S19 expressway, Via Carpatia (Kuźnica – Białystok – Lublin – Rzeszów – Barwinek)

Expressway of about 570 km from the Belarus border at Kuźnica to the Slovak border at Barwinek, through Białystok, Lublin and Rzeszów. In October 2026 the northern end (Kuźnica – Sokółka Północ, Deniski – Boćki), the Lublin – Rzeszów sections, the Kock bypass, the Rzeszów bypass and Krosno – Dukla are open, and most of the remainder is under construction or contracted. The Białystok Zachód – Deniski gap and the stretch to the Lubelskie border are still in preparation. Lots follow GDDKiA contract sections, grouped where they share an opening date; cost figures are contract values at signing. Rzeszów Wschód – Rzeszów Zachód runs on A4 and Lublin Rudnik – Lublin Sławinek is shared with S12 and S17, so neither is drawn as an S19 lot. Domaradz – Krosno (12.5 km, also called Domaradz – Iskrzynia) is not drawn: its design-build contract of 7 November 2022 was terminated on 14 May 2026 with 13% of the work done, a new tender was announced on 1 September 2026, and OpenStreetMap maps no alignment for it. Geometry comes from OpenStreetMap, cut at junctions where they are mapped and otherwise by the sourced section lengths.

Total length
557 km
Open today
241 km
Under construction
86 km
Sections
35
Cost on record
€6.4B
30 of 35 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of S19 expressway, Via Carpatia (Kuźnica – Białystok – Lublin – Rzeszów – Barwinek): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Kuźnica – Sokółka Północ

Design-build, the northern end of S19 at the Belarus border. The main carriageway opened on 31 December 2025 and permanent traffic arrangements followed on 27 July 2026. The whole project is 15.79 km: 10.6 km to expressway standard and 5.2 km of dual carriageway DK19 in class GP from the border crossing to the Kuźnica junction, which is not drawn. The 10.6 km is the expressway length stated by GDDKiA Białystok; the OpenStreetMap centreline from the Kuźnica junction to Sokółka Północ is 8.9 km, 16% shorter. Contract value 526.22 million PLN (monthly table, gross); plwiki gives "over 526 million" for the whole project.

Opened11 km
  1. Mar 12, 2021Tender awarded
  2. Jan 11, 2023Construction start
  3. Dec 31, 2025Opened
––
  • PORR S.A.Builder
Contract value zł526.22M
Sokółka Północ – Czarna Białostocka

Design-build contract with Stecol Corporation signed on 21 June 2024; contract deadline 21 June 2028. The road permit (ZRID) application was filed on 22 April 2025 and the MSBD page records no decision, so the lot is shown as awarded, not under construction, although GDDKiA lists the stage as "Realizacja". Planned junctions: Sokółka Zachód, Geniusze, Straż and Czarna Białostocka; 28 structures. OpenStreetMap maps no alignment for the last part before Czarna Białostocka, so the drawn line stops where the mapped ways end and is not joined to the next lot. It is 17.9 km long, 26% shorter than the sourced 24.1 km.

Tendered24 km
  1. Jun 21, 2024Tender awarded
  2. Jun 21, 2028Expected opening
––
  • Stecol CorporationBuilder
Contract value zł828.83M
Czarna Białostocka – Białystok Północ

Design-build contract with Unibep signed on 19 February 2024; the road permit (ZRID) was issued on 24 June 2026 and the monthly table gives 8 July 2026 as the works start. The contract deadline is 19 November 2027 (monthly table). Includes the Wasilków junction; 20 structures. OpenStreetMap maps no alignment for the first part after Czarna Białostocka, so the drawn line starts where the mapped ways begin and is not joined to the previous lot. The south end sits at the mapped Białystok Północ junction (unnamed in OpenStreetMap). The drawn centreline is 8.4 km, 32% shorter than the 12.34 km sourced.

Under construction12 km
  1. Feb 19, 2024Tender awarded
  2. Jul 8, 2026Construction start
  3. Nov 19, 2027Expected opening
––
  • UNIBEP S.A.Builder
Contract value zł347.8M
Białystok Północ – Dobrzyniewo

Design-build contract with Unibep signed on 14 May 2024, contract deadline 15 May 2028. The road permit (ZRID) was issued on 20 August 2026 and no works start is recorded, so the lot is shown as awarded. Includes the Białystok Północ and Dobrzyniewo junctions; 14 structures. Part of the northern Białystok bypass. Cut proportionally to the sourced lengths; the drawn centreline is 9% shorter than 9.47 km.

Tendered9 km
  1. May 14, 2024Tender awarded
  2. May 15, 2028Expected opening
––
  • UNIBEP S.A.Builder
Contract value zł320.89M
Krynice – Dobrzyniewo – Białystok Zachód

Design-build contract with Porr together with Unibep, signed on 19 May 2021. The road permit (ZRID) was issued on 28 February 2024; the monthly table gives 12 March 2024 as the works start. The contract deadline was 30 April 2025; GDDKiA Białystok said on 14 May 2026 that the section would open in autumn 2026 with work nearly 80% complete. It joins S8 at the Białystok Zachód junction and will meet S16 near Krynice. Cut at the south end by the end of the mapped interchange; the drawn centreline is 9% shorter than the sourced 10.18 km.

Under construction10 km
  1. May 19, 2021Tender awarded
  2. Mar 12, 2024Construction start
  3. 2026Expected opening
––
  • PORR S.A.Builder
  • UNIBEP S.A.Builder
Contract value zł405.61M
Białystok Zachód – Deniski (southern Białystok bypass)

Length measured from OpenStreetMap geometry. The section is also called Choroszcz – Ploski. GDDKiA lists Białystok Zachód – Księżyno at 16.65 km and Białystok Południe – Ploski at 12.72 km (plwiki gives 7.9 km for Księżyno – Południe), 37.3 km to Ploski, and the stretch from Ploski to the Deniski junction is not given separately. Design-build contracts signed in November and December 2020 were terminated after the environmental decision was annulled by the courts. A new environmental decision was issued on 31 July 2023 and the General Director for Environmental Protection partly changed and partly upheld it in October 2025; a complaint to the administrative court is pending (GDDKiA Białystok, 14 May 2026). Both works contracts appear as terminated in the monthly table. No tender or works start is recorded.

Planned41 km–––––
Deniski – Haćki

Design-build; the Deniski junction joins S19 to the existing DK19, with two rest areas at Haćki. Split out of the earlier Ploski – Haćki section after a court annulled the environmental decision for Choroszcz – Ploski. The permit (ZRID) application was filed in July 2023 and issued on 9 September 2024, against the end of 2021 planned in the contract; the main carriageway opened on 4 August 2026. plwiki names Value Engineering as a third consortium member. There is no junction at Haćki, so the boundary with Haćki – Boćki is placed by the sourced length of 6.5 km.

Opened7 km
  1. Jan 29, 2021Tender awarded
  2. Sep 11, 2024Construction start
  3. Aug 4, 2026Opened
––
  • UNIBEP S.A.Builder
  • Budrex Sp. z o.o.Builder
Contract value zł305.42M
Haćki – Boćki

Two design-build contracts: Haćki – Bielsk Podlaski Zachód (about 9 km, Budimex, includes a link on DK66) and Bielsk Podlaski Zachód – Boćki (12.19 km, Strabag). Both opened to traffic on 31 October 2025. The permits (ZRID) were issued on 23 August 2023 and 4 October 2023. The length is the sum of the two sections (plwiki 9 km and MSBD 12.19 km); the drawn centreline is 6% shorter.

Opened21 km
  1. Sep 6, 2021Tender awarded
  2. Oct 31, 2025Opened
––
  • Budimex S.A.Builder
  • Strabag Sp. z o.o.Builder
Contract value zł635.34M
Boćki – Malewice – Chlebczyn

Two design-build contracts: Boćki – Malewice (15.91 km, Strabag) and Malewice – Chlebczyn (25.07 km, Kolin, with a 658 m bridge over the Bug and the Siemiatycze Północ and Południe junctions). The contract deadlines of 2 May 2025 have passed. On 14 May 2026 GDDKiA Białystok reported Boćki – Malewice at 98% and Malewice – Chlebczyn due in autumn 2026; Boćki – Malewice can only open together with the first half of Malewice – Chlebczyn. The planned total cost of the project is almost 1.5 billion PLN (GDDKiA Białystok). The tender announcement dates differ between pages (23 September and 4 November 2020 on MSBD, 18 September and 30 October on plwiki).

Under construction41 km
  1. Sep 6, 2021Tender awarded
  2. 2026Expected opening
–
  • European UnionCo-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS); the MSBD pages list 787.6 million PLN of co-financing for the project S19 Boćki – Chlebczyn.
  • Strabag Sp. z o.o.Builder
  • Kolin İnşaat Turizm Sanayi ve TicaretBuilder
Contract value zł1B
Chlebczyn – Łosice – Lubelskie border

Section "granica woj. podlaskiego – Łosice – granica woj. lubelskiego" (32 km on the MSBD page, 32.4 km on plwiki), in the preparation stage with implementation planned for 2029–2031. The environmental decision was issued on 4 October 2024. It would include the Sarnaki, Ostromęczyn, Łosice and Mszanna junctions according to plwiki. No tender is recorded. The drawn centreline, from OpenStreetMap proposed ways, is 29.6 km (7% shorter).

Planned32 km–––––
Lubelskie border – Międzyrzec Podlaski (end of bypass)

Design-build contract with Strabag signed on 23 February 2022 (the MSBD page states a cost of 391.5 million PLN). The road permit (ZRID) was issued on 12 December 2024; GDDKiA gives 2027 as the planned opening. No works start date is recorded. Part of the Białystok – Lubartów expressway between the Mazovian/Lubelskie border and the Lubartów Północ junction.

Under construction14 km
  1. Feb 23, 2022Tender awarded
  2. 2027Expected opening
–
  • European UnionCo-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS).
  • Strabag Sp. z o.o.Builder
Contract value zł391.54M
Międzyrzec Podlaski bypass

Built 2005–2008 as a single-carriageway expressway (dual only at the junctions) and signposted as DK19. plwiki gives the opening as 18 April 2008; the MSBD page gives only the year 2008. The 13.7 km section to the north and the sections to the south are being built to dual carriageway. No junction is mapped at the south end, so the boundary with the next lot is placed by the sourced length of 6.6 km.

Opened7 km
  1. Apr 18, 2008Opened
––––
Międzyrzec Podlaski – Radzyń Podlaski – Kock

Two design-build contracts: Międzyrzec Podlaski – Radzyń Podlaski (22.2 km, Stecol) and Radzyń Podlaski – Kock (18.3 km, Polaqua). The road permits (ZRID) were issued on 21 April 2026 and 22 December 2025; plwiki reports works at 5% and 1% in June 2026. GDDKiA gives 2028 as the planned completion. The cut with the Kock bypass is proportional to the sourced lengths; the drawn centreline is 6% shorter than 40.5 km.

Under construction41 km
  1. Jul 26, 2022Tender awarded
  2. 2028Expected opening
–
  • European UnionCo-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS), project S19 Międzyrzec Podlaski – Lubartów Północ.
  • Stecol CorporationBuilder
  • Polaqua Sp. z o.o.Builder
Contract value zł1.2B
Kock and Wola Skromowska bypass

Built 2009–2011 as a single-carriageway expressway and opened to traffic on 19 December 2011 (the MSBD page; plwiki gives 21 December). A second carriageway was added under a contract with Polaqua signed on 1 April 2022 (183.44 million PLN gross per the monthly table); the MSBD page gives 19 May 2026 as the date the road was made available, and plwiki says the bypass regained expressway status on 21 May 2026 in full dual-carriageway form. The lot keeps the 2011 opening date because the road has been in use since then. The north boundary is placed by the sourced length of 7.9 km, ending at the mapped Kock Południe junction; the mapped Kock Północ junction lies 1.6 km inside the drawn line.

Opened8 km
  1. Dec 19, 2011Opened
––––
Kock – Lubartów Północ

Design-build contract with a Rubau Polska (leader) and Poltores consortium signed on 15 September 2022. The permit (ZRID) was applied for on 17 July 2023 and issued on 24 March 2026; plwiki reports works at 1% in June 2026. Planned completion 2028. The cut at Lubartów Północ is proportional to the sourced lengths of this lot and the next; the drawn centreline is 5% longer than 15.8 km.

Under construction16 km
  1. Sep 15, 2022Tender awarded
  2. 2028Expected opening
–
  • European UnionCo-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS), project S19 Międzyrzec Podlaski – Lubartów Północ.
  • Rubau Polska Sp. z o.o.Builder
  • Poltores Sp. z o.o.Builder
Contract value zł390M
Lubartów Północ – Lublin Rudnik

Design-build contract with Duna Polska (formerly Mota-Engil Central Europe), signed on 26 February 2021. The permit (ZRID) was issued on 15 November 2024, against 2022 planned at signing; the monthly table gives 25 November 2024 as the works start and MSBD gives 2027 as the planned end of works. plwiki reports works at 55% in June 2026, with 29 structures and a reserve for a third lane. The road ends at the Lublin Rudnik junction, from where it shares the Lublin northern ring with S12 and S17; that part is not drawn as an S19 lot.

Under construction23 km
  1. Feb 26, 2021Tender awarded
  2. Nov 25, 2024Construction start
  3. 2027Expected opening
––
  • Duna Polska S.A.Builder
Contract value zł835.66M
Lublin Sławinek – Lublin Węglin (western Lublin bypass)

Dual carriageway western bypass of Lublin, built by Budimex. The monthly table gives 423.88 million PLN (gross); the MSBD page gives 3.62 million for design and 411.51 million for works. Opened on 9 December 2016. The stretch Lublin Rudnik – Lublin Sławinek (10.2 km, opened 31 October 2014) is shared with S12 and S17 and is not drawn here, so it is not counted twice.

Opened10 km
  1. Oct 29, 2014Tender awarded
  2. Nov 19, 2014Construction start
  3. Dec 9, 2016Opened
––
  • Budimex S.A.Builder
Contract value zł423.88M
Lublin Węglin – Niedrzwica Duża

Design-build by Aldesa Construcciones Polska with Aldesa Construcciones S.A. The permit (ZRID) was issued on 12 August 2019. Opened on 16 December 2021. The drawn centreline is 13% longer than the 12 km stated.

Opened12 km
  1. Feb 28, 2018Tender awarded
  2. Aug 12, 2019Construction start
  3. Dec 16, 2021Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Aldesa Construcciones Polska Sp. z o.o.Builder
Contract value zł312.3M
Niedrzwica Duża – Kraśnik Północ

Design-build by Mota-Engil Central Europe (now Duna Polska), design by IVIA. Opened on 21 May 2022. The contract deadline was 28 March 2022 (plwiki). The monthly table lists the contractor as Duna Polska SA.

Opened20 km
  1. Feb 28, 2018Tender awarded
  2. Nov 29, 2019Construction start
  3. May 21, 2022Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Mota-Engil Central Europe S.A.Builder
Contract value zł498.03M
Kraśnik bypass

Design-build by Aldesa Construcciones Polska with Aldesa Construcciones S.A. Opened on 16 December 2021. The section ends at the Słodków junction, now Kraśnik Południe; the boundary is placed at the mapped Kraśnik Południe junction, 4.9 km from Kraśnik Północ along the drawn line. The sourced length is 9.9 km (about 10 km in GDDKiA documents), so the drawn line is 51% shorter and the next lot 16% longer than their sourced lengths; the sums agree.

Opened10 km
  1. Feb 28, 2018Tender awarded
  2. Oct 7, 2019Construction start
  3. Dec 16, 2021Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Aldesa Construcciones Polska Sp. z o.o.Builder
Contract value zł319.46M
Kraśnik Południe – Janów Lubelski Południe

Two design-build contracts signed on 30 October 2017: Kraśnik Południe – Janów Lubelski Północ (18.15 km, Strabag with Strabag Infrastruktura Południe) and the Janów Lubelski bypass (6.43 km, Mota-Engil Central Europe). Both opened on 16 December 2021. The Kraśnik Południe junction, at the start of this lot, crosses DK74 (MSBD). The boundary follows the mapped junction, so the drawn line is 16% longer than the sourced 24.58 km.

Opened25 km
  1. Oct 30, 2017Tender awarded
  2. Jun 26, 2019Construction start
  3. Dec 16, 2021Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Strabag Sp. z o.o.Builder
  • Strabag Infrastruktura Południe Sp. z o.o.Builder
  • Mota-Engil Central Europe S.A.Builder
Contract value zł538.48M
Janów Lubelski Południe – Lasy Janowskie

Design-build by Strabag with Strabag Infrastruktura Południe. Opened on 14 June 2021 (the MSBD page; plwiki gives 15 June), the first of the Lublin – Rzeszów sections in this stretch to open.

Opened8 km
  1. Oct 30, 2017Tender awarded
  2. Aug 5, 2019Construction start
  3. Jun 14, 2021Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Strabag Sp. z o.o.Builder
  • Strabag Infrastruktura Południe Sp. z o.o.Builder
Contract value zł183.55M
Lasy Janowskie – Zdziary

Design-build by Strabag with Strabag Infrastruktura Południe. Opened on 11 October 2021.

Opened9 km
  1. Jun 18, 2018Tender awarded
  2. Feb 28, 2020Construction start
  3. Oct 11, 2021Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Strabag Sp. z o.o.Builder
  • Strabag Infrastruktura Południe Sp. z o.o.Builder
Contract value zł236.33M
Zdziary – Rudnik nad Sanem

Design-build by Mosty Łódź, including the bridge over the San. Opened on 29 April 2022 (the contract deadline was 15 April 2022). plwiki gives about 9 km and the MSBD page 8.22 km. The end is cut at the mapped Rudnik nad Sanem junction, so the drawn line is 9.9 km, 20% longer than the MSBD figure.

Opened8 km
  1. Jun 18, 2018Tender awarded
  2. Oct 10, 2019Construction start
  3. Apr 29, 2022Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Mosty Łódź S.A.Builder
Contract value zł286.89M
Rudnik nad Sanem – Nisko – Łowisko

Three design-build contracts, all opened to traffic on 6 December 2021: Rudnik nad Sanem – Nisko Południe (6.45 km), Nisko – Jeżowe (11.15 km) and Jeżowe – Łowisko (10.33 km). The MSBD pages list contract values of 196.34, 272.69 and 335.93 million PLN; the monthly table values are used here because it states they are gross. The lot is drawn from the mapped Rudnik nad Sanem junction to the mapped Łowisko junction (27.9 km, equal to the sourced sum); the three sections are not drawn separately.

Opened28 km
  1. Jun 18, 2018Tender awarded
  2. Jan 7, 2020Construction start
  3. Dec 6, 2021Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Strabag Sp. z o.o.Builder
  • Strabag Infrastruktura Południe Sp. z o.o.Builder
  • Mostostal Warszawa S.A.Builder
  • Acciona Construcción S.A.Builder
  • Budimex S.A.Builder
Contract value zł802.32M
Łowisko – Sokołów Małopolski Północ

Design-build by Budimex. Opened on 23 December 2021. The section ends at the Sokołów Małopolski Północ junction, where the dual carriageway road ends and the single-carriageway section begins. The start is cut at the mapped Łowisko junction, so the drawn line is 13% shorter than the sourced 8.19 km.

Opened8 km
  1. Dec 21, 2018Tender awarded
  2. Jul 13, 2020Construction start
  3. Dec 23, 2021Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Budimex S.A.Builder
Contract value zł286.4M
Sokołów Małopolski Północ – Stobierna

Built by a consortium led by Aldesa Construcciones Polska, in a design-build system, as a single-carriageway expressway. The permit (ZRID) was issued on 10 July 2015 and the road opened on 1 September 2017. A second carriageway is being added on Sokołów Małopolski Północ – Jasionka (13.83 km, Strabag, contract signed 21 November 2022, 69% in May 2026 per plwiki) and is not a separate lot. No junction is mapped at Stobierna, so the boundary with Stobierna – Rzeszów Wschód is placed by the sourced length of 12.5 km.

Opened13 km
  1. Jun 5, 2014Tender awarded
  2. Jul 23, 2015Construction start
  3. Sep 1, 2017Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Aldesa Construcciones Polska Sp. z o.o.Builder
Contract value zł289.98M
Stobierna – Rzeszów Wschód

Built by a Polish–Portuguese consortium led by MSF Engenharia. plwiki gives 3.1 km of dual carriageway (Jasionka – Rzeszów Wschód) and 3.8 km of single carriageway (Stobierna – Jasionka); the MSBD page gives 6.89 km. Opened on 10 September 2012. The second carriageway between Stobierna and Jasionka is part of the Sokołów Małopolski Północ – Jasionka expansion.

Opened7 km
  1. Feb 8, 2010Tender awarded
  2. Sep 10, 2012Opened
––
  • MSF Engenharia S.A.Builder
Contract value zł213.58M
Rzeszów Zachód – Świlcza

The first contract, signed on 22 April 2010 with a consortium of Radko, Autostrada Wschodnia and Punj Lloyd for this section and A4 Rzeszów Zachód – Rzeszów Centralny (441.7 million PLN in total, about 207.5 million for the S19 part), was terminated on 25 May 2012. A new contract with Eurovia Polska was signed on 18 January 2013 and the section opened on 13 December 2013. No value is recorded because the 2013 contract value is not in the sources. Between Rzeszów Wschód and Rzeszów Zachód, S19 runs on A4, which is not drawn here. The drawn centreline is 8% longer than the sourced 4.375 km.

Opened4 km
  1. Apr 22, 2010Tender awarded
  2. Dec 13, 2013Opened
––
  • Eurovia Polska S.A.Builder
–
Świlcza – Rzeszów Południe

Design-build by Eurovia Polska with Warbud, signed on 9 April 2014 as the first contract of the 2014–2020 EU financial perspective. The permit (ZRID) was issued on 19 May 2015 and the section opened on 7 December 2017. Includes the Świlcza junction with DK94 and the Rzeszów Południe (Kielanówka) junction.

Opened6 km
  1. Apr 9, 2014Tender awarded
  2. Jun 2, 2015Construction start
  3. Dec 7, 2017Opened
–
  • European UnionCo-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
  • Eurovia Polska S.A.Builder
  • Warbud S.A.Builder
Contract value zł342.57M
Rzeszów Południe – Babica (Babica tunnel)

Design-build with Mostostal Warszawa and Acciona, signed on 10 July 2020; works began on 1 March 2022 (monthly table) after the permit of 24 February 2022. The lot includes the Babica tunnel, running from about km 18+475 to 20+730 of the project chainage, about 2.26 km (MSBD description; the plwiki route table gives 2 km), bored with the machine Karpatka. It also has the Lutoryż rest areas and several viaducts. The contract deadline was moved to January 2028; GDDKiA gives 58% progress in May 2026 and cites methane, a redesigned tunnel and slower boring as the reasons for the delay. The length is the sourced 10.3 km.

Under construction10 km
  1. Jul 10, 2020Tender awarded
  2. Mar 1, 2022Construction start
  3. Jan 2028Expected opening
–
  • European UnionCo-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS); the MSBD page lists co-financing of 1.5 billion PLN.
  • Mostostal Warszawa S.A.Builder
  • Acciona Construcción S.A.Builder
Contract value zł2.2B
Babica – Jawornik

Design-build signed on 14 February 2022, with the Strzyżów – Żarnowa junction, a rest area at Jawornik and a temporary link to DK19. The permit (ZRID) was issued on 25 August 2023 (plwiki gives 29 August) and the monthly table gives 4 September 2023 as the works start. GDDKiA gives 2027 as the end of works and 80% progress in May 2026.

Under construction12 km
  1. Feb 14, 2022Tender awarded
  2. Sep 4, 2023Construction start
  3. 2027Expected opening
––
  • Przedsiębiorstwo Usług Technicznych Intercor Sp. z o.o.Builder
Contract value zł1.3B
Jawornik – Lutcza – Domaradz

Two design-build contracts: Jawornik – Lutcza (5.25 km, Gülermak and Budimex, with a further Gülermak partner named in the monthly table) and Lutcza – Domaradz (6.38 km, Kolin; a first tender was annulled because offers exceeded the estimate). Permit applications were filed on 13 January 2026 and 11 December 2025 and no decision is recorded, so the lot is shown as awarded. GDDKiA gives completion dates of 2031 and June 2030. The Domaradz junction is included. The next stretch, Domaradz – Krosno (12.5 km), is not drawn: its contract was terminated on 14 May 2026 and a new tender was announced on 1 September 2026 (MSBD).

Tendered12 km
  1. May 28, 2024Tender awarded
  2. 2031Expected opening
––
  • Kolin İnşaat Turizm Sanayi ve TicaretBuilder
  • GülermakBuilder
  • Budimex S.A.Builder
Contract value zł3.3B
Krosno – Miejsce Piastowe – Dukla

Two design-build contracts, both opened to traffic on 23 December 2025: Krosno – Miejsce Piastowe (10.3 km, Aldesa Construcciones Polska with Aldesa Construcciones, with two junctions) and Miejsce Piastowe – Dukla (about 10.1 km, Strabag, with the Dukla junction and the Równe rest area). The permits (ZRID) were issued on 16 February 2023 and 28 September 2023. The drawn centreline is 7% shorter than the 20.4 km sourced. The stretch before it, Domaradz – Krosno (12.5 km), is not drawn: it is being re-tendered.

Opened20 km
  1. Jul 12, 2021Tender awarded
  2. Dec 23, 2025Opened
––
  • Aldesa Construcciones Polska Sp. z o.o.Builder
  • Strabag Sp. z o.o.Builder
Contract value zł843.98M
Dukla – Barwinek

Design-build with Polaqua signed on 10 October 2022, with the Barwinek junction at the Slovak border. The road has no hard shoulder, only emergency bays. The permit (ZRID) was applied for on 1 December 2023 and issued on 2 July 2025, and the monthly table gives 23 July 2025 as the works start. Contract deadline 4 May 2027; plwiki cites 13% progress in May 2026 and says the date may change because the permit was late and structures need redesign.

Under construction18 km
  1. Oct 10, 2022Tender awarded
  2. Jul 23, 2025Construction start
  3. May 4, 2027Expected opening
–
  • European UnionCo-financed by the Connecting Europe Facility (CEF): the MSBD page lists co-financing of 326,637,490 EUR.
  • Polaqua Sp. z o.o.Builder
Contract value zł1.5B

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union287 km
    17 sections
    • Co-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS); the MSBD pages list 787.6 million PLN of co-financing for the project S19 Boćki – Chlebczyn.
    • Co-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS).
    • Co-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS), project S19 Międzyrzec Podlaski – Lubartów Północ.
    • Co-financed under the Infrastructure and Environment Operational Programme 2014–2020 (POIiŚ), per the MSBD pages.
    • Co-financed under the EU programme Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS); the MSBD page lists co-financing of 1.5 billion PLN.
    • Co-financed by the Connecting Europe Facility (CEF): the MSBD page lists co-financing of 326,637,490 EUR.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia (pl): Droga ekspresowa S19 (Polska), section histories and route tableread Oct 9, 2026
  2. GDDKiA: Bieżąca realizacja RPBDK do 2030 r., monthly contract table (September 2026 edition, PDF)read Oct 9, 2026
  3. GDDKiA Oddział Białystok: Oddanie do ruchu kolejnych odcinków S19 coraz bliżej (14.05.2026)read Oct 9, 2026
  4. GDDKiA Mapa Stanu Budowy Dróg: S19 Kuźnica – Sokółka Północread Oct 9, 2026
  5. GDDKiA Mapa Stanu Budowy Dróg: S19 Sokółka Północ – Czarna Białostockaread Oct 9, 2026
  6. GDDKiA Mapa Stanu Budowy Dróg: S19 Czarna Białostocka – Białystok Północread Oct 9, 2026
  7. GDDKiA Mapa Stanu Budowy Dróg: S19 Białystok Północ – Dobrzynieworead Oct 9, 2026
  8. GDDKiA Mapa Stanu Budowy Dróg: S19 Krynice – Dobrzyniewo – Białystok Zachódread Oct 9, 2026
  9. GDDKiA Mapa Stanu Budowy Dróg: S19 Białystok Zachód – Księżynoread Oct 9, 2026
  10. GDDKiA Mapa Stanu Budowy Dróg: S19 Białystok Południe – Ploskiread Oct 9, 2026
  11. GDDKiA Mapa Stanu Budowy Dróg: S19 Deniski – Haćkiread Oct 9, 2026
  12. GDDKiA Mapa Stanu Budowy Dróg: S19 Bielsk Podlaski Zachód – Boćkiread Oct 9, 2026
  13. GDDKiA Mapa Stanu Budowy Dróg: S19 Boćki – Malewiceread Oct 9, 2026
  14. GDDKiA Mapa Stanu Budowy Dróg: S19 Malewice – Chlebczynread Oct 9, 2026
  15. GDDKiA Mapa Stanu Budowy Dróg: S19 granica woj. podlaskiego – Łosice – granica woj. lubelskiegoread Oct 9, 2026
  16. GDDKiA Mapa Stanu Budowy Dróg: S19 gr. woj. lubelskiego i mazowieckiego – Międzyrzec Podlaski (koniec obwodnicy)read Oct 9, 2026
  17. GDDKiA Mapa Stanu Budowy Dróg: S19 obwodnica Międzyrzeca Podlaskiegoread Oct 9, 2026
  18. GDDKiA Mapa Stanu Budowy Dróg: S19 Międzyrzec Podlaski – Radzyń Podlaskiread Oct 9, 2026
  19. GDDKiA Mapa Stanu Budowy Dróg: S19 Radzyń Podlaski – Kockread Oct 9, 2026
  20. GDDKiA Mapa Stanu Budowy Dróg: S19 obwodnica Kocka i Woli Skromowskiej, etap Iread Oct 9, 2026
  21. GDDKiA Mapa Stanu Budowy Dróg: S19 obwodnica Kocka i Woli Skromowskiej, dobudowa II jezdniread Oct 9, 2026
  22. GDDKiA Mapa Stanu Budowy Dróg: S19 koniec obwodnicy Kocka i Woli Skromowskiej – Lubartów Północread Oct 9, 2026
  23. GDDKiA Mapa Stanu Budowy Dróg: S19 Lubartów Północ – Lublin Rudnikread Oct 9, 2026
  24. GDDKiA Mapa Stanu Budowy Dróg: S19 obwodnica Lublina (Lublin Sławinek – Lublin Węglin)read Oct 9, 2026
  25. GDDKiA Mapa Stanu Budowy Dróg: S19 Lublin Węglin – Niedrzwica Dużaread Oct 9, 2026
  26. GDDKiA Mapa Stanu Budowy Dróg: S19 Niedrzwica Duża – Kraśnik Północread Oct 9, 2026
  27. GDDKiA Mapa Stanu Budowy Dróg: S19 obwodnica Kraśnikaread Oct 9, 2026
  28. GDDKiA Mapa Stanu Budowy Dróg: S19 Kraśnik Południe – Janów Lubelski Północread Oct 9, 2026
  29. GDDKiA Mapa Stanu Budowy Dróg: S19 Janów Lubelski Północ – Janów Lubelski Południeread Oct 9, 2026
  30. GDDKiA Mapa Stanu Budowy Dróg: S19 Janów Lubelski Południe – Lasy Janowskieread Oct 9, 2026
  31. GDDKiA Mapa Stanu Budowy Dróg: S19 Lasy Janowskie – Zdziaryread Oct 9, 2026
  32. GDDKiA Mapa Stanu Budowy Dróg: S19 Zdziary – Rudnik nad Sanemread Oct 9, 2026
  33. GDDKiA Mapa Stanu Budowy Dróg: S19 Rudnik nad Sanem – Nisko Południeread Oct 9, 2026
  34. GDDKiA Mapa Stanu Budowy Dróg: S19 Nisko – Jeżoweread Oct 9, 2026
  35. GDDKiA Mapa Stanu Budowy Dróg: S19 Jeżowe – Łowiskoread Oct 9, 2026
  36. GDDKiA Mapa Stanu Budowy Dróg: S19 Łowisko – Sokołów Małopolski Północread Oct 9, 2026
  37. GDDKiA Mapa Stanu Budowy Dróg: S19 Sokołów Małopolski Północ – Stobiernaread Oct 9, 2026
  38. GDDKiA Mapa Stanu Budowy Dróg: S19 Stobierna – Rzeszów Wschódread Oct 9, 2026
  39. GDDKiA Mapa Stanu Budowy Dróg: S19 Sokołów Młp. Północ – Jasionka, etap II (dobudowa drugiej jezdni)read Oct 9, 2026
  40. GDDKiA Mapa Stanu Budowy Dróg: S19 Rzeszów Zachód – Świlczaread Oct 9, 2026
  41. GDDKiA Mapa Stanu Budowy Dróg: S19 Świlcza – Rzeszów Południeread Oct 9, 2026
  42. GDDKiA Mapa Stanu Budowy Dróg: S19 Rzeszów Południe – Babicaread Oct 9, 2026
  43. GDDKiA Mapa Stanu Budowy Dróg: S19 Babica – Jawornikread Oct 9, 2026
  44. GDDKiA Mapa Stanu Budowy Dróg: S19 Jawornik – Lutczaread Oct 9, 2026
  45. GDDKiA Mapa Stanu Budowy Dróg: S19 Lutcza – Domaradzread Oct 9, 2026
  46. GDDKiA Mapa Stanu Budowy Dróg: S19 Domaradz – Krosnoread Oct 9, 2026
  47. GDDKiA Mapa Stanu Budowy Dróg: S19 Krosno – Miejsce Piastoweread Oct 9, 2026
  48. GDDKiA Mapa Stanu Budowy Dróg: S19 Miejsce Piastowe – Duklaread Oct 9, 2026
  49. GDDKiA Mapa Stanu Budowy Dróg: S19 Dukla – Barwinekread Oct 9, 2026
  50. OpenStreetMap: relation 2315275, Droga ekspresowa S19 (network PL:expressway)read Oct 9, 2026
  51. OpenStreetMap contributors: route geometry (ODbL)read Oct 9, 2026

Figures last checked against their sources in Oct 9, 2026.