A52 Amvrakia Odos (Aktio – Amvrakia)
Branch of the A5 Ionia Odos in Aetolia-Acarnania, 48.5 km with 2+2 lanes, from the Aktio area at the Aktio – Preveza underwater tunnel to the Amvrakia interchange of the A5 near Amfilochia, by way of Vonitsa and Loutraki. It bypasses Vonitsa and Amfilochia and replaces a 62 km road. Construction began in July 2009 under the ESPA 2007–2013 programme and was due by 2012, but stalled. Aktio – Vonitsa opened on 24 April 2019, the Amfilochia bypass in July 2022, and the whole road was handed to traffic on 31 January 2024. METKA (Mytilineos) built the 2020–2024 contract. The drawn lots cover 46.4 km: the short stretch near Aktio that was last to open is not mapped as A52 in OpenStreetMap and is not drawn.
- Total length
- 47 km
- Open today
- 47 km
- Sections
- 3
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Aktio – Vonitsa First section to open, about ten years after construction began in July 2009. It starts about 1.5 km beyond the Aktio – Preveza underwater artery and ends near the Vonitsa (Palairos) interchange, completing half of the Vonitsa bypass. Ypodomes gave it as 15 km in 2019 and 14 km in 2022. The contractor of this earlier contract is not named in the sources found. | Opened | 15 km |
| – |
| – | – |
| Vonitsa – Loutraki (Drymos) Last section under construction in July 2022. Works at Drymos (km 27+000 to 27+850) held up the final handover into early 2024 because of ancient finds. The 30-month construction period is that of the whole end-2020 contract with the Ministry of Infrastructure and Transport, counted from signing. Ypodomes gives the budget of the whole Aktio – Amvrakia axis as EUR 160 million in 2024 and its initial cost as EUR 150 million in 2022. A small stretch near Aktio opened with this section and is not drawn. Length measured from OpenStreetMap geometry; the sources give no figure for this section. | Opened | 15 km |
| – |
|
| 30 mo total |
| Loutraki – Amvrakia (Amfilochia bypass) Amfilochia bypass through mountainous terrain, from the Loutraki interchange to the Amvrakia interchange with the A5, cutting about 15 km from the route through Amfilochia and Drymos. The 30-month construction period is that of the whole end-2020 contract, counted from signing. Delivered five months ahead of the contract deadline; first site work began in early spring 2021. Ypodomes dates its report 22 July 2022, so the opening is recorded to the month. An option for a link of about 400 m to the Ionia Odos (EUR 6.35 million) was activated and completed. The drawn line ends where the A52 meets the A5 and does not overlap lot kouvaras-amfilochia of the A5. | Opened | 17 km |
| – |
|
| 30 mo total |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union47 km3 sections
- The project began with ESPA 2007–2013 funds and is financed from ESPA 2014–2020 through the operational programme Transport Infrastructure, Environment and Sustainable Development.
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- RailwaysAthens – Thessaloniki railway modernisation (PATHE)Same contractor: METKA
- HighwaysA1 Motorway Athens – Thessaloniki – Evzonoi (PATHE)Same country and category
- HighwaysA2 Egnatia Odos (Igoumenitsa – Kipoi)Same country and category
- HighwaysA29 Siatista – Kastoria – KrystallopigiSame country and category
- HighwaysA5 Ionia Odos (Antirrio – Ioannina)Same country and category
- HighwaysA6 Attiki OdosSame country and category
Sources
- Wikipedia: A52 motorway (Greece)read Oct 5, 2026
- Ypodomes.com: Αμβρακία Οδός – Το προφίλ του νέου αυτοκινητόδρομου που μειώνει το Αθήνα – Λευκάδα κατά 45 λεπτά (31 January 2024)read Oct 5, 2026
- Ypodomes.com: Άκτιο-Αμβρακία: Στην κυκλοφορία η Παράκαμψη Αμφιλοχίας – Κατά 20 λεπτά πιο σύντομη η διαδρομή (22 July 2022)read Oct 5, 2026
- Ypodomes.com: Αμβρακία Οδός: Στην κυκλοφορία το τμήμα Άκτιο-Βόνιτσα (24 April 2019)read Oct 5, 2026 · archived copy
- Ypodomes.com: Western Greece's new Amvrakia Odos motorway will be completed in early 2024 (1 December 2023)read Oct 5, 2026
- OpenStreetMap contributors (geometry, ODbL)read Oct 5, 2026