Cluj-Napoca – Oradea – Episcopia Bihor railway rehabilitation

EU-funded electrification and rehabilitation of the main railway between Cluj-Napoca, Oradea and the Hungarian border at Episcopia Bihor (166.2 km, TEN-T Rhine–Danube Corridor), let as four design-and-build lots. In March 2026 Prime Minister Bolojan set 2028 as the target for finishing all four lots.

Total length
166 km
Open today
0 km
Under construction
166 km
Sections
4
Cost on record
€1.9B
4 of 4 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Cluj-Napoca – Oradea – Episcopia Bihor railway rehabilitation: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Lot 1: Cluj-Napoca – Aghireș

Contract signed 30 December 2022, works started 30 January 2023. CFR's August 2026 report puts physical progress at 75% and the end of works in H2 2027.

Under construction
45 of 36 contracted months
9 months past the contract date
30 km
  1. Dec 30, 2022Tender awarded
  2. Jan 30, 2023Construction start
  3. 2027Expected opening
  • Estimated lei 1.5BEstimated value before award, excluding VAT, as published by CFR SA on 17 May 2022.
  • European UnionPNRR, Component 4 (Sustainable transport): stage I of the works
  • European UnionProgramul Transport 2021-2027: stage II of the works
  • National budgetCo-financing
  • Alstom Transport – Arcada Company (Asocierea Railworks)Builder
6 mo design · 36 mo execution · 42 mo total · Contract value lei 1.6B
Lot 2: Aghireș – Poieni

Contract signed 21 December 2022, works started 25 January 2023. CFR's August 2026 report puts physical progress at 76% and the end of works in H2 2027.

Under construction
45 of 36 contracted months
9 months past the contract date
37 km
  1. Dec 21, 2022Tender awarded
  2. Jan 25, 2023Construction start
  3. 2027Expected opening
  • Estimated lei 1.5BEstimated value before award, excluding VAT, as published by CFR SA on 17 May 2022.
  • European UnionPNRR, Component 4 (Sustainable transport): stage I of the works
  • European UnionProgramul Transport 2021-2027: stage II of the works
  • National budgetCo-financing
  • Alstom Transport – Arcada Company (Asocierea Railworks)Builder
6 mo design · 36 mo execution · 42 mo total · Contract value lei 1.5B
Lot 3: Poieni – Aleșd

Contract signed 10 November 2022, works started 16 January 2023. Length 52.74 km per CFR's August 2026 report (53 km at signing). The report puts physical progress at 38.96% and the end of works in H1 2029, the latest of the four lots. In March 2026 Prime Minister Bolojan asked the builders to speed up and set 2028 as the target for all four lots.

Under construction
45 of 36 contracted months
9 months past the contract date
53 km
  1. Nov 10, 2022Tender awarded
  2. Jan 16, 2023Construction start
  3. 2029Expected opening
  • Estimated lei 2.2BEstimated value before award, excluding VAT, as published by CFR SA on 17 May 2022.
  • European UnionPNRR, Component 4 (Sustainable transport): stage I of the works
  • European UnionProgramul Transport 2021-2027: stage II of the works
  • National budgetCo-financing
  • FCC Construccion – Gülermak – CCNBuilder
6 mo design · 36 mo execution · 42 mo total · Contract value lei 2.1B
Lot 4: Aleșd – Hungarian border (Episcopia Bihor)

Runs through Oradea to Episcopia Bihor and the Hungarian border. Contract signed 7 December 2022 (2,416.85 M lei excluding VAT, 42 months), works started 23 January 2023. About 14 km of new track between Tileagd and the Oșorhei halt reopened to trains on 31 March 2026 at 50 km/h, rising to 120 km/h and to 160 km/h once the whole project is finished; the catenary masts are in place but not yet electrified. CFR's August 2026 report puts physical progress at 59.29% and the end of works in H2 2028.

Under construction
45 of 36 contracted months
9 months past the contract date
47 km
  1. Dec 7, 2022Tender awarded
  2. Jan 23, 2023Construction start
  3. 2028Expected opening
  • Estimated lei 2.4BEstimated value before award, excluding VAT, as published by CFR SA on 17 May 2022.
  • European UnionPNRR, Component 4 (Sustainable transport): stage I of the works
  • European UnionProgramul Transport 2021-2027: stage II of the works
  • National budgetCo-financing
  • Webuild – Impresa Pizzarotti – SalcefBuilder
6 mo design · 36 mo execution · 42 mo total · Contract value lei 2.4B

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union333 km
    8 sections
    • PNRR, Component 4 (Sustainable transport): stage I of the works
    • Programul Transport 2021-2027: stage II of the works
  • National budget166 km
    4 sections
    • Co-financing

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • TEN-T Rhine–Danube CorridorTEN-T

Sources

  1. CFR SA: Stadiul proiectelor de reabilitare/modernizare infrastructură feroviară, August 2026read Sep 25, 2026
  2. CFR SA: Electrificarea și reabilitarea liniei de cale ferată Cluj-Napoca – Oradea – Episcopia Bihorread Sep 25, 2026
  3. Economica.net: Calea ferată Cluj – Oradea: toate contractele pentru electrificarea liniei au fost semnate (2022-12-30)read Sep 25, 2026
  4. HotNews.ro: CFR SA a semnat contractul de 2,1 miliarde lei pentru 53 de km de cale ferată din Transilvania (2022-11-10)read Sep 25, 2026
  5. Economica.net: Calea ferată Cluj – Oradea: CFR a semnat contractul pentru lotul 2 cu asocierea Arcada – Alstom (2022-12-21)read Oct 2, 2026
  6. Economica.net: Cluj – Oradea – Episcopia Bihor, semnat contractul pentru lotul de la graniță cu Webuild (2022-12-07)read Sep 25, 2026
  7. Economica.net: Bolojan le cere constructorilor lotului Poieni – Aleșd să accelereze ritmul lucrărilor (2026-03-13)read Sep 25, 2026
  8. CFR SA: 17 mai 2022 – CFR SA a primit 19 oferte pentru Electrificarea și reabilitarea liniei CF Cluj Napoca-Oradea-Episcopia Bihor-Frontierăread Sep 28, 2026
  9. CFR SA: Redeschiderea circulației feroviare pe tronsonul Tileagd – Oșorhei (2026-03-31)read Oct 2, 2026
  10. OpenStreetMap contributors (geometry of CFR line 300, ODbL)read Oct 2, 2026