Transport.
  • National budget
  • OtherCo-financing by NRIC.
  • Svitelski-RVP Kyone consortiumBuilder
  • Ay Dzhi Ey – Zhp Infrastruktura DZZDBuilder
  • Porr Bau GmbHBuilder
  • TKB Sofia-Plovdiv consortiumBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union152 km
    6 sections
    • Connecting Europe Facility
    • Phase 1: Operational Programme Transport and Transport Infrastructure 2014–2020. Phase 2: Transport Connectivity Programme 2021–2027, grant agreement DPTS-7/11.09.2024 for the whole Elin Pelin – Kostenets project: project value BGN 907.80 million, EU contribution BGN 600.21 million and national co-financing BGN 105.92 million (NRIC marks the project value and the national share as excluding VAT).
    • Connecting Europe Facility, financing agreement signed 10 November 2016.
    • Cohesion Fund, Operational Programme Transport.
  • National budget78 km
    2 sections
  • Other54 km
    1 section
    • Co-financing by NRIC.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • TEN-T core networkTEN-T

Sources

  1. NRIC: Модернизация на железопътната линия София - Пловдив: жп участък Елин Пелин – Костенец, Фаза 2 (PDF)read Oct 5, 2026
  2. NRIC: Модернизация на железопътен участък Костенец - Септемвриread Oct 5, 2026
  3. NRIC: Строителството на жп линията между Костенец и Септември вече напредва с добри темпове (26.08.2025)read Oct 5, 2026
  4. NRIC: Проектиране и строителство за модернизация на железопътен участък София – Елин Пелинread Oct 5, 2026
  5. NRIC: Модернизация на участъка от гара Искър до гара Елин Пелин (09.05.2025)read Oct 2, 2026
  6. NRIC: Модернизация на железопътен участък Септември – Пловдив – част от Транс-европейската железопътна мрежаread Oct 5, 2026
  7. BTA: До май месец 2027 г. БДЖ ще разполагат с общо 60 нови мотриси до 160 км/ч (24.09.2026)read Oct 5, 2026
  8. OpenStreetMap contributors (geometry, ODbL)read Oct 5, 2026

Figures last checked against their sources in Oct 5, 2026.