Nurol
Romania
- Sections
- 4
- Length
- 167 km
- Median slip
- +10 mo
- Median overrun
- –
Slip measured on 4 of 4 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A11 Arad–Oradea Motorway / DEx16 lot 3: Chișineu-Criș – Arad | Romania | Tendered | 47 km | – | +12 mo |
| A3 Transylvania Motorway (Brașov–Cluj–Borș) / Suplacu de Barcău – Nușfalău | Romania | Opened | 14 km | Sep 2023 | +7 mo |
| A7 Motorway (Moldavia Motorway) / Stâlpu – Buzău (Ploiești–Buzău lot 3) | Romania | Opened | 14 km | Nov 2025 | 0 mo |
| A8 Târgu Mureș–Iași–Ungheni Motorway (Unirii) / Târgu Mureș – Ditrău (sections 1A–1D) | Romania | Under construction | 92 km | – | +32 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.