S7 expressway (Gdańsk – Elbląg – Warszawa – Radom – Kielce – Kraków – Rabka)

Poland's longest north–south expressway, from Gdańsk to Rabka-Zdrój, drawn as one carriageway from OpenStreetMap relation 112778. Much of it follows the former DK7 corridor, and several lots are rebuilds of that road to expressway standard (Elbląg bypass, Miłomłyn bypass, Szydłowiec bypass, Kielce bypass, Płońsk bypass, Zakroczym – Czosnów, Czosnów – Kiełpin) rather than new roads, so an upgrade date is not a new-build opening. Lots cover the sections opened since 2005 or under construction, grouped by contract and split wherever the parts opened in different years, so each lot carries its own opening date; a lot whose parts opened within one year carries the date of its last part, with the earlier openings listed as events. Not drawn: Kiełpin – Warszawa (design stage), the Warszawa stretch carried by S2 and S8, Głuchów – Radom Północ (older sections), Mistrzejowice – Nowa Huta and the Nowa Huta – Bieżanów eastern ring road of Kraków, Myślenice – Lubień, and the planned Kraków – Myślenice and Rabka – Chyżne sections. Contract values come from GDDKiA pages and pl.wikipedia; each note states the VAT basis where the source gives one and says so where it does not.

Total length
598 km
Open today
589 km
Under construction
9 km
Sections
33
Cost on record
€3.9B
15 of 33 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of S7 expressway (Gdańsk – Elbląg – Warszawa – Radom – Kielce – Kraków – Rabka): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Chwaszczyno – Gdańsk Południe (Metropolitan Ring Road of the Tri-City)

Two sub-sections of 16.2 km and 16 km, tendered on 19 August 2020 and signed on 16 April 2021 (pl.wikipedia). The missing ramps at the Chwaszczyno junction, giving direct S6 – S7 movements, opened on 22 September 2025. The drawn centreline starts at the Chwaszczyno junction; the planned northern extension to Gdynia is not drawn.

Opened32 km
  1. Apr 16, 2021Tender awarded
  2. Dec 23, 2025Opened
––––
Gdańsk Południe – Koszwały (southern bypass of Gdańsk)

Built in 2010–2012 by a consortium of Bilfinger Berger (leader) and Wakoz, linking the Tri-City ring road and the A1 with the former DK7 (pl.wikipedia). The drawn centreline is 9% shorter than the sourced 18.0 km; the sourced length is kept.

Opened18 km
  1. Jun 9, 2012Opened
––
  • Bilfinger BergerBuilder
  • WakozBuilder
–
Koszwały – Nowy Dwór Gdański – Kazimierzowo

Two contracts signed on 9 October 2015: Koszwały – Nowy Dwór Gdański (20.47 km, Metrostav, more than 1.642 bn PLN) and Nowy Dwór Gdański – Kazimierzowo (19.14 km per GDDKiA, 19.5 km per pl.wikipedia, Budimex, 1.576 bn PLN per pl.wikipedia). Built in 2015–2019 and opened together on 31 October 2018. The Budimex contract included a viaduct on ul. Żuławska in Elbląg. The drawn centreline ends at the Elbląg Południe junction, 4% longer than the sourced 40 km.

Opened40 km
  1. Oct 9, 2015Tender awarded
  2. Oct 31, 2018Opened
––
  • MetrostavBuilder
  • BudimexBuilder
Contract value zł3.2B
Elbląg Południe – Elbląg Wschód (Elbląg bypass)

Sum of two entries listed by pl.wikipedia (4.2 km section rebuilt from DK7 in 2005–2007, and the 0.7 km Elbląg Wschód junction, a rebuild of an existing interchange from 2004–2005). The drawn centreline follows the DK7 corridor.

Opened5 km
  1. Sep 14, 2007Opened
––––
Elbląg Wschód – Pasłęk Północ

Built in 2008–2011 by a consortium led by Eurovia Polska, for 662.1 million PLN (VAT basis not stated). The contract also added the missing ramp at the Raczki (now Elbląg Południe) junction.

Opened14 km
  1. Jul 28, 2011Opened
––
  • Eurovia PolskaBuilder
–
Pasłęk Północ – Pasłęk – Miłomłyn Północ

Works began in 2010 (pl.wikipedia, no month given). The sources read do not name the contractor or the contract value.

Opened37 km
  1. 2010Construction start
  2. Aug 1, 2012Opened
––––
Miłomłyn Północ – Ostróda Północ

The Miłomłyn bypass opened as a single carriageway on 9 December 1997 and was rebuilt in 2014–2016 together with DK7 up to Czerwona Karczma. Contract signed on 5 November 2014 with Budimex and Ferrovial Agroman: 20 months, winter periods (15 December to 15 March) excluded. The Miłomłyn Północ and Południe junctions were rebuilt to expressway standard.

Opened9 km
  1. Nov 5, 2014Tender awarded
  2. Dec 19, 2016Opened
––
  • BudimexBuilder
  • Ferrovial AgromanBuilder
20 mo execution · Contract value zł292.3M
Ostróda Północ – Ostróda Południe – Rychnowo – Olsztynek Zachód

Sum of three sections (9.7 + 8.8 + 11.2 km), all opened in 2017. Ostróda Północ – Południe: Budimex with Ferrovial Agroman, signed on 15 June 2015 for 1.3 bn PLN (pl.wikipedia, GDDKiA); that contract also covers the 8.7 km Ostróda bypass on DK16, so it is not recorded as the cost of this lot. Its last structure, the Niepodległości bridge over the Pauzeński canal, opened on 20 June 2018. Ostróda Południe – Rychnowo: Strabag Infrastruktura Południe (formerly Heilit+Woerner), 299.2 million PLN. Rychnowo – Olsztynek Zachód: Strabag, 388.5 million PLN. VAT basis of the pl.wikipedia figures is not stated. The section lengths are contract lengths and do not match the junction-to-junction distance on the drawn line exactly.

Opened30 km
  1. Jun 15, 2015Tender awarded
  2. Dec 22, 2017Opened
––
  • BudimexBuilder
  • Ferrovial AgromanBuilder
  • Strabag Infrastruktura PołudnieBuilder
  • StrabagBuilder
–
Olsztynek Zachód – Grunwald – Nidzica Północ

GDDKiA gives 31.3 km of expressway for the contract (3 km of S7 opened on 29 September 2012 plus 28.3 km, pl.wikipedia). The contract value was over 1.185 bn PLN, but it also covers the 5.7 km Olsztynek bypass on S51, so it is not recorded as the cost of this lot. Junctions Olsztynek Wschód, Olsztynek Zachód, Grunwald, Waplewo and Rączki. The drawn centreline is 17% shorter than 31.3 km: it runs between the OpenStreetMap junction nodes Olsztynek Zachód and Nidzica Północ (the GDDKiA chainage km 175+800 to 203+600 is 27.8 km).

Opened31 km
  1. May 2009Tender awarded
  2. Nov 8, 2012Opened
––––
Nidzica Północ – Nidzica Południe – Napierki

Two contracts: Nidzica Północ – Nidzica Południe (9.1 km, Strabag, 229.4 million PLN) and Nidzica Południe – Napierki (13.6 km, Strabag Infrastruktura Południe, 263.1 million PLN), signed on 22 January 2015. GDDKiA gives a total project cost of 629.75 million PLN including documentation, land and supervision; it is not recorded as a contract value. Junctions Nidzica Północ, Nidzica Południe, Powierż and Napierki. The drawn centreline is 20% shorter than the sourced 22.7 km: the sourced lengths run beyond the junction nodes at both ends (GDDKiA chainage km 203+500 to 225+100 is 21.6 km).

Opened23 km
  1. Jan 22, 2015Tender awarded
  2. Jun 23, 2017Opened
––
  • StrabagBuilder
  • Strabag Infrastruktura PołudnieBuilder
Contract value zł492.5M
Napierki – Mława – Strzegowo – Płońsk

Four contracts: Napierki – Mława (about 14 km, Strabag consortium, 294.7 million PLN, signed on 20 December 2017, ZRID of 6 March 2020), Mława – Strzegowo (about 21.5 km, PORR S.A. and PORR Bau GmbH, 446.1 million PLN, signed on 20 December 2017, ZRID of 9 October 2019), Strzegowo – Pieńki (about 22 km, Strabag consortium, 516.2 million PLN) and Pieńki – Płońsk (about 13.7 km, Strabag consortium, 311.7 million PLN), the last two signed on 12 January 2018 with a ZRID of 30 August 2019. GDDKiA states 34 months for each contract and gives the contract amounts without a VAT basis; pl.wikipedia rounds two of them to 294.8 and 446.2. Lengths are 35.5 km (Napierki – Strzegowo) and 35.7 km (Strzegowo – Płońsk). The drawn centreline runs from Napierki to Płońsk Północ.

Opened71 km
  1. Dec 20, 2017Tender awarded
  2. Sep 13, 2019Construction start
  3. Dec 23, 2022Opened
––
  • StrabagBuilder
  • Strabag Infrastruktura PołudnieBuilder
  • PORR S.A.Builder
  • PORR Bau GmbHBuilder
34 mo total · Contract value zł1.6B
Płońsk eastern bypass (Płońsk Północ – Płońsk Południe)

DK7 rebuilt to expressway standard on km 275+700 to 280+400 of the Płońsk bypass, with three junctions (Płońsk Północ, Płońsk, Siedlin), built from 28 September 2007 to 31 May 2009 by a Teerag-Asdag consortium for about 200 million PLN (pl.wikipedia, VAT basis not stated). GDDKiA gives the opening as 3 June 2009.

Opened5 km
  1. Sep 28, 2007Construction start
  2. Jun 3, 2009Opened
––
  • Teerag-AsdagBuilder
–
Płońsk Południe – Załuski – Modlin – Czosnów

Three design-build contracts: Płońsk Południe (Siedlin) – Załuski (12.9 km), Załuski – Modlin (12 km) and Modlin – Czosnów (9.7 km). Modlin – Czosnów was signed on 12 May 2020 with Budimex for about 598.8 million PLN (VAT basis not stated), 36 months, and is rebuilt in place of DK7 with three lanes per direction; the sources read do not name the contractors of the other two contracts, so none is recorded for them, and no lot total is recorded. Between Zakroczym and Czosnów (14.6 km) the former expressway, opened as 2x2 on 16 June 1990, was widened to two carriageways of three lanes. The ZRID for Siedlin – Załuski was issued on 2 May 2023. The drawn centreline ends where OpenStreetMap stops tagging the road as S7, 4% shorter than the sourced 34.6 km.

Opened35 km
  1. May 12, 2020Tender awarded
  2. Dec 19, 2025Opened
––
  • BudimexBuilder
–
Czosnów – Kiełpin

Design-build contract signed on 16 November 2023 with a consortium of Fabe Polska (leader), SP Sine Midas Stroy (Kazakhstan) and Yörük Yapı İnşaat (Turkey), 536.3 million PLN, 36 months from signing with winter periods (16 December to 15 March) not counted. The existing two-lane dual carriageway DK7 becomes an expressway with three lanes plus a hard shoulder in each direction, with junctions Czosnów, Palmiry and Sadowa. The ZRID permits for sections A and B were issued on 11 March 2026 and the site of section A was handed over on 16 March 2026. The GDDKiA project site still gives May 2027 as the planned end (17 months were allowed for design and ZRID, which came about a year later) and reported works progress of 7.47% in October 2026; pl.wikipedia gives May 2028 without an official source, so no expected opening is recorded. The road is built in place of DK7: OpenStreetMap has no separate S7 alignment here (some DK7 ways carry highway=construction, ref 7), so the drawn centreline follows the existing DK7. It is 30% longer than the sourced 9 km because it starts where OpenStreetMap stops tagging S7 near Czosnów and ends where the proposed Kiełpin – Warszawa S7 begins.

Under construction
35 of 36 contracted months
9 km
  1. Nov 16, 2023Tender awarded
  2. Mar 16, 2026Construction start
  3. ≈2026Expected openingProjected from contract
––
  • Fabe PolskaBuilder
  • SP Sine Midas StroyBuilder
  • Yörük Yapı İnşaatBuilder
36 mo total · Contract value zł536.3M
Warszawa Lotnisko – Zamienie – Lesznowola

Section A of the Warszawa – Grójec project, 6.6 km from the Warszawa Lotnisko junction to the Lesznowola junction, with the Zamienie junction; three lanes per direction. The planned completion in the first contracts was April 2021. The drawn centreline starts at the Warszawa Lotnisko junction ramps and is 21% shorter than the sourced 6.6 km; the road north of it is shared with S2 and S8 and is not drawn.

Opened7 km
  1. Aug 17, 2017Tender awarded
  2. Aug 30, 2022Opened
––
  • PolaquaBuilder
Contract value zł457.3M
Lesznowola – Antoninów – Złotokłos – Tarczyn Północ

Section B of the Warszawa – Grójec project, 14.8 km (pl.wikipedia: about 15 km), two lanes per direction with a reserve for a third. The Antoninów junction opened on 31 August 2023 and the Tarczyn Północ junction on 30 October 2023; the road was designated an expressway on 22 March 2024 (pl.wikipedia). The lot is shown as opened on the day the main carriageways opened.

Opened15 km
  1. Aug 17, 2017Tender awarded
  2. Apr 28, 2023Opened
––
  • PTU IntercorBuilder
Contract value zł510.5M
Tarczyn Północ – Tarczyn Południe – Głuchów (start of the Grójec bypass)

Section C of the Warszawa – Grójec project, 7.9 km from the crossing with the former DK7 near Pamiątka to the existing Grójec bypass, with the Tarczyn Południe junction. Marked as an expressway from May 2021 (pl.wikipedia). The Tarczyn Północ junction at its start belongs to the previous lot. The drawn centreline is 15% longer than the sourced 7.9 km.

Opened8 km
  1. Aug 17, 2017Tender awarded
  2. Dec 17, 2020Opened
––
  • Mota-Engil Central EuropeBuilder
Contract value zł203.4M
Western Radom bypass (Radom Północ – Radom Południe)

Design-build contract with Dragados (729.4 million PLN per pl.wikipedia; GDDKiA gives about 728.2 million PLN for the construction works at opening), 2015–2018, with four junctions (Radom Północ, Radom Zachód, Wolanów, Radom Południe) and 27 bridge structures.

Opened25 km
  1. Jul 29, 2015Tender awarded
  2. Aug 2015Construction start
  3. Oct 19, 2018Opened
––
  • DragadosBuilder
Contract value zł729.4M
Radom Południe – Szydłowiec – voivodeship border

Contract with Dragados signed on 3 July 2014 (pl.wikipedia). The section includes the Szydłowiec bypass, a 4.1 km single carriageway from 1992 rebuilt to an expressway with three junctions; elsewhere it mostly follows a new alignment east of DK7. The drawn centreline ends at the Mazowieckie – Świętokrzyskie voivodeship boundary, placed where the line crosses the OpenStreetMap boundary.

Opened22 km
  1. Jul 3, 2014Tender awarded
  2. Jul 12, 2017Opened
––
  • DragadosBuilder
–
Voivodeship border – Skarżysko-Kamienna Zachód

Contract with Budimex signed on 10 October 2017, 22 months excluding winters. The route runs west of the old DK7, with junctions Skarżysko-Kamienna Zachód and Północ, four viaducts and two bridges. The drawn centreline starts at the voivodeship boundary and is 16% shorter than the sourced 7.6 km, which probably includes the junction approaches.

Opened8 km
  1. Oct 10, 2017Tender awarded
  2. Dec 18, 2019Opened
––
  • BudimexBuilder
22 mo execution · Contract value zł259.8M
Skarżysko-Kamienna bypass

Short bypass opened on 19 December 2005; designated an expressway on 27 April 2011 together with the next section.

Opened2 km
  1. Dec 19, 2005Opened
––––
Skarżysko-Kamienna – Suchedniów – Występa

Section opened on 27 April 2011. The Występa end is placed by the cumulative sourced section lengths, because no junction marks it.

Opened17 km
  1. Apr 27, 2011Opened
––––
Występa – Wiśniówka (Kielce Północ junction)

Section with the Kielce Północ junction. The cuts at Występa and Wiśniówka are placed by the cumulative sourced section lengths.

Opened7 km
  1. Sep 19, 2009Opened
––––
Wiśniówka – Chęciny (north-western Kielce bypass)

The bypass was a single carriageway built in 1974–1984 and widened to 2x2 in 2010–2013, with the option of three lanes per direction. Junctions Kielce Zachód, Kielce Jaworznia and Kielce Południe (Chęciny).

Opened23 km
  1. Jul 10, 2013Opened
––––
Chęciny – Jędrzejów

Opened in stages in 2018; the planned end was the third quarter of 2017 and all works finished at the end of 2020, with contractual penalties of 60.6 million PLN charged to the contractor. A short stretch of about 1 km at Chęciny opened on 26 October 2018.

Opened22 km
  1. Jun 15, 2015Tender awarded
  2. Dec 21, 2018Opened
––
  • Salini PolskaBuilder
Contract value zł585.7M
Jędrzejów – Mierzawa – Wodzisław – voivodeship border (Moczydło)

Junctions Jędrzejów Wschód, Jędrzejów Południe (Łączyn), Mierzawa and Wodzisław. The Jędrzejów bypass (6.8 km, 2003–2005) was completed to two carriageways under this contract. The drawn centreline starts at the Jędrzejów Północ junction and ends where it crosses the Świętokrzyskie – Małopolskie boundary in OpenStreetMap, 6% longer than the sourced 20 km.

Opened20 km
  1. Oct 16, 2014Tender awarded
  2. Sep 23, 2017Opened
––
  • BudimexBuilder
–
Voivodeship border (Moczydło) – Książ – Miechów

The first tender for Moczydło – Szczepanowice (September 2015) ended without a contract after the environmental decision was annulled following protests in Poradów. Contract of 16 April 2020 with Intercor for more than 752.9 million PLN (VAT basis not stated), 31 months with winters excluded from the works period; junctions Książ and Miechów, 24 structures and two rest areas. pl.wikipedia gives August 2020 for the start of works; GDDKiA gives 27 July 2020. The drawn centreline ends after the Miechów junction and is within 1% of the sourced 18.7 km.

Opened19 km
  1. Apr 16, 2020Tender awarded
  2. Jul 27, 2020Construction start
  3. Sep 5, 2023Opened
––
  • IntercorBuilder
31 mo total · Contract value zł752.9M
Miechów – Szczepanowice

The last section of S7 in Małopolskie to be contracted. The first tender (September 2015) ended without a contract after the environmental decision was annulled following protests in Poradów. Works began in 2023 (pl.wikipedia, no month given). The drawn centreline spans the stretch between the Miechów and Szczepanowice junctions.

Opened5 km
  1. Feb 8, 2021Tender awarded
  2. 2023Construction start
  3. Aug 26, 2024Opened
––
  • Fabe PolskaBuilder
  • SP Sine Midas StroyBuilder
Contract value zł162.4M
Szczepanowice – Widoma

Contract signed on 8 January 2018, 34 months with winters excluded from the works period. The ZRID was issued on 23 August 2019 and the site handed over on 28 August 2019 (GDDKiA; pl.wikipedia gives the ZRID as 28 August). Two junctions (Szczepanowice and Widoma), 10 viaducts and one 681 – 689 m viaduct at Szczepanowice. GDDKiA gives 13.1 km; pl.wikipedia says about 14 km.

Opened13 km
  1. Jan 8, 2018Tender awarded
  2. Sep 11, 2019Construction start
  3. Oct 4, 2021Opened
––
  • Mota-Engil Central EuropeBuilder
34 mo total · Contract value zł508.1M
Widoma – Kraków Mistrzejowice

The contracts cover the whole 18.3 km Widoma – Kraków Nowa Huta (junctions Łuczyce, Raciborowice, Mistrzejowice and Grębałów), of which 13.3 km, without the Mistrzejowice junction, opened on 23 December 2024. The 2021 contract with Gülermak and Mosty Łódź is worth 1,545,681,714.00 PLN (VAT basis not stated), so it is not recorded as the cost of this lot. The ZRID decision of the Małopolska voivode is dated 20 July 2020 and the site was handed over a week later; Webuild (formerly Salini) was terminated on 7 December 2020 after only preparatory works. The Mistrzejowice interchange and the remaining 5 km of the Kraków ring road towards Nowa Huta were still being built at the time of the source and are not part of this lot.

Opened13 km
  1. Sep 26, 2018Tender awarded
  2. Dec 23, 2024Opened
––
  • GülermakBuilder
  • Mosty ŁódźBuilder
–
Lubień – Naprawa

7.6 km (7.5 km in the 2016 GDDKiA announcement), about 24% of it on structures and 49% in cuttings. Gross (brutto) contract value at signing: 521.52 million PLN (IDS-Bud with Altis-Holding, terminated); the replacement contracts were about 42.2 million (TBM, viaduct) and over 74.5 million PLN (Strabag, right carriageway, VAT basis not stated). A landslide halted work on the right carriageway and GDDKiA terminated the IDS-Bud contract on 17 July 2020; replacement contracts followed on 1 September 2020 (TBM) and 22 December 2020 (Strabag). The lot is shown as opened when traffic first ran over the whole length on one carriageway (20 December 2019); the second carriageway opened on 30 November 2021. The road ends at Naprawa and joins the Naprawa – Skomielna Biała tunnel section. The drawn centreline starts 2.4 km after the Lubień junction node: the sourced section lengths (7.6 + 3.1 km) place the start there, and the first kilometres from the node belong to the Lubień bypass opened in 2009, which is not drawn.

Opened8 km
  1. Jun 29, 2016Tender awarded
  2. Dec 20, 2019Opened
––
  • IDS-BudBuilder
  • Altis-HoldingBuilder
  • TBMBuilder
  • Strabag Infrastruktura PołudnieBuilder
–
Naprawa – Skomielna Biała (Luboń Mały tunnel)

3.1 km (GDDKiA: about 3.0 km) with the 2.058 km twin-tube Luboń Mały tunnel, drilled in Carpathian flysch cut by faults. The planned 54 months ran to the end of 2020, then to autumn 2021, and neither date was met (pl.wikipedia). Gross contract value at signing 968.84 million PLN (Astaldi). About 8 km of the 15.9 km Lubień – Rabka main line is on viaducts, bridges and in the tunnel. The tunnel is recorded as a profile figure, not as a separate lot. The drawn tunnel section is 2.05 km long.

Opened3 km
  1. Jun 29, 2016Tender awarded
  2. Nov 12, 2022Opened
–
  • European UnionEU co-financing of 1,322,398,015.17 PLN for the whole Lubień – Rabka-Zdrój project (three contracts, total contract value 2,471,380,000 PLN per GDDKiA); the agreement was signed on 11 September 2017. Recorded once, on this lot, and not as the cost of any one lot.
  • AstaldiBuilder
54 mo total · Contract value zł968.8M
Skomielna Biała – Rabka-Zdrój (Zabornia)

S7 Skomielna Biała – Rabka-Zdrój (Zabornia), 5.2 km, with the Skomielna Biała and Zabornia junctions. The contract signed on 31 March 2016 with Salini Impregilo, 615.07 million PLN gross, also covers the new DK47 Rabka-Zdrój – Chabówka (6.1 km in total from Skomielna Biała to Chabówka), so it is not recorded as the cost of this lot; 22 months were allowed. The S7 ends at the Zabornia junction; the Rabka-Zdrój – Chyżne section is only planned.

Opened5 km
  1. Mar 31, 2016Tender awarded
  2. Sep 28, 2019Opened
––
  • Salini ImpregiloBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union3 km
    1 section
    • EU co-financing of 1,322,398,015.17 PLN for the whole Lubień – Rabka-Zdrój project (three contracts, total contract value 2,471,380,000 PLN per GDDKiA); the agreement was signed on 11 September 2017. Recorded once, on this lot, and not as the cost of any one lot.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia (pl): Droga ekspresowa S7 (Polska)read Oct 9, 2026
  2. OpenStreetMap: route relation 112778 (S7, network PL:expressway)read Oct 9, 2026
  3. GDDKiA: Podpisano umowy na budowę dwóch odcinków S7 między Koszwałami a Elblągiem (9 Oct 2015)read Oct 9, 2026
  4. GDDKiA: Podpisano umowę na budowę S7 Miłomłyn-Ostróda Północ (5 Nov 2014)read Oct 9, 2026
  5. GDDKiA: Umowa na budowę siódemki i szesnastki wokół Ostródy podpisana (15 Jun 2015)read Oct 9, 2026
  6. GDDKiA: Obwodnica Olsztynka gotowa (29 Sep 2012)read Oct 9, 2026
  7. GDDKiA: Droga ekspresowa S7 Olsztynek – Nidzica jest już dostępna dla kierowców (8 Nov 2012)read Oct 9, 2026
  8. GDDKiA: S7 Nidzica – Napierki otwarta (23 Jun 2017)read Oct 9, 2026
  9. GDDKiA: Podpisanie umów na dwa odcinki S7 na Mazowszu (20 Dec 2017)read Oct 9, 2026
  10. GDDKiA: Komplet umów na budowę S7 między Płońskiem a Warmińsko-Mazurskiem (12 Jan 2018)read Oct 9, 2026
  11. GDDKiA: Kolejny ZRID na mazowiecki odcinek S7 (Mława – Strzegowo, 2019)read Oct 9, 2026
  12. Ministerstwo Infrastruktury: Kolejne kilometry S7 na Mazowszu udostępnione kierowcom (22 Dec 2021)read Oct 9, 2026
  13. GDDKiA: Ekspresowa obwodnica Płońska otwarta (3 Jun 2009)read Oct 9, 2026
  14. GDDKiA: Pierwsza umowa na projekt i budowę S7 Płońsk – Czosnów podpisana (12 May 2020)read Oct 9, 2026
  15. GDDKiA: S7 Czosnów – Kiełpin project siteread Oct 9, 2026
  16. GDDKiA: Przekazanie terenu budowy dla realizacji odcinka A (S7 Czosnów – Kiełpin, 16 Mar 2026)read Oct 9, 2026
  17. GDDKiA: Wydanie decyzji ZRID dla odcinka A i odcinka B (S7 Czosnów – Kiełpin, 11 Mar 2026)read Oct 9, 2026
  18. GDDKiA: S7 Czosnów – Kiełpin, postęp pracread Oct 9, 2026
  19. GDDKiA: S7 Warszawa – Grójec (project page with contract values)read Oct 9, 2026
  20. GDDKiA: GDDKiA podpisała kontrakty na budowę południowego wylotu trasy S7 (17 Aug 2017)read Oct 9, 2026
  21. GDDKiA: Kolejna umowa na budowę S7 do Krakowa (Moczydło – Miechów)read Oct 9, 2026
  22. GDDKiA: Mamy umowę z wykonawcą ostatniego odcinka S7 na terenie województwa małopolskiego (8 Feb 2021)read Oct 9, 2026
  23. GDDKiA: Umowa na projekt i budowę S7, odcinek II węzeł Szczepanowice – węzeł Widoma (8 Jan 2018)read Oct 9, 2026
  24. GDDKiA: Coraz bliżej ekspresowego połączenia Warszawy i Krakowa, kolejny odcinek S7 w budowie (11 Sep 2019)read Oct 9, 2026
  25. GDDKiA Kraków: Umowa na S7 Widoma – Kraków podpisana (15 Jul 2021)read Oct 9, 2026
  26. GDDKiA: S7 Widoma – Kraków zbuduje już nowy wykonawca (Dec 2020)read Oct 9, 2026
  27. GDDKiA Kraków: Dwie jezdnie na S7 Lubień – Naprawa (30 Nov 2021)read Oct 9, 2026
  28. GDDKiA: Pierwsza jezdnia S7 Lubień – Naprawa od jutra udostępniona kierowcom (19 Dec 2019)read Oct 9, 2026
  29. GDDKiA: Zakopianka w budowie, umowy na kolejne odcinki S7 podpisane (29 Jun 2016)read Oct 9, 2026
  30. GDDKiA: Umowa na budowę S7 Skomielna – Rabka Zdrój i dk 47 Rabka Zdrój – Chabówka została podpisana (31 Mar 2016)read Oct 9, 2026
  31. OpenStreetMap contributors (ODbL)read Oct 9, 2026

Figures last checked against their sources in Oct 9, 2026.