Cluj-Napoca Metro Line M1 (Florești – Cluj-Napoca)

Driverless light metro under construction from Florești through Mănăștur and the centre of Cluj-Napoca to Piața Mărăști, where it splits into a Muncii branch and a Sopor branch with the depot: 21.03 km and 19 underground stations. One design-and-build contract with the Gülermak – Alstom – Arcada association was signed on 25 May 2023, with a term of 96 months. Construction was launched at a ceremony on 5 June 2024. The first stage (Sfânta Maria – Europa Unită, 9.16 km, 9 stations and the depot) was financed from the PNRR with an end date of August 2026; the mayor's target for the whole line is 2031.

Total length
21 km
Open today
0 km
Under construction
21 km
Sections
1
Loading map data…

Sections

Sections of Cluj-Napoca Metro Line M1 (Florești – Cluj-Napoca): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Line M1: Florești – Piața Mărăști – Sopor / Muncii

Order to start the contract issued for 1 September 2023, opening the design phase. Construction works were launched at a ceremony on 5 June 2024. In May 2026 diaphragm walls were under way at Teilor station, and a 2026 report cited by local media put physical progress at about 1.24%. The first stage (Sfânta Maria – Europa Unită, 9.16 km) was due by the end of August 2026 under the PNRR; the second stage (Țara Moților – Sfânta Maria and Piața Mărăști – Muncii, 11.87 km) completes the line, with 2031 as the mayor's date for the whole metro. One contract covers the whole line, so it is recorded as one lot.

Under construction
28 of 84 contracted months
21 km
  1. May 25, 2023Tender awarded
  2. Jun 5, 2024Construction start
  3. 2031Expected opening
  • Estimated lei 9.1BExcluding VAT. Estimated total value of the design-and-build works as stated by the Cluj-Napoca city hall (reported on the day the contract was signed): works 8,666.34 million RON and design, studies and technical assistance 398.11 million RON. The source does not call it the contract price and does not state the price year.
  • European UnionNational Recovery and Resilience Plan: pays for the first stage (Sfânta Maria – Europa Unită, 9 stations and the depot)
  • National budgetFinancing contract of 13.69 billion RON signed by the Ministry of Transport in December 2022, drawing on PNRR, other EU funds, the state budget and the budgets of Cluj-Napoca and Florești
  • Gülermak Ağır Sanayi İnşaat ve Taahhüt A.Ş. – Gülermak Spółka z o.o. – Alstom Transport S.A. – Arcada Company S.A.Builder
12 mo design · 84 mo execution · 96 mo total

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union21 km
    1 section
    • National Recovery and Resilience Plan: pays for the first stage (Sfânta Maria – Europa Unită, 9 stations and the depot)
  • National budget21 km
    1 section
    • Financing contract of 13.69 billion RON signed by the Ministry of Transport in December 2022, drawing on PNRR, other EU funds, the state budget and the budgets of Cluj-Napoca and Florești

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. HotNews: Prima linie de metrou din Cluj-Napoca: cine sunt constructorii, când va fi gata (25 mai 2023)read Oct 5, 2026
  2. Curs de Guvernare: Transporturile au semnat contractul de finanțare al metroului Cluj-Napoca: 13,69 mld. lei (December 2022)read Oct 5, 2026
  3. Infrapress: Undă verde pentru metroul din Cluj, Guvernul a aprobat indicatorii tehnico-economici (30 decembrie 2021)read Oct 5, 2026
  4. Railway PRO: Cluj-Napoca metro construction kicks off (6 June 2024)read Oct 5, 2026
  5. Railway Gazette International: Cluj-Napoca breaks ground for first metro line (18 June 2024)read Oct 5, 2026
  6. Monitorul de Cluj: Încep lucrările la metroul din Cluj, la 1 septembrie s-a dat ordinul de începere (1 septembrie 2023)read Oct 5, 2026
  7. Ziua de Cluj: 1 septembrie 2023, ZI ISTORICĂ: Încep lucrările la METROUL Clujuluiread Oct 5, 2026
  8. Actual de Cluj: Au început lucrările la viitoarea stație Teilor din Florești, se execută pereții mulați (19 mai 2026)read Oct 5, 2026
  9. Wikipedia: Cluj-Napoca Metroread Oct 5, 2026
  10. Wikipedia: Metroul din Clujread Oct 5, 2026
  11. OpenStreetMap contributors: Cluj-Napoca metro line M1 geometry (ODbL)read Oct 5, 2026