A10 motorway (Sebeș–Turda)

70 km motorway linking the A1 at Sebeș with the A3 near Turda, also serving Alba Iulia and Aiud. Built in four lots with works starting in 2014–2015 and opened in stages between July 2018 and November 2021. Total cost 420 million euro, financed 85% from European Union funds and 15% from the state budget.

Total length
70 km
Open today
70 km
Sections
4
Cost on record
€630.32M
4 of 4 sections carry a comparable figure

Restated into EUR at 2025 prices.

Cost for the project as a whole
lei 2.1Bwhole programmeIncluding VAT. Whole A10 project under POIM 2014–2020 (all four lots plus supervision, land and other costs), per financing contract addendum no. 5 of 24 June 2021 (CNAIR). A budget, not an outturn. An earlier POS-T budget (2014) was 621.5 million euro, per AM POST via HotNews.
Loading map data…

Sections

Sections of A10 motorway (Sebeș–Turda): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Lot 1: Sebeș (A1) – Alba Iulia North

Part of the A10 Sebeș–Turda motorway: €420M total, 85% EU funds / 15% state budget

Opened17 km
  1. Nov 14, 2014Tender awarded
  2. Dec 2, 2014Construction start
  3. Dec 3, 2020Opened
–
  • European Union85% of the motorway's cost
  • National budget15% of the motorway's cost
  • Impresa PizzarottiBuilder
  • Pomponio ConstrucțiiBuilder
4 mo design · 18 mo execution · 22 mo total · 48 mo guarantee · Contract value lei 541.7M
Lot 2: Alba Iulia North – Aiud

Part of the A10 Sebeș–Turda motorway: €420M total, 85% EU funds / 15% state budget

Opened24 km
  1. Nov 14, 2014Tender awarded
  2. 2015Construction start
  3. Nov 30, 2021Opened
–
  • European Union85% of the motorway's cost
  • National budget15% of the motorway's cost
  • AktorBuilder
  • Euroconstruct Trading '98Builder
4 mo design · 18 mo execution · 48 mo guarantee · Contract value lei 549.332M
Lot 3: Aiud – Decea

Part of the A10 Sebeș–Turda motorway: €420M total, 85% EU funds / 15% state budget

Opened13 km
  1. Dec 2013Tender awarded
  2. May 20, 2014Construction start
  3. Jul 30, 2018Opened
  • Estimated lei 420.5M(2013)
  • European Union85% of the motorway's cost
  • National budget15% of the motorway's cost
  • Tirrena ScaviBuilder
  • Società Italiana per Condotte d'AcquaBuilder
18 mo execution · 22 mo total · Contract value lei 420.5M
Lot 4: Decea – Turda (A3)

Part of the A10 Sebeș–Turda motorway: €420M total, 85% EU funds / 15% state budget

Opened16 km
  1. Dec 2013Tender awarded
  2. May 20, 2014Construction start
  3. Jul 30, 2018Opened
  • Estimated lei 470M(2013)
  • European Union85% of the motorway's cost
  • National budget15% of the motorway's cost
  • Porr ConstructBuilder
  • Porr BauBuilder
18 mo execution · 22 mo total · Contract value lei 470M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union70 km
    4 sections
    • 85% of the motorway's cost
  • National budget70 km
    4 sections
    • 15% of the motorway's cost

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia: A10 motorway (Romania)
  2. OpenStreetMap contributors (geometry, ODbL)read Aug 14, 2026
  3. zcj.ro
  4. hotnews.ro
  5. Wikipedia (ro): Autostrada A10 (România)
  6. CNAIR: Autostrada Sebeș–Turda (POIM financing contract no. 144, MySMIS 118317)read Sep 25, 2026
  7. CNAIR: Sebeș–Turda Lot 1read Sep 25, 2026
  8. CNAIR: Sebeș–Turda Lot 2read Sep 25, 2026
  9. CNAIR: Situație centralizată contracte 2018 (la 30.11.2018)read Sep 25, 2026