A2 Egnatia Odos (Igoumenitsa – Kipoi)

Greece's longest motorway, 670 km from the port of Igoumenitsa to the Turkish border at Kipoi by way of Ioannina, Kozani, Veria, Thessaloniki, Kavala, Xanthi, Komotini and Alexandroupoli. Construction officially began in 1994, and the state company Egnatia Odos A.E. took over the project in February 1997; the main axis was inaugurated on 30 May 2009 and the last structure, the Peristeri bridge near Metsovo, carried traffic from 10 May 2014. It has two lanes and a hard shoulder per direction, three between Kleidi and Derveni. Lots follow the section-by-section opening table in Greek Wikipedia; three of its lengths (Derveni – Nymfopetra, Megali Volvi – Rentina and Strymonas – Agios Andreas) are corrected from the contemporary reports it cites. The lots sum to about 642 km. The 25 km Kleidi – Kalochori stretch is shared with the A1 motorway and is not recorded as a lot here. The operator gives completion costs per region, excluding VAT and without a price year: Epirus (Igoumenitsa – Panagia, 123 km) about EUR 2.2 billion, Western Macedonia (Panagia – Polymylos, 110 km) EUR 933 million, Central Macedonia (Polymylos – Strymonas, 191 km) EUR 1,298 million and Eastern Macedonia and Thrace (Strymonas – Kipoi, 246 km) EUR 1,042 million. Only the Kastania bypass has a published per-section cost.

Total length
642 km
Open today
642 km
Sections
36
Loading map data…

Sections

Sections of A2 Egnatia Odos (Igoumenitsa – Kipoi): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Igoumenitsa Port – Neochori

The Vasilikos tunnel on this section was completed in 1996; the section opened in 2004.

Opened23 km
  1. Aug 2004Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Neochori – Eleftherochori

Completed the Igoumenitsa – Ioannina stretch.

Opened9 km
  1. Nov 13, 2008Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Eleftherochori – Tyria

First section of the motorway to open in Thesprotia.

Opened18 km
  1. 2002Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Tyria – Dodoni

In April 2009 tunnel S2 at Tyria was still outstanding, expected by the end of that year (Makedonia, 8 April 2009).

Opened10 km
  1. Nov 2006Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Dodoni – Pedini

Includes the twin-tube Dodoni tunnel, 3.3 km per bore.

Opened4 km
  1. 2005Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Pedini – IoanninaOpened4 km
  1. 2003Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Ioannina – Arachthos Bridge

Runs from the Ioannina interchange to the western end of the Arachthos bridge. Includes the Driskos tunnel, 4.5 km per bore and the longest on the motorway, whose construction began in 2001.

Opened20 km
  1. Jun 18, 2008Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Arachthos Bridge

The bridge is 1,036 m long and the longest on the motorway. Only the carriageway towards Kipoi opened on 8 April 2009; the other followed later in 2009 (Makedonia expected July, Greek Wikipedia gives the end of the year). Construction began in 2006.

Opened1 km
  1. 2006Construction start
  2. Apr 8, 2009Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Arachthos – Peristeri

Opened without the Peristeri bridge. That 900 m sub-section, from the Demati tunnel exit to bridge T9–T11, was finished last: its left carriageway opened on 10 May 2014, after which Egnatia Odos A.E. reported traffic running without restriction over the whole 670 km.

Opened9 km
  1. Jan 13, 2009Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Peristeri – MetsovoOpened9 km
  1. Feb 23, 2006Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Metsovo – Panagia

One bore each of the Metsovo and Malakasi A tunnels had carried traffic towards Ioannina since 1994, to national-road standard. The 2009 works added the second bores. The section has six tunnels, the longest being Metsovo at 3,550 m, and the Metsovitikos bridge, with piers 110 m high and a 235 m span.

Opened15 km
  1. Apr 8, 2009Opened
–
  • European UnionOperator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered part of the national contribution.
  • National budget
––
Panagia – Venetikos

Last section of the main axis, opened at a ceremony on the Venetikos bridge near Grevena on 30 May 2009. In 2003 Panagia – Grevena was outside the funded programme and alternative financing was being studied.

Opened31 km
  1. May 30, 2009Opened
–
  • European UnionOperator statement for the whole Western Macedonia section (Panagia – Polymylos, 110 km): national and EU funds through the 2nd CSF OP Accesses and Road Axes and the 3rd CSF OP Road Axes, Ports, Urban Development. No per-section split.
  • National budget
––
Venetikos – Grevena East

Grevena bypass.

Opened13 km
  1. Sep 7, 2007Opened
–
  • European UnionOperator statement for the whole Western Macedonia section (Panagia – Polymylos, 110 km): national and EU funds through the 2nd CSF OP Accesses and Road Axes and the 3rd CSF OP Road Axes, Ports, Urban Development. No per-section split.
  • National budget
––
Grevena East – Siatista East

Includes the Taxiarchis tunnel.

Opened18 km
  1. Apr 2001Opened
–
  • European UnionOperator statement for the whole Western Macedonia section (Panagia – Polymylos, 110 km): national and EU funds through the 2nd CSF OP Accesses and Road Axes and the 3rd CSF OP Road Axes, Ports, Urban Development. No per-section split.
  • National budget
––
Siatista East – KozaniOpened24 km
  1. Jul 2000Opened
–
  • European UnionOperator statement for the whole Western Macedonia section (Panagia – Polymylos, 110 km): national and EU funds through the 2nd CSF OP Accesses and Road Axes and the 3rd CSF OP Road Axes, Ports, Urban Development. No per-section split.
  • National budget
––
Kozani – PolymylosOpened22 km
  1. Mar 2001Opened
–
  • European UnionOperator statement for the whole Western Macedonia section (Panagia – Polymylos, 110 km): national and EU funds through the 2nd CSF OP Accesses and Road Axes and the 3rd CSF OP Road Axes, Ports, Urban Development. No per-section split.
  • National budget
––
Polymylos – Veria (Kastania bypass)

Crosses the Vermio mountains between Western and Central Macedonia, with twin-tube tunnels of 7 km per bore and bridges of 1.4 km per carriageway.

Opened26 km
  1. Dec 20, 2004Opened
  • Actual €485MVAT not included. Construction cost of the Kastania bypass as stated by Egnatia Odos A.E.; price year not stated.
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Veria – Kouloura

Upgrade of the existing road, completed as a national road in 1987, with a second carriageway added.

Opened9 km
  1. Sep 2001Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Kouloura – Kleidi

Contract 6.0: a second carriageway and central reserve, 25.14 km, beside the existing 13.5 m single carriageway from Kleidi to Kouloura, built 11/2000 to 06/2003. The builder gives the contract value as 15,164.46 million drachma (EUR 44.50 million at 340.75 GRD per euro), without a signing date or VAT treatment. Greek Wikipedia gives the section as 26 km.

Opened25 km
  1. Nov 2000Construction start
  2. Jun 2003Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
  • AEGEK – Techniki Olympiaki – EKTER – Evropaiki Techniki JVBuilder
–
Kalochori – Efkarpia

Thessaloniki outer ring road. Part of the six-lane Kleidi – Thessaloniki – Derveni stretch.

Opened15 km
  1. Aug 2004Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Efkarpia – Derveni

Part of the six-lane Kleidi – Thessaloniki – Derveni stretch.

Opened3 km
  1. Feb 2000Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Derveni – Nymfopetra

The Prime Minister opened 30 km of this section on 7 September 2003; the remaining 2 km, through the Derveni narrows, were due in December 2003. Greek Wikipedia's table gives 41 km.

Opened32 km
  1. Dec 2003Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Nymfopetra – Megali VolviOpened8 km
  1. Sep 2006Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Megali Volvi – Rentina

Completed the Central Macedonia section. Length from the ministry's announcement of the opening; Greek Wikipedia's table gives 3 km.

Opened15 km
  1. Sep 7, 2007Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Rentina – AsprovaltaOpened8 km
  1. Sep 2006Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Asprovalta – StrymonasOpened22 km
  1. 2005Opened
–
  • European UnionOperator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
  • LoanEIB loans covered the national contribution.
  • National budget
––
Strymonas – Agios Andreas

Runs 41 km on the inland alignment from the Strymonas river to the start of the Kavala bypass, replacing the coastal national road. Greek Wikipedia's table gives 9 km, the length of Arachthos – Chrysovitsa in the same 2009 announcement.

Opened41 km
  1. Jan 13, 2009Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Agios Andreas – Agios Syllas (Kavala bypass)

Construction of the Kavala bypass began in 1985 as part of national road 2; it was taken into the Egnatia axis in the 1990s, before completion.

Opened14 km
  1. 1985Construction start
  2. Aug 2000Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Agios Syllas – Aspri Ammos (Kavala bypass)

Construction of the Kavala bypass began in 1985 as part of national road 2; it was taken into the Egnatia axis in the 1990s, before completion.

Opened12 km
  1. 1985Construction start
  2. Apr 3, 2001Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Aspri Ammos – ChrysoupoliOpened19 km
  1. 2003Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Chrysoupoli – Vaniano

Crosses the Nestos wetlands, protected under the Ramsar Convention. Built under two contracts: Chrysoupoli – Paradeisos (10 km) opened in August 2007; the second contract, signed in May 2006, built the Nestos bridge and the last 7 km to Vaniano, which opened on 13 January 2009 and completed the Eastern Macedonia and Thrace section. In 2003 the Nestos crossing was outside the funded programme and alternative financing was being studied.

Opened17 km
  1. Jan 13, 2009Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Vaniano – Komotini WestOpened47 km
  1. Jun 30, 2002Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Komotini West – Mesti (Komotini bypass)Opened31 km
  1. Apr 2001Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Mesti – Makri

Built before 1994 as a national road; upgraded with a second carriageway.

Opened17 km
  1. 2008Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Makri – Alexandroupoli Industrial AreaOpened20 km
  1. 2002Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––
Alexandroupoli Industrial Area – Kipoi

Ends at the Kipoi customs post on the Turkish border.

Opened31 km
  1. Apr 2001Opened
–
  • European UnionOperator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • European Union
  • LoanEIB loans covered the national contribution.
  • National budget
––

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union891 km
    46 sections
    • Operator statement for the whole Epirus section (Igoumenitsa – Panagia, 123 km): national and EU funds (50%) under the 2nd and 3rd Community Support Frameworks (OP-RAPUD and the Epirus regional OP), and the Cohesion Fund. No per-section split.
    • Operator statement for the whole Western Macedonia section (Panagia – Polymylos, 110 km): national and EU funds through the 2nd CSF OP Accesses and Road Axes and the 3rd CSF OP Road Axes, Ports, Urban Development. No per-section split.
    • Operator statement for the whole Central Macedonia section (Polymylos – Strymonas, 191 km): the 3rd CSF OP Road Axes and the Cohesion Fund. No per-section split.
    • Operator statement for the whole Eastern Macedonia and Thrace section (Strymonas – Kipoi, 246 km): OPs of the 2nd and 3rd CSF (ERDF) and the Cohesion Fund. No per-section split.
  • National budget642 km
    36 sections
  • Loan534 km
    31 sections
    • EIB loans covered part of the national contribution.
    • EIB loans covered the national contribution.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Greek Wikipedia: Εγνατία Οδόςread Sep 28, 2026
  2. Egnatia Odos A.E.: The Construction of the Egnatia Motorwayread Sep 28, 2026 · archived copy
  3. Technika Chronika (TEE), Nov–Dec 2003: Egnatia Odos, presentation of Egnatia Odos A.E., the main axis and the vertical axesread Sep 28, 2026 · archived copy
  4. To Vima: Το όνειρο της Εγνατίας έγινε πραγματικότητα (7 June 2009)read Sep 28, 2026
  5. Makedonia: Εγνατία οδός: Παραδίδονται το τμήμα Παναγία-Μέτσοβο και η γέφυρα του Αράχθου (8 April 2009)read Sep 28, 2026
  6. ypodomes.com: Ολοκληρώθηκε και τυπικά η Εγνατία Οδός, στην κυκλοφορία η γέφυρα Περιστερίου (16 May 2014)read Sep 28, 2026 · archived copy
  7. AEGEK: Αυτοκινητόδρομος Εγνατία: Κουλούρα – Κλειδί 6.0 (project sheet)read Sep 28, 2026 · archived copy
  8. in.gr: Παραδόθηκε στην κυκλοφορία από τον πρωθυπουργό τμήμα της Εγνατίας Οδού (7 September 2003)read Sep 28, 2026
  9. capital.gr: ΥΠΕΧΩΔΕ: Παράδοση νέων τμημάτων Εγνατίας Οδού (7 September 2007)read Sep 28, 2026
  10. capital.gr: Δόθηκαν στην κυκλοφορία 70 χλμ. της Εγνατίας Οδού (13 January 2009)read Sep 28, 2026
  11. OpenStreetMap contributors (geometry, ODbL)read Sep 28, 2026